If it is helpful, please rate the answer and if any doubt arises let me know
Assets: | |||
Accounts receivables | = | $ 8,000,000 | |
Costs plus profit in excess of billings | = | $ 1,000,000 | |
Workings: | |||
Amount billed | = | $ 1,10,00,000 | |
Less: | Amount collected | = | $ -30,00,000 |
Accounts receivables | = | $ 80,00,000 | |
Total Revenue | = | $ 3,00,00,000 | |
Less: | Total Estimated cost | = | $ -2,50,00,000 |
Total Estimated Profit | = | $ 50,00,000 | |
Percentage of completion in first year ($10 million / $25 million) | = | 40% | |
Profit recognized in first year ($50 million X 40%) | = | $ 20,00,000 | |
Cost plus profit ($10 million + $2 million) | = | $ 1,20,00,000 | |
Less: | Amount billed | = | $ 1,10,00,000 |
Cost plus profit in excess of billings | = | $ 10,00,000 |
I actually hate people that put 2 zeros in the middle comma set. Fucking die honestly, that is standard literally nowhere
A construction company entered into a fixed-price contract to build an office building for $30 million....
A construction company entered into a fixed price contract to build an office building for $44 million. Construction costs incurred during the first year were $14 million and estimated costs to complete at the end of the year were $21 million. During the first year the company billed its customer $16 million, of which $10 million was collected before year-end. What would appear in the year-end balance sheet related to this contract using the percentage-of-completion method? (Enter your answers in...
A construction company entered into a fixed-price contract to build an office building for $20 million. Construction costs incurred during the first year were $6 million and estimated costs to complete at the end of the year were $9 million. The building was completed during the second year. Construction costs incurred during the second year were $10 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes revenue...
A construction company entered into a fixed-price contract to build an office building for $44 million. Construction costs incurred during the first year were $14 million and estimated costs to complete at the end of the year were $21 million. The building was completed during the second year. Construction costs incurred during the second year were $22 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes revenue...
A construction company entered into a fixed price contract to build an office building for $16 milion. Construction costs incurred during the first year were $3 million and estimated costs to complete at the end of the year were $7 million. The company recognizes revenue over time according to percentage of completion How much revenue and gross profit or loss will appear in the company's income statement in the first year of the contract? (Enter your answer in whole dollars.)...
A construction company entered into a fixed-price contract to build an office building for $12 million. Construction costs incurred during the first year were $4 million and estimated costs to complete at the end of the year were $6 million. The company recognizes revenue over time according to percentage of completion. How much revenue and gross profit or loss will appear in the company's income statement in the first year of the contract? (Enter your answer in whole dollars.) Revenue
A construction company entered into a fixed-price contract to build an office building for $46 million. Construction costs incurred during the first year were $12 million and estimated costs to complete at the end of the year were $28 million. The company recognizes revenue over time according to percentage of completion. How much revenue and gross profit or loss will appear in the company's income statement in the first year of the contract? (Enter your answer in whole dollars.) Revenue
A construction company entered into a fixed price contract to build an office building for $46 million. Construction costs incurred during the first year were $12 million and estimated costs to complete at the end of the year were $28 million. The company recognizes revenue over time according to percentage of completion. How much revenue and gross profit or loss will appear in the company's income statement in the first year of the contract? (Enter your answer in whole dollars.)...
1) A construction company entered into a fixed-price contract to build an office building for $20 million. Construction costs incurred during the first year were $6 million and estimated costs to complete at the end of the year were $9 million. The building was completed during the second year. Construction costs incurred during the second year were $10 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes...
A construction company entered into a fixed-price contract to build an office building for $48 million. Construction costs incurred during the first year were $18 million and estimated costs to complete at the end of the year were $27 million. The building was completed during the second year. Construction costs incurred during the second year were $28 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes revenue...
A construction company entered into a fixed-price contract to build an office building for $10 million. Construction costs incurred during the first year were $2 million and estimated costs to complete at the end of the year were $3 million. The building was completed during the second year. Construction costs incurred during the second year were $4 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes revenue...