Ranger's Corp. entered into a contract to construct a factory building. The contract price is $10M. cost information over life of the contract is as follows

5.16 Rangers Corp. entered into a contract to construct a factory building. The contract price is $10,000,000. Cost informati
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution:

Computation of % of completion, revenue recognition and Gross Profit - Rangers Corp.
Year Actual cost incurred (A) Total cost incurred till date (B) Total estimated Cost ( C ) % of completion (D) (B/C) Contract Price
(E)
Total Revenue to be recoganized (F) (E * D) Revenue for current period (G) Gross Profit (H) (G-A)
2014 $2,000,000 $2,000,000 $7,000,000 28.57% $10,000,000 $2,857,143 $2,857,143 $857,143
2015 $3,500,000 $5,500,000 $6,750,000 81.48% $10,000,000 $8,148,148 $5,291,005 $1,791,005
2016 $1,100,000 $6,600,000 $6,600,000 100.00% $10,000,000 $10,000,000 $1,851,852 $751,852
Computation of Gross Profit - Revenue on completion -Rangers Corp.
Year Actual cost incurred (A) Total cost incurred till date (B) Total estimated Cost ( C ) Contract Price
(D)
Gross Profit
2014 $2,000,000 $2,000,000 $7,000,000 $10,000,000 $0
2015 $3,500,000 $5,500,000 $6,750,000 $10,000,000 $0
2016 $1,100,000 $6,600,000 $6,600,000 $10,000,000 $3,400,000.00
Add a comment
Know the answer?
Add Answer to:
Ranger's Corp. entered into a contract to construct a factory building. The contract price is $10M....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Rangers Corp. entered into a contract to construct a factory building. The contract price is $10,000,000....

    Rangers Corp. entered into a contract to construct a factory building. The contract price is $10,000,000. Cost information over the life of the contract is as follows: Year 2014 2015 2016 Cost Incurred During Year $2,000,000 3,500,000 1.100.000 Estimated Cost to Complete $5,000,000 1,250,000 0 Rangers uses cost-to-cost to estimate the percentage complete on the contract. Provide the amount of gross profit recognized each year using two alternative revenue recognition methods. Year Completed Contract Method Percentage of Completion Method 2014...

  • 1.Hometown Construction Corp. entered into a long-term contract to build an office building for Outsider Corp....

    1.Hometown Construction Corp. entered into a long-term contract to build an office building for Outsider Corp. at a fixed contract price of $27.5 million on 6/15/2016. Construction of the building is completed on 12/15/2018. Hometown Construction expects the building to be completed in two and a half years and uses the Percentage of Completion Method (cost to cost approach) to account for the contract. Cost information related to the contract are as follows: 2016 2017 2018 Actual Construction costs incurred...

  • Fender period. Construction Company receives a contract to construct a building over a 3 year Information...

    Fender period. Construction Company receives a contract to construct a building over a 3 year Information relating to the performance of the contract is summarized as follows: 2015 2016 2017 S 16,000,000 Cumulative construction costs incurred to date Estimated costs to complete Billings during the year Cash collected during the year 6,000,000 8,000,000 6,000,000 3,000,000 8,000,000 7,000,000 4,000,000 5,000,000 Required: 1. How much is Fender Construction charging to build this athletic stadium? In other words, what is the contract price...

  • Accounting 305 Chapters 2 & 3 Homework Hometown Construction Corp. entered into a long-term contract to...

    Accounting 305 Chapters 2 & 3 Homework Hometown Construction Corp. entered into a long-term contract to build an office building for Outsider Corp. at a fixed contract price of $27.5 million on 6/15/2016. Construction of the building is completed on 12/15/2018. Hometown Construction expects the building to be completed in two and a half years and uses the Percentage of Completion Method (cost to cost approach) to account for the contract. Cost information related to the contract are as follows:...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,259,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,291,000 5,609,000 2,110,000 1,855,000 2022 $3,555,000 2,054,000 3,736,000 3,500,000 4,154,000 4,645,000 Westgate recognizes revenue over time according to percentage of completion. 3....

  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows:                                      2018                         2019                            2020 Cost incurred during the year    $ 2,291,000 $ 3,555,000 $ 2,259,400 Estimated costs to complete as of year-end         5,609,000 2,054,000 0 Billings during the year    2,110,000               3,736,000                   4,154,000 Cash collections during the year                            1,855,000    3,500,000 4,645,000 Westgate...

  • LO5-9 Concept Check: Revenue Recognition Over Time Robertson Construction entered into a contract to construct a...

    LO5-9 Concept Check: Revenue Recognition Over Time Robertson Construction entered into a contract to construct a tunnel for a fixed price of $12,000,000. Robertson recognizes revenue over time according to percentage of completion. Here are some facts: Estimated Additional Cost to Complete $6,000,000 2,000,000 Cost incurred $ 3,000,000 5,000,000 2,500,000 2021 2022 2023 How much revenue would Robertson recognize in 2021? a. $4,000,000 b. $5,000,000 $6,000,000 d. $12,000,000 LO5-9 Concept Check: Revenue Recognition Robertson Construction entered into a contract to...

  • In 2016, Pioneer Construction Company entered into a contract to construct a road for Denton County...

    In 2016, Pioneer Construction Company entered into a contract to construct a road for Denton County for S10,000,000. The road was completed in 2018. Information related to the contract is as follows: 2017 $2,610,000 S3,162,000 $2,230,800 2,028,000 2,100,000 3,672,000 4,228,000 1,850,000 3,000,000 5,150,000 2016 2018 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year 6,390,000 0 Cash collections during the year Pioneer recognizes revenue over time according to percentage of completion. Calculate the...

  • Excess Construction Corp. has a $16 million contract to construct a building. The company estimates $10.4...

    Excess Construction Corp. has a $16 million contract to construct a building. The company estimates $10.4 million in costs to construct the building and an expected gross profit of $5.6 million. During the current year, the company incurred S3,120,000 of costs on the contract Under the percentage-of-completion method, how much will Excess Construction Corp. report as revenue in the current year? $3,120,000 $5,600,000 $4,800,000 $10,400,000

  • LOS-9 Concept Check: Percentage Completion Robertson Construction entered into a contract to construct a tunnel for...

    LOS-9 Concept Check: Percentage Completion Robertson Construction entered into a contract to construct a tunnel for a fixed price of $12,000,000. Robertson recognizes revenue over time according to percentage of completion. Here are some facts: Estimated Additional Cost to Complete $6,000,000 6,500,000 Cost Incurred $ 3,000,000 500,000 6,500,000 2021 2022 2023 What is Robertson's percentage completion in 2021? a. b. c. d. 5% 35% 65% 100% LO5-9 Concept Check: Percentage Completion (2) Robertson Construction entered into a contract to construct...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT