Question

Oakwood Company produces maple bookcases to customer order. The following information is available for the production of theRequired 1 Required 2 Required 3 Compute the companys manufacturing cycle efficiency. (Round your answers to 1 decimal placeRequired 1 Required 2 Required 3 Management believes it can reduce move time by 1.10 days and wait time by 2.50 days by adopt

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Requirement 1 Manfacturing Cycle Time Time 5 days 1.2 days Process Time Inspection Time Move Time Wait Time 4.4 days 19 days

Add a comment
Know the answer?
Add Answer to:
Oakwood Company produces maple bookcases to customer order. The following information is available for the production...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Oakwood Company produces maple bookcases to customer order. The following information is available for the production o...

    Oakwood Company produces maple bookcases to customer order. The following information is available for the production of the bookcases. Process time Inspection time Move time Wait time 70 days 1.8 days 4. 3 days 13.0 days Required: 1. Compute the company's manufacturing cycle time 2. Compute the company's manufacturing cycle efficiency 3. Management believes it can reduce move time by 1.10 days and wait time by 2.50 days by adopting lean manufacturing techniques. Compute the company's manufacturing cycle efficiency assuming...

  • Oakwood Company produces maple bookcases to customer order. The following information is available for the production...

    Oakwood Company produces maple bookcases to customer order. The following information is available for the production of the bookcases Process time Inspection time Move time Wait time 5.0 days 1.1 days 4.1 days 17.0 days Required: 1. Compute the company's manufacturing cycle time. 2. Compute the company's manufacturing cycle efficiency. 3. Management believes it can reduce move time by 1.10 days and wait time by 2.50 days by adopting lean manufacturing techniques. Compute the company's manufacturing cycle efficiency assuming the...

  • Oakwood Company produces maple bookcases to customer order. The following information is available for the production...

    Oakwood Company produces maple bookcases to customer order. The following information is available for the production of the bookcases Process time Inspection time Move time Wait time 14.0 days 0.5 days 4.5 days 9.0 days Required 1. Compute the company's manufacturing cycle time 2. Compute the company's manufacturing cycle efficiency. 3. Management believes it can reduce move time by 1.10 days and wait time by 2.50 days by adopting lean manufacturing techniques Compute the company's manufacturing cycle efficiency assuming the...

  • Oakwood Company produces maple bookcases to customer order. The following information Is avallable for the produc...

    Oakwood Company produces maple bookcases to customer order. The following information Is avallable for the production of the bookcases. Process time 16.0 days e.8 days 5.4 days 11.0 days Inspection time Move time Wait time Required: 1. Compute the company's manufacturing cycle time. 2 Compute the company's manufacturing cycle efficiency 3. Management belleves it can reduce move time by 110 days and walt time by 2.50 days by adopting lean manufacturing techniques Compute the company's manufacturing cycle efficiency assuming the...

  • Exercise 9-18 Manufacturing cycle time and efficiency LO A4 Oakwood Company produces maple bookcases to customer...

    Exercise 9-18 Manufacturing cycle time and efficiency LO A4 Oakwood Company produces maple bookcases to customer order. The following information is available for the production of the bookcases Process time Inspection ti Hove time Walt time 15.0 days 2.0 days 4.1 days 3.0 days Required: 1. Compute the company's manufacturing cycle time 2. Compute the company's manufacturing cycle efficiency 3. Management believes it can reduce move time by 110 days and wait time by 250 days by adopting lean manufacturing...

  • The following information is from a manufacturing company. Process time Inspection time Move time Wait time...

    The following information is from a manufacturing company. Process time Inspection time Move time Wait time 20.0 minutes 3.0 minutes 8.6 minutes 42.6 minutes Required: a. Compute manufacturing cycle time b. Compute manufacturing cycle efficiency Complete this question by entering your answers in the tabs below. Required A Required B Compute manufacturing cycle time. (Round your answers to 1 decimal place.) Manufacturing cycle time Time Manufacturing cycle time The following information is from a manufacturing company. Process time Inspection time...

  • The following information is from a manufacturing company. Process time Inspection time Move time wait time...

    The following information is from a manufacturing company. Process time Inspection time Move time wait time 19.0 minutes 2.0 minutes 6.6 minutes 43.8 minutes Required: a. Compute manufacturing cycle time - b. Compute manufacturing cycle efficiency Complete this question by entering your answers in the tabs below. Required A Required B Compute manufacturing cycle time. (Round your answers to 1 decimal place) Manufacturing cycle time Time Manufacturing cycle time Required B > Complete this question by entering your answers in...

  • The following information is from a manufacturing company. Process time Inspection time Move time Wait time 17.0 minute...

    The following information is from a manufacturing company. Process time Inspection time Move time Wait time 17.0 minutes 2.0 minutes 7.0 minutes 41.4 minutes Required: a. Compute manufacturing cycle time b. Compute manufacturing cycle efficiency Complete this question by entering your answers in the tabs below. Required A Required B Compute manufacturing cycle time. (Round your answers to 1 decimal place.) Manufacturing cycle time Time Manufacturing cycle time 0.0 Required: a. Compute manufacturing cycle time b. Compute manufacturing cycle efficiency...

  • Check my w Inspection time Wait time (from order to start of production) Process time Move...

    Check my w Inspection time Wait time (from order to start of production) Process time Move time Queue time 0.5 days 15.4 days 3.2 days 0.9 days 4.3 days Required: 1. Compute the throughput time. (Round your answer to 1 decimal place.) 2. Compute the manufacturing cycle efficiency (MCE) for the quarter. (Round your percentage answer to nearest whole percent.) 3. What percentage of the throughput time was spent in non-value-added activities? (Round your percentage answer to nearest whole percent.)...

  • Ruiz Foods makes energy bars using a traditional manufacturing process. Raw materials are stored in inventory...

    Ruiz Foods makes energy bars using a traditional manufacturing process. Raw materials are stored in inventory and then moved into production. Work in process inventory is moved across the company's three separate departments. The information below (in the Traditional column) is available for a recent order. If the company adopts lean manufacturing, management believes both move time and wait time can be reduced, as shown in the Lean column. Activity Traditional Lean Process time Inspection time Move time 20 hours...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT