Question

Ruiz Foods makes energy bars using a traditional manufacturing process. Raw materials are stored in inventory...

Ruiz Foods makes energy bars using a traditional manufacturing process. Raw materials are stored in inventory and then moved into production. Work in process inventory is moved across the company’s three separate departments. The information below (in the Traditional column) is available for a recent order. If the company adopts lean manufacturing, management believes both move time and wait time can be reduced, as shown in the Lean column.

Activity Traditional Lean
Process time 33 hours 33 hours
Inspection time 5 hours 5 hours
Move time 6 hours 4 hours
Wait time 3 hours 1 hour


Required
1. Compute the total amount of non-value-added time under the traditional manufacturing process.
2. Compute cycle efficiency under the traditional manufacturing process. (Round your answer to 2 decimal places.)
3. Compute the total amount of non-value-added time under the proposed lean manufacturing process.
4. Compute cycle efficiency under the proposed lean manufacturing process. (Round your answer to 2 decimal places.)
5. Would the proposed lean approach improve cycle efficiency?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer to Question 1, 2 and 3:

Question 1 Non Valued Added Time = Inspection time + Move time + Wait time Non Valued Added Time = 5+ 6+3 Non Valued Added Ti

Answer to Question 4 and 5:

Question 4 Numerator Value Added Time Manufacturing Cycle Efficiency Manufacturing Denominator Cycle Efficiency Manufacturing

Add a comment
Know the answer?
Add Answer to:
Ruiz Foods makes energy bars using a traditional manufacturing process. Raw materials are stored in inventory...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Ruiz Foods makes energy bars using a traditional manufacturing process. Raw materials are stored in inventory...

    Ruiz Foods makes energy bars using a traditional manufacturing process. Raw materials are stored in inventory and then moved into production. Work in process inventory is moved across the company's three separate departments. The information below (in the Traditional column) is available for a recent order. If the company adopts lean manufacturing, management believes both move time and wait time can be reduced, as shown in the Lean column. Activity Traditional Lean Process time Inspection time Move time 20 hours...

  • Check my w Inspection time Wait time (from order to start of production) Process time Move...

    Check my w Inspection time Wait time (from order to start of production) Process time Move time Queue time 0.5 days 15.4 days 3.2 days 0.9 days 4.3 days Required: 1. Compute the throughput time. (Round your answer to 1 decimal place.) 2. Compute the manufacturing cycle efficiency (MCE) for the quarter. (Round your percentage answer to nearest whole percent.) 3. What percentage of the throughput time was spent in non-value-added activities? (Round your percentage answer to nearest whole percent.)...

  • The following information is from a manufacturing company. Process time Inspection time Move time Wait time...

    The following information is from a manufacturing company. Process time Inspection time Move time Wait time 20.0 minutes 3.0 minutes 8.6 minutes 42.6 minutes Required: a. Compute manufacturing cycle time b. Compute manufacturing cycle efficiency Complete this question by entering your answers in the tabs below. Required A Required B Compute manufacturing cycle time. (Round your answers to 1 decimal place.) Manufacturing cycle time Time Manufacturing cycle time The following information is from a manufacturing company. Process time Inspection time...

  • The following information is from a manufacturing company. Process time Inspection time Move time wait time...

    The following information is from a manufacturing company. Process time Inspection time Move time wait time 19.0 minutes 2.0 minutes 6.6 minutes 43.8 minutes Required: a. Compute manufacturing cycle time - b. Compute manufacturing cycle efficiency Complete this question by entering your answers in the tabs below. Required A Required B Compute manufacturing cycle time. (Round your answers to 1 decimal place) Manufacturing cycle time Time Manufacturing cycle time Required B > Complete this question by entering your answers in...

  • Exercise 11-3 Measures of Internal Business Process Performance [LO11-3] Management of Mittel Rhein AG of Köln,...

    Exercise 11-3 Measures of Internal Business Process Performance [LO11-3] Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time Wait time (from order to start of production) Process time Move time Queue time 0.7 days 15.2 days 3.2 days 0.7 days 4.0 days Required:...

  • The following information is from a manufacturing company. Process time Inspection time Move time Wait time 17.0 minute...

    The following information is from a manufacturing company. Process time Inspection time Move time Wait time 17.0 minutes 2.0 minutes 7.0 minutes 41.4 minutes Required: a. Compute manufacturing cycle time b. Compute manufacturing cycle efficiency Complete this question by entering your answers in the tabs below. Required A Required B Compute manufacturing cycle time. (Round your answers to 1 decimal place.) Manufacturing cycle time Time Manufacturing cycle time 0.0 Required: a. Compute manufacturing cycle time b. Compute manufacturing cycle efficiency...

  • Compute Lead Time Jackson Fabricators Inc. machines metal parts for the automotive industry. Under the traditional...

    Compute Lead Time Jackson Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 40 parts. A part requires 6 minutes in milling and 8 minutes in finishing. The move time between the two operations for a complete batch is 5 minutes. Under the lean philosophy, the part is produced in a cell that includes both the milling and...

  • Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between w...

    Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during...

  • EXERCISE 11–3 Measures of Internal Business Process Performance [LO11–3] Guided Example 11-3 Management of Mittel Rhein...

    EXERCISE 11–3 Measures of Internal Business Process Performance [LO11–3] Guided Example 11-3 Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Compute the throughput time. Compute the manufacturing cycle efficiency (MCE) for the quarter. What percentage of the throughput time was spent in non–value-added activities?...

  • Lipex, Ltd., of Birmingham, England, is interested in cutting the amount of time between when a...

    Lipex, Ltd., of Birmingham, England, is interested in cutting the amount of time between when a customer places an order and when the order is completed. For the first quarter of the year, the following data were reported: Inspection time Process time Wait time Queue time Move time 0.5 days 2.7 days 15.9 days 3.7 days 1.1 days Required: 1. Compute the throughput time. (Round your intermediate calculations to 1 decimal place.) Throughput time days 2. Compute the manufacturing cycle...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT