A | ||||
Manufacturing Cycle Time | ||||
Time | ||||
Process time | 19.0 | |||
Inspection time | 2.0 | |||
Move time | 6.6 | |||
Wait time | 43.8 | |||
Manufacturing Cycle Time | 71.4 | minutes | ||
B | ||||
Choose Numerator: | / | Choose Denominator: | = | Manufacturing Cycle Efficiency |
Process Time | / | Manufacturing Cycle Time | = | Manufacturing Cycle Efficiency |
19.0 | / | 71.4 | = | 0.27 |
Percentage spent on value added activities | 27% | |||
Percentage spent on non value added activities | 73% |
The following information is from a manufacturing company. Process time Inspection time Move time wait time...
The following information is from a manufacturing company. Process time Inspection time Move time Wait time 20.0 minutes 3.0 minutes 8.6 minutes 42.6 minutes Required: a. Compute manufacturing cycle time b. Compute manufacturing cycle efficiency Complete this question by entering your answers in the tabs below. Required A Required B Compute manufacturing cycle time. (Round your answers to 1 decimal place.) Manufacturing cycle time Time Manufacturing cycle time The following information is from a manufacturing company. Process time Inspection time...
The following information is from a manufacturing company. Process time Inspection time Move time Wait time 17.0 minutes 2.0 minutes 7.0 minutes 41.4 minutes Required: a. Compute manufacturing cycle time b. Compute manufacturing cycle efficiency Complete this question by entering your answers in the tabs below. Required A Required B Compute manufacturing cycle time. (Round your answers to 1 decimal place.) Manufacturing cycle time Time Manufacturing cycle time 0.0 Required: a. Compute manufacturing cycle time b. Compute manufacturing cycle efficiency...
Process time Inspection time Move time Wait time 15.0 minutes 2.0 minutes 6.4 minutes 36.6 minutes Required a. Compute manufacturing cycle time b. Compute manufacturing cycle efficiency Complete this question by entering your answers in the tabs below Required A Required B Compute manufacturing cycle time. (Round your answers to 1 decimal place.) Manufacturing cycle time Time 15.0 minutes 2.0 minutes 6.4 minutes 36.6 minutes rocess time Inspection time Move time ait time Manufacturing cycle time 60.0 minutes
Check my w Inspection time Wait time (from order to start of production) Process time Move time Queue time 0.5 days 15.4 days 3.2 days 0.9 days 4.3 days Required: 1. Compute the throughput time. (Round your answer to 1 decimal place.) 2. Compute the manufacturing cycle efficiency (MCE) for the quarter. (Round your percentage answer to nearest whole percent.) 3. What percentage of the throughput time was spent in non-value-added activities? (Round your percentage answer to nearest whole percent.)...
Oakwood Company produces maple bookcases to customer order. The following information is available for the production of the bookcases. Process time Inspection time Move time Wait time 5.0 days 1.2 days 4.4 days 19.0 days Required: 1. Compute the company's manufacturing cycle time. 2. Compute the company's manufacturing cycle efficiency. 3. Management believes it can reduce move time by 1.10 days and wait time by 2.50 days by adopting lean manufacturing techniques. Compute the company's manufacturing cycle efficiency assuming the...
Oakwood Company produces maple bookcases to customer order. The following information Is avallable for the production of the bookcases. Process time 16.0 days e.8 days 5.4 days 11.0 days Inspection time Move time Wait time Required: 1. Compute the company's manufacturing cycle time. 2 Compute the company's manufacturing cycle efficiency 3. Management belleves it can reduce move time by 110 days and walt time by 2.50 days by adopting lean manufacturing techniques Compute the company's manufacturing cycle efficiency assuming the...
Oakwood Company produces maple bookcases to customer order. The following information is available for the production of the bookcases. Process time Inspection time Move time Wait time 70 days 1.8 days 4. 3 days 13.0 days Required: 1. Compute the company's manufacturing cycle time 2. Compute the company's manufacturing cycle efficiency 3. Management believes it can reduce move time by 1.10 days and wait time by 2.50 days by adopting lean manufacturing techniques. Compute the company's manufacturing cycle efficiency assuming...
Oakwood Company produces maple bookcases to customer order. The following information is available for the production of the bookcases Process time Inspection time Move time Wait time 14.0 days 0.5 days 4.5 days 9.0 days Required 1. Compute the company's manufacturing cycle time 2. Compute the company's manufacturing cycle efficiency. 3. Management believes it can reduce move time by 1.10 days and wait time by 2.50 days by adopting lean manufacturing techniques Compute the company's manufacturing cycle efficiency assuming the...
Exercise 9-18 Manufacturing cycle time and efficiency LO A4 Oakwood Company produces maple bookcases to customer order. The following information is available for the production of the bookcases Process time Inspection ti Hove time Walt time 15.0 days 2.0 days 4.1 days 3.0 days Required: 1. Compute the company's manufacturing cycle time 2. Compute the company's manufacturing cycle efficiency 3. Management believes it can reduce move time by 110 days and wait time by 250 days by adopting lean manufacturing...
Oakwood Company produces maple bookcases to customer order. The following information is available for the production of the bookcases Process time Inspection time Move time Wait time 5.0 days 1.1 days 4.1 days 17.0 days Required: 1. Compute the company's manufacturing cycle time. 2. Compute the company's manufacturing cycle efficiency. 3. Management believes it can reduce move time by 1.10 days and wait time by 2.50 days by adopting lean manufacturing techniques. Compute the company's manufacturing cycle efficiency assuming the...