Ruiz Foods makes energy bars using a traditional manufacturing
process. Raw materials are stored in inventory and then moved into
production. Work in process inventory is moved across the company’s
three separate departments. The information below (in the
Traditional column) is available for a recent order. If the company
adopts lean manufacturing, management believes both move time and
wait time can be reduced, as shown in the Lean column.
Activity | Traditional | Lean | ||||
Process time | 33 | hours | 33 | hours | ||
Inspection time | 5 | hours | 5 | hours | ||
Move time | 6 | hours | 4 | hours | ||
Wait time | 3 | hours | 1 | hour | ||
Required
1. Compute the total amount of non-value-added
time under the traditional manufacturing process.
2. Compute cycle efficiency under the traditional
manufacturing process. (Round your answer to 2 decimal
places.)
3. Compute the total amount of non-value-added
time under the proposed lean manufacturing process.
4. Compute cycle efficiency under the proposed
lean manufacturing process. (Round your answer to 2 decimal
places.)
5. Would the proposed lean approach improve cycle
efficiency?
Answer to Question 1, 2 and 3:
Answer to Question 4 and 5:
Ruiz Foods makes energy bars using a traditional manufacturing process. Raw materials are stored in inventory...
Ruiz Foods makes energy bars using a traditional manufacturing process. Raw materials are stored in inventory and then moved into production. Work in process inventory is moved across the company's three separate departments. The information below (in the Traditional column) is available for a recent order. If the company adopts lean manufacturing, management believes both move time and wait time can be reduced, as shown in the Lean column. Activity Traditional Lean Process time Inspection time Move time 20 hours...
Check my w Inspection time Wait time (from order to start of production) Process time Move time Queue time 0.5 days 15.4 days 3.2 days 0.9 days 4.3 days Required: 1. Compute the throughput time. (Round your answer to 1 decimal place.) 2. Compute the manufacturing cycle efficiency (MCE) for the quarter. (Round your percentage answer to nearest whole percent.) 3. What percentage of the throughput time was spent in non-value-added activities? (Round your percentage answer to nearest whole percent.)...
The following information is from a manufacturing company. Process time Inspection time Move time Wait time 20.0 minutes 3.0 minutes 8.6 minutes 42.6 minutes Required: a. Compute manufacturing cycle time b. Compute manufacturing cycle efficiency Complete this question by entering your answers in the tabs below. Required A Required B Compute manufacturing cycle time. (Round your answers to 1 decimal place.) Manufacturing cycle time Time Manufacturing cycle time The following information is from a manufacturing company. Process time Inspection time...
The following information is from a manufacturing company. Process time Inspection time Move time wait time 19.0 minutes 2.0 minutes 6.6 minutes 43.8 minutes Required: a. Compute manufacturing cycle time - b. Compute manufacturing cycle efficiency Complete this question by entering your answers in the tabs below. Required A Required B Compute manufacturing cycle time. (Round your answers to 1 decimal place) Manufacturing cycle time Time Manufacturing cycle time Required B > Complete this question by entering your answers in...
Exercise 11-3 Measures of Internal Business Process Performance [LO11-3] Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time Wait time (from order to start of production) Process time Move time Queue time 0.7 days 15.2 days 3.2 days 0.7 days 4.0 days Required:...
The following information is from a manufacturing company. Process time Inspection time Move time Wait time 17.0 minutes 2.0 minutes 7.0 minutes 41.4 minutes Required: a. Compute manufacturing cycle time b. Compute manufacturing cycle efficiency Complete this question by entering your answers in the tabs below. Required A Required B Compute manufacturing cycle time. (Round your answers to 1 decimal place.) Manufacturing cycle time Time Manufacturing cycle time 0.0 Required: a. Compute manufacturing cycle time b. Compute manufacturing cycle efficiency...
Compute Lead Time Jackson Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 40 parts. A part requires 6 minutes in milling and 8 minutes in finishing. The move time between the two operations for a complete batch is 5 minutes. Under the lean philosophy, the part is produced in a cell that includes both the milling and...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during...
EXERCISE 11–3 Measures of Internal Business Process Performance [LO11–3] Guided Example 11-3 Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Compute the throughput time. Compute the manufacturing cycle efficiency (MCE) for the quarter. What percentage of the throughput time was spent in non–value-added activities?...
Lipex, Ltd., of Birmingham, England, is interested in cutting the amount of time between when a customer places an order and when the order is completed. For the first quarter of the year, the following data were reported: Inspection time Process time Wait time Queue time Move time 0.5 days 2.7 days 15.9 days 3.7 days 1.1 days Required: 1. Compute the throughput time. (Round your intermediate calculations to 1 decimal place.) Throughput time days 2. Compute the manufacturing cycle...