Question

Construction Solutions has a $20 million contract to construct a building. The company estimates a gross...

Construction Solutions has a $20 million contract to construct a building. The company estimates a gross profit of $4 million. During the current year, the company incurred $2 million of costs on the contract.

Under the percentage-of-completion method, how much will Construction Solutions report as revenue in the current year?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

% of completion = Costs incurred / Estimated cost of the project

Estimated project cost = 20 million - 4 Million = 16 million

% of completion = 2 / 16 = 12.50%

Revenue to be recognized in current year = 20 Million * 12.50%

= 2.50 Million

or 2500000

Add a comment
Know the answer?
Add Answer to:
Construction Solutions has a $20 million contract to construct a building. The company estimates a gross...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Excess Construction Corp. has a $16 million contract to construct a building. The company estimates $10.4...

    Excess Construction Corp. has a $16 million contract to construct a building. The company estimates $10.4 million in costs to construct the building and an expected gross profit of $5.6 million. During the current year, the company incurred S3,120,000 of costs on the contract Under the percentage-of-completion method, how much will Excess Construction Corp. report as revenue in the current year? $3,120,000 $5,600,000 $4,800,000 $10,400,000

  • 1) A construction company entered into a fixed-price contract to build an office building for $20...

    1) A construction company entered into a fixed-price contract to build an office building for $20 million. Construction costs incurred during the first year were $6 million and estimated costs to complete at the end of the year were $9 million. The building was completed during the second year. Construction costs incurred during the second year were $10 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes...

  • A construction company entered into a fixed-price contract to build an office building for $20 million....

    A construction company entered into a fixed-price contract to build an office building for $20 million. Construction costs incurred during the first year were $6 million and estimated costs to complete at the end of the year were $9 million. The building was completed during the second year. Construction costs incurred during the second year were $10 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes revenue...

  • A construction company entered into a fixed-price contract to build an office building for $44 million....

    A construction company entered into a fixed-price contract to build an office building for $44 million. Construction costs incurred during the first year were $14 million and estimated costs to complete at the end of the year were $21 million. The building was completed during the second year. Construction costs incurred during the second year were $22 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes revenue...

  • A construction company entered into a fixed-price contract to build an office building for $12 million....

    A construction company entered into a fixed-price contract to build an office building for $12 million. Construction costs incurred during the first year were $4 million and estimated costs to complete at the end of the year were $6 million. The company recognizes revenue over time according to percentage of completion. How much revenue and gross profit or loss will appear in the company's income statement in the first year of the contract? (Enter your answer in whole dollars.) Revenue

  • A construction company entered into a fixed-price contract to build an office building for $46 million....

    A construction company entered into a fixed-price contract to build an office building for $46 million. Construction costs incurred during the first year were $12 million and estimated costs to complete at the end of the year were $28 million. The company recognizes revenue over time according to percentage of completion. How much revenue and gross profit or loss will appear in the company's income statement in the first year of the contract? (Enter your answer in whole dollars.) Revenue

  • A construction company entered into a fixed-price contract to build an office building for $48 million....

    A construction company entered into a fixed-price contract to build an office building for $48 million. Construction costs incurred during the first year were $18 million and estimated costs to complete at the end of the year were $27 million. The building was completed during the second year. Construction costs incurred during the second year were $28 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes revenue...

  • A construction company entered into a fixed-price contract to build an office building for $10 million....

    A construction company entered into a fixed-price contract to build an office building for $10 million. Construction costs incurred during the first year were $2 million and estimated costs to complete at the end of the year were $3 million. The building was completed during the second year. Construction costs incurred during the second year were $4 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes revenue...

  • A construction company entered into a fixed price contract to build an office building for $46...

    A construction company entered into a fixed price contract to build an office building for $46 million. Construction costs incurred during the first year were $12 million and estimated costs to complete at the end of the year were $28 million. The company recognizes revenue over time according to percentage of completion. How much revenue and gross profit or loss will appear in the company's income statement in the first year of the contract? (Enter your answer in whole dollars.)...

  • A construction company entered into a fixed price contract to build an office building for $16...

    A construction company entered into a fixed price contract to build an office building for $16 milion. Construction costs incurred during the first year were $3 million and estimated costs to complete at the end of the year were $7 million. The company recognizes revenue over time according to percentage of completion How much revenue and gross profit or loss will appear in the company's income statement in the first year of the contract? (Enter your answer in whole dollars.)...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT