Question

Oakwood Company produces maple bookcases to customer order. The following information Is avallable for the production of the
Complete this question by entering your answers in the tabs below. Required 2 Required 3 Required 1 Compute the companys man
Rejuired 3 Required 1 Required 2 Management believes it can reduce move time by 1.10 days and wait time by 2.50 days by adopt
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Process Time Inspection Time Move time Wait time 16.00 days 0.80 days 5.40 days 11.00 days Solution 1. Companys Maufacturing

In case of any doubt, please comment below

Add a comment
Know the answer?
Add Answer to:
Oakwood Company produces maple bookcases to customer order. The following information Is avallable for the produc...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Oakwood Company produces maple bookcases to customer order. The following information is available for the production o...

    Oakwood Company produces maple bookcases to customer order. The following information is available for the production of the bookcases. Process time Inspection time Move time Wait time 70 days 1.8 days 4. 3 days 13.0 days Required: 1. Compute the company's manufacturing cycle time 2. Compute the company's manufacturing cycle efficiency 3. Management believes it can reduce move time by 1.10 days and wait time by 2.50 days by adopting lean manufacturing techniques. Compute the company's manufacturing cycle efficiency assuming...

  • Oakwood Company produces maple bookcases to customer order. The following information is available for the production...

    Oakwood Company produces maple bookcases to customer order. The following information is available for the production of the bookcases. Process time Inspection time Move time Wait time 5.0 days 1.2 days 4.4 days 19.0 days Required: 1. Compute the company's manufacturing cycle time. 2. Compute the company's manufacturing cycle efficiency. 3. Management believes it can reduce move time by 1.10 days and wait time by 2.50 days by adopting lean manufacturing techniques. Compute the company's manufacturing cycle efficiency assuming the...

  • Oakwood Company produces maple bookcases to customer order. The following information is available for the production...

    Oakwood Company produces maple bookcases to customer order. The following information is available for the production of the bookcases Process time Inspection time Move time Wait time 5.0 days 1.1 days 4.1 days 17.0 days Required: 1. Compute the company's manufacturing cycle time. 2. Compute the company's manufacturing cycle efficiency. 3. Management believes it can reduce move time by 1.10 days and wait time by 2.50 days by adopting lean manufacturing techniques. Compute the company's manufacturing cycle efficiency assuming the...

  • Oakwood Company produces maple bookcases to customer order. The following information is available for the production...

    Oakwood Company produces maple bookcases to customer order. The following information is available for the production of the bookcases Process time Inspection time Move time Wait time 14.0 days 0.5 days 4.5 days 9.0 days Required 1. Compute the company's manufacturing cycle time 2. Compute the company's manufacturing cycle efficiency. 3. Management believes it can reduce move time by 1.10 days and wait time by 2.50 days by adopting lean manufacturing techniques Compute the company's manufacturing cycle efficiency assuming the...

  • Exercise 9-18 Manufacturing cycle time and efficiency LO A4 Oakwood Company produces maple bookcases to customer...

    Exercise 9-18 Manufacturing cycle time and efficiency LO A4 Oakwood Company produces maple bookcases to customer order. The following information is available for the production of the bookcases Process time Inspection ti Hove time Walt time 15.0 days 2.0 days 4.1 days 3.0 days Required: 1. Compute the company's manufacturing cycle time 2. Compute the company's manufacturing cycle efficiency 3. Management believes it can reduce move time by 110 days and wait time by 250 days by adopting lean manufacturing...

  • The following information is from a manufacturing company. Process time Inspection time Move time Wait time...

    The following information is from a manufacturing company. Process time Inspection time Move time Wait time 20.0 minutes 3.0 minutes 8.6 minutes 42.6 minutes Required: a. Compute manufacturing cycle time b. Compute manufacturing cycle efficiency Complete this question by entering your answers in the tabs below. Required A Required B Compute manufacturing cycle time. (Round your answers to 1 decimal place.) Manufacturing cycle time Time Manufacturing cycle time The following information is from a manufacturing company. Process time Inspection time...

  • The following information is from a manufacturing company. Process time Inspection time Move time wait time...

    The following information is from a manufacturing company. Process time Inspection time Move time wait time 19.0 minutes 2.0 minutes 6.6 minutes 43.8 minutes Required: a. Compute manufacturing cycle time - b. Compute manufacturing cycle efficiency Complete this question by entering your answers in the tabs below. Required A Required B Compute manufacturing cycle time. (Round your answers to 1 decimal place) Manufacturing cycle time Time Manufacturing cycle time Required B > Complete this question by entering your answers in...

  • The following information is from a manufacturing company. Process time Inspection time Move time Wait time 17.0 minute...

    The following information is from a manufacturing company. Process time Inspection time Move time Wait time 17.0 minutes 2.0 minutes 7.0 minutes 41.4 minutes Required: a. Compute manufacturing cycle time b. Compute manufacturing cycle efficiency Complete this question by entering your answers in the tabs below. Required A Required B Compute manufacturing cycle time. (Round your answers to 1 decimal place.) Manufacturing cycle time Time Manufacturing cycle time 0.0 Required: a. Compute manufacturing cycle time b. Compute manufacturing cycle efficiency...

  • Check my w Inspection time Wait time (from order to start of production) Process time Move...

    Check my w Inspection time Wait time (from order to start of production) Process time Move time Queue time 0.5 days 15.4 days 3.2 days 0.9 days 4.3 days Required: 1. Compute the throughput time. (Round your answer to 1 decimal place.) 2. Compute the manufacturing cycle efficiency (MCE) for the quarter. (Round your percentage answer to nearest whole percent.) 3. What percentage of the throughput time was spent in non-value-added activities? (Round your percentage answer to nearest whole percent.)...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month Throughput time (days) Delivery cycle time (days) Manufacturing...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT