Excess Construction Corp. has a $16 million contract to construct a building. The company estimates $10.4 million in costs to

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Percentage completion = 3120000/10400000 = 30%

Revenue report in Current year = 16000000*30% = $4800000

So answer is c)$4800000

Add a comment
Know the answer?
Add Answer to:
Excess Construction Corp. has a $16 million contract to construct a building. The company estimates $10.4...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Construction Solutions has a $20 million contract to construct a building. The company estimates a gross...

    Construction Solutions has a $20 million contract to construct a building. The company estimates a gross profit of $4 million. During the current year, the company incurred $2 million of costs on the contract. Under the percentage-of-completion method, how much will Construction Solutions report as revenue in the current year?

  • 1.Hometown Construction Corp. entered into a long-term contract to build an office building for Outsider Corp....

    1.Hometown Construction Corp. entered into a long-term contract to build an office building for Outsider Corp. at a fixed contract price of $27.5 million on 6/15/2016. Construction of the building is completed on 12/15/2018. Hometown Construction expects the building to be completed in two and a half years and uses the Percentage of Completion Method (cost to cost approach) to account for the contract. Cost information related to the contract are as follows: 2016 2017 2018 Actual Construction costs incurred...

  • A construction company entered into a fixed price contract to build an office building for $16...

    A construction company entered into a fixed price contract to build an office building for $16 milion. Construction costs incurred during the first year were $3 million and estimated costs to complete at the end of the year were $7 million. The company recognizes revenue over time according to percentage of completion How much revenue and gross profit or loss will appear in the company's income statement in the first year of the contract? (Enter your answer in whole dollars.)...

  • A construction company entered into a fixed-price contract to build an office building for $12 million....

    A construction company entered into a fixed-price contract to build an office building for $12 million. Construction costs incurred during the first year were $4 million and estimated costs to complete at the end of the year were $6 million. The company recognizes revenue over time according to percentage of completion. How much revenue and gross profit or loss will appear in the company's income statement in the first year of the contract? (Enter your answer in whole dollars.) Revenue

  • A construction company entered into a fixed-price contract to build an office building for $46 million....

    A construction company entered into a fixed-price contract to build an office building for $46 million. Construction costs incurred during the first year were $12 million and estimated costs to complete at the end of the year were $28 million. The company recognizes revenue over time according to percentage of completion. How much revenue and gross profit or loss will appear in the company's income statement in the first year of the contract? (Enter your answer in whole dollars.) Revenue

  • 1) A construction company entered into a fixed-price contract to build an office building for $20...

    1) A construction company entered into a fixed-price contract to build an office building for $20 million. Construction costs incurred during the first year were $6 million and estimated costs to complete at the end of the year were $9 million. The building was completed during the second year. Construction costs incurred during the second year were $10 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes...

  • A construction company entered into a fixed-price contract to build an office building for $20 million....

    A construction company entered into a fixed-price contract to build an office building for $20 million. Construction costs incurred during the first year were $6 million and estimated costs to complete at the end of the year were $9 million. The building was completed during the second year. Construction costs incurred during the second year were $10 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes revenue...

  • A construction company entered into a fixed-price contract to build an office building for $44 million....

    A construction company entered into a fixed-price contract to build an office building for $44 million. Construction costs incurred during the first year were $14 million and estimated costs to complete at the end of the year were $21 million. The building was completed during the second year. Construction costs incurred during the second year were $22 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes revenue...

  • Accounting 305 Chapters 2 & 3 Homework Hometown Construction Corp. entered into a long-term contract to...

    Accounting 305 Chapters 2 & 3 Homework Hometown Construction Corp. entered into a long-term contract to build an office building for Outsider Corp. at a fixed contract price of $27.5 million on 6/15/2016. Construction of the building is completed on 12/15/2018. Hometown Construction expects the building to be completed in two and a half years and uses the Percentage of Completion Method (cost to cost approach) to account for the contract. Cost information related to the contract are as follows:...

  • A construction company entered into a fixed-price contract to build an office building for $30 million....

    A construction company entered into a fixed-price contract to build an office building for $30 million. Construction costs incurred during the first year were $10 million and estimated costs to complete at the end of the year were $15 million. During the first year the company billed its customer $11 million, of which $3 million was collected before year-end. What would appear in the year-end balance sheet related to this contract using the percentage-of-completion method? (Enter you answers in whole...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT