oogle Chrome ent/1/OPME%20Study%20Guide%20SP5%20-%202019.pdf 2. Case Study A company has the following demand forecast next y

How many employees will be needed during demand of 610 units in period 5 if no overtime production is to be scheduled

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Standard Hours required to produce one unit = 20 hours

No. of units to be produced in period -5 (i.e. Demand of Period-5) = 610 units

Total Hours required to produce 610 units in period-5 = No. of units to be produced in period -5 * Standard Hours required to produce one unit

= 610*20

= 12,200 hours.

.

.

No of hours worked by each employee per month = 160 regular working hours.

Therefore, No of hours worked by each employee in each bimonth period = 160*2 = 320 hours

.

.

No. of employees needed during demand of 610 units in period 5 if no overtime production is to be scheduled = Total Hours required to produce 610 units in period-5/ No of hours worked by each employee in each bimonth period

= 12,200/320

= 38.125

= 39 (Rounded up as per rule -3 – since in period-5 no, of employees is increasing as demand increases in period-5 as compared to period-4)

Add a comment
Know the answer?
Add Answer to:
How many employees will be needed during demand of 610 units in period 5 if no...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Kangaroo P/L has the following demand forecast next year, expressed in six bimonthly (2-month) periods: Period...

    Kangaroo P/L has the following demand forecast next year, expressed in six bimonthly (2-month) periods: Period Forecast Demand (Standard U nits of Work) 1 400 2 380 3 470 4 530 5 610 6 500 The following costing data have been obtained: Each employee works 176 regular working hours per month Each unit requires 20 standard hours to produce The labour costs are $6 per normal hour and $9 per overtime hour It costs $3 per month to hold an...

  • Here is an operations planning case analysis. You are expected to do the following questions and...

    Here is an operations planning case analysis. You are expected to do the following questions and submit them for marking at the end of the semester via utsonline and in hard copy to your tutor in week 10. A company has the following demand forecast next year, expressed in six bimonthly periods: Forecast Demand: Period 1 = 4,500 units Period 4 = 6,500 units Period 2 = 3,000 units Period 5 = 5,100 units Period 3 = 4,800 units Period...

  • Problem 8-8 Plan production for a four-month period: February through May. For February and March, you...

    Problem 8-8 Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May. However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply,...

  • Plan production for a four-month period: February through May. For February and March, you should produce...

    Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May. However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply, then backorders...

  • Plan production for a four-month period: February through May. For February and March, you should produce...

    Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May. However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply, then backorders...

  • Calculate Payroll Breakin Away Company has three employees—a consultant, a computer programmer, and an administrator. The...

    Calculate Payroll Breakin Away Company has three employees—a consultant, a computer programmer, and an administrator. The following payroll information is available for each employee: Consultant Computer Programmer Administrator Regular earnings rate $4,000 per week $60 per hour $50 per hour Overtime earnings rate* Not applicable 1.5 times hourly rate 2 times hourly rate Number of withholding allowances 2 1 2 *For hourly employees, overtime is paid for hours worked in excess of 40 hours per week. For the current pay...

  • Problem 8-7 Develop a production plan and calculate the annual cost for a firm whose demand...

    Problem 8-7 Develop a production plan and calculate the annual cost for a firm whose demand forecast is fall, 10,700; winter, 8,300; spring, 6,900; summer, 12,700. Inventory at the beginning of fall is 535 units. At the beginning of fall you currently have 35 workers, but you plan to hire temporary workers at the beginning of summer and lay them off at the end of summer. In addition, you have negotiated with the union an option to use the regular...

  • Develop a production plan and calculate the annual cost for a firm whose demand forecast is...

    Develop a production plan and calculate the annual cost for a firm whose demand forecast is fall, 11,000; winter, 7,700; spring, 6,700; summer, 13,000. Inventory at the beginning of fall is 550 units. At the beginning of fall you currently have 30 workers, but you plan to hire temporary workers at the beginning of summer and lay them off at the end of summer. In addition, you have negotiated with the union an option to use the regular workforce on...

  • Calculate Payroll Breakin Away Company has three employees-a consultant, a computer programmer, and an administrator. The...

    Calculate Payroll Breakin Away Company has three employees-a consultant, a computer programmer, and an administrator. The following payroll information is available for each employee: Consultant Computer Programmer Administrator Regular earnings rate $2,910 per week $36 per hour $46 per hour Overtime earnings rate Not applicable 1.5 times hourly rate 2 times hourly rate Number of withholding allowances 3 2 1 For the current pay period, the computer programmer worked 60 hours and the administrator worked 50 hours. The federal income...

  • A manager receives a forecast for next year. Demand is projected to be 528 units for...

    A manager receives a forecast for next year. Demand is projected to be 528 units for the first half of the year and 1,020 units for the second half. The monthly holding cost is $2 per unit, and it costs an estimated $55 to process an order. a. Assuming that monthly demand will be level during each of the six-month periods covered by the forecast (e.g., 88 per month for each of the first six months), determine an order size...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT