Question

Rangers Corp. entered into a contract to construct a factory building. The contract price is $10,000,000. Cost information ov
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution

Year Percentage of completion Method Completed contract Method
2014 $      857,143
2015 $   1,791,005
2016 $      751,852 $ 3,400,000

Working

Percentage of completion method

Working 2014 2015 2016
A Contract Price $ 10,000,000 $ 10,000,000 $ 10,000,000
B Cost Incurred to Date $ 2,000,000 $ 5,500,000 $ 6,600,000
C Estimated cost yet to be incurred to complete the contract $ 5,000,000 $ 1,250,000 $ 0
D = B+C Total Cost $ 7,000,000 $ 6,750,000 $ 6,600,000
E = (D/B) x 100 % of Completion 29% 81% 100%
F = A x E Revenue to date $ 2,857,143 $ 8,148,148 $ 10,000,000
G Revenue of Previous year $ 0 $ 2,857,143 $ 8,148,148
H = F - G Net Revenue this year $ 2,857,143 $ 5,291,005 $ 1,851,852
I Cost to date $ 2,000,000 $ 5,500,000 $ 6,600,000
J Cost to date of previous year $ 0 $ 2,000,000 $ 5,500,000
K = I - J Net Cost for the year $ 2,000,000 $ 3,500,000 $ 1,100,000
L = H - K Gross Profits $ 857,143 $ 1,791,005 $ 751,852

.

In completed contract method all the profit will be recorded in the year the contract is completed. Gross profit to be recorded in 2016 will be (10,000000 minus all cost in three years)

Add a comment
Know the answer?
Add Answer to:
Rangers Corp. entered into a contract to construct a factory building. The contract price is $10,000,000....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Ranger's Corp. entered into a contract to construct a factory building. The contract price is $10M....

    Ranger's Corp. entered into a contract to construct a factory building. The contract price is $10M. cost information over life of the contract is as follows 5.16 Rangers Corp. entered into a contract to construct a factory building. The contract price is $10,000,000. Cost information over the life of the contract is as follows: Year 2014 2015 2016 Cost Incurred During Year $2,000,000 3,500,000 1,100,000 Estimated Cost to Complete $5,000,000 1.250.000 Rangers uses cost-to-cost to estimate the percentage complete on...

  • 1.Hometown Construction Corp. entered into a long-term contract to build an office building for Outsider Corp....

    1.Hometown Construction Corp. entered into a long-term contract to build an office building for Outsider Corp. at a fixed contract price of $27.5 million on 6/15/2016. Construction of the building is completed on 12/15/2018. Hometown Construction expects the building to be completed in two and a half years and uses the Percentage of Completion Method (cost to cost approach) to account for the contract. Cost information related to the contract are as follows: 2016 2017 2018 Actual Construction costs incurred...

  • Fender period. Construction Company receives a contract to construct a building over a 3 year Information...

    Fender period. Construction Company receives a contract to construct a building over a 3 year Information relating to the performance of the contract is summarized as follows: 2015 2016 2017 S 16,000,000 Cumulative construction costs incurred to date Estimated costs to complete Billings during the year Cash collected during the year 6,000,000 8,000,000 6,000,000 3,000,000 8,000,000 7,000,000 4,000,000 5,000,000 Required: 1. How much is Fender Construction charging to build this athletic stadium? In other words, what is the contract price...

  • LO5-9 Concept Check: Revenue Recognition Over Time Robertson Construction entered into a contract to construct a...

    LO5-9 Concept Check: Revenue Recognition Over Time Robertson Construction entered into a contract to construct a tunnel for a fixed price of $12,000,000. Robertson recognizes revenue over time according to percentage of completion. Here are some facts: Estimated Additional Cost to Complete $6,000,000 2,000,000 Cost incurred $ 3,000,000 5,000,000 2,500,000 2021 2022 2023 How much revenue would Robertson recognize in 2021? a. $4,000,000 b. $5,000,000 $6,000,000 d. $12,000,000 LO5-9 Concept Check: Revenue Recognition Robertson Construction entered into a contract to...

  • Accounting 305 Chapters 2 & 3 Homework Hometown Construction Corp. entered into a long-term contract to...

    Accounting 305 Chapters 2 & 3 Homework Hometown Construction Corp. entered into a long-term contract to build an office building for Outsider Corp. at a fixed contract price of $27.5 million on 6/15/2016. Construction of the building is completed on 12/15/2018. Hometown Construction expects the building to be completed in two and a half years and uses the Percentage of Completion Method (cost to cost approach) to account for the contract. Cost information related to the contract are as follows:...

  • 22) Noah Construction Company is building a large complex for a contract price of $5,000,000 This...

    22) Noah Construction Company is building a large complex for a contract price of $5,000,000 This is a three-year project and the requirements for recognizing revenue over time are met. The total estimated cost of the project is $4,000,000 and the following information is available: K$ in thousands) Costs incurred Estimated completion costs Billings Cash collected Year 1 $ 1,000 $ 3,000 $ 750 $ 500 Year 2 $ 1,500 $ 1,500 $ 1,750 $ 1,500 Year 3 $ 1,250...

  • Ex. 18-127-Percentage-of-completion and completed-contract methods. On February 1, 2012, Marsh Contractors agreed to construct a building...

    Ex. 18-127-Percentage-of-completion and completed-contract methods. On February 1, 2012, Marsh Contractors agreed to construct a building at a contract price of $5,400,000. Marsh estimated total construction costs would be $4,000,000 and the project would be finished in 2014. Information relating to the costs and billings for this contract is as follows: 2014 2012 $1,500,000 2,500,000 2,200,000 2,000,000 2013 $4,600,000 $2,640,000 1,760,000 4,000,000 3,500,000 Total costs incurred to date Estimated costs to complete Customer billings to date Collections to date -0-...

  • Question Three: In 2016, the Westgate Construction Company entered into a contract to construct a road...

    Question Three: In 2016, the Westgate Construction Company entered into a contract to construct a road for Santa Clara Countyfor $10,000,000. The road was completed in 201 contract is as follows: 8. Information related to the 2018 2016 2,400,000 3,600,000 2,200,00 5,600,000 2,000,000 4,000,000 4,000,000 ,800,000 3,600,000 4,600,000 2017 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2,000,000 Westgate recognizes revenue over time according to percentage of...

  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows:                                      2018                         2019                            2020 Cost incurred during the year    $ 2,291,000 $ 3,555,000 $ 2,259,400 Estimated costs to complete as of year-end         5,609,000 2,054,000 0 Billings during the year    2,110,000               3,736,000                   4,154,000 Cash collections during the year                            1,855,000    3,500,000 4,645,000 Westgate...

  • At the beginning of 2013, the Harding Construction Company received a contract to build an office...

    At the beginning of 2013, the Harding Construction Company received a contract to build an office building for $10 million. Harding will construct the building according to specifications provided by the buyer, and the project is estimated to take three years to complete. According to the contract, Harding will bill the buyer in installments over the construction period according to a prearranged schedule. Information related to the contract is as follows: 2013 2014 2015 Cost incurred during the year $2,300,000...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT