Question

Fol variable and fixed costs!) w Method of cost analysis estimate a cost formula for maintenance What total factory overhead
TER 6: COST BEHAVIOUR: ANALYSIS AND USE ch of this consiste Required: 1. As shown, overhead costs in July amounted to $246,00
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer 1

Maintenance cost = $ 153,000

Calculations:

Machine hours         60,000         90,000
Total cost $ 174,000 $ 246,000
Utilities $     48,000 $     72,000
Supervisor $     21,000 $     21,000
Maintainence $ 105,000 $ 153,000

Answer 2

Lowest range Highest range
Cost $      105,000 $       153,000
Hours $        60,000 $         90,000
As per High Low Method,
Variable cost per hour = Change in costs / change in hours
Variable cost per hour = (153,000-105,000)/(90,000-60,000)
Variable cost per hour = 48,000/30,000
Variable cost per hour = $ 1.6
Fixed Cost = Total Cost - Variable Cost
Fixed Cost = Total Cost - (Variable Cost per hour * hours)
Fixed Cost = 153,000-(1.6*90,000)
Fixed Cost = $ 9000

Answer 3

Total cost = ($ 9,000 + $ 21,000)+ ($ 1.6 +0.8)* Hours

Total cost = $ 30,000 + $ 2.4 * Hours

Answer 4

Total cost = $ 30,000 + $ 2.4 * Hours

= $ 30,000 + 2.4 * 75,000

= $ 210,000

In case of any doubt, please comment.

Add a comment
Know the answer?
Add Answer to:
Fol variable and fixed costs!) w Method of cost analysis estimate a cost formula for maintenance...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • PROBLEM 3-15 High-Low Method; Predicting Cost [LO1, LO2] Crosshill Company's total overhead costs at various levels...

    PROBLEM 3-15 High-Low Method; Predicting Cost [LO1, LO2] Crosshill Company's total overhead costs at various levels of activity are presented below: Total Overhead Cost Month Machine Hours April. ..... May .......... June ........ July................... 70,000 60,000 80,000 90,000 $198,000 $174,000 $222,000 $246,000 Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 60,000-machine-hour level of activity in May is as follows: Utilities (variable) .......................... $ 48,000 Supervisory salaries (fixed)... 21,000...

  • PROBLEM 5A-8 High-Low Method; Predicting Cost LO5-10 Nova Company's total overhead cost at various levels of...

    PROBLEM 5A-8 High-Low Method; Predicting Cost LO5-10 Nova Company's total overhead cost at various levels of activity are presented below: Total Overhead Machine- Month Cost Hours April..... May $198,000 $174,000 $222,000 $246,000 70,000 60,000 ... .. June. 80,000 July 90,000 Cost-Volume-Profit Relationships Assume that the total overhead cost above consists of utilities, supervisory salaries, and main- tenance. The breakdown of these costs at the 60,000 machine-hour level of activity is: Utilities (variable).... Supervisory salaries (fixed) Maintenance (mixed).. $ 48,000 21,000...

  • Problem 5A-8 High-Low Method; Predicting Cost (L05-10) Nova Company's total overhead cost at various levels of...

    Problem 5A-8 High-Low Method; Predicting Cost (L05-10) Nova Company's total overhead cost at various levels of activity are presented below: Month April May June July Machine- Hours 51,000 41,000 61,000 71,000 Total Overhead Cost $ 212,630 $ 187,330 $ 237,930 $ 263,230 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 41,000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $...

  • Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown...

    Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 35.000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 45,500 54,000 60,850 $160, 350 Nova Company's management wants to break down the maintenance cost into its variable and fixed cost elements. Required: 1. Estimate how much of the $236,250 of overhead cost in July was maintenance cost. (Hint: to do this,...

  • Crosshill Company's total overhead costs at various levels of activity are presented below: Month April May...

    Crosshill Company's total overhead costs at various levels of activity are presented below: Month April May June July Machine- Hours 52,000 42,000 62,000 72,000 Total Overhead Cost $204,360 $180,060 $228,660 $252,960 Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 42,000-machine-hour level of activity in May is as follows: $ Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) 54,600 60,000 65,460 Total overhead cost $ 180,060 The company wants to...

  • Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total...

    Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total Overhead Cost      April 54,000    $188,180        May 44,000    $163,980        June 64,000    $212,380        July 74,000    $236,580   Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 44,000-machine-hour level of activity in May is as follows:   Utilities (variable) $ 52,800     Supervisory salaries (fixed) 44,000   Maintenance (mixed) 67,180   Total overhead cost $ 163,980 The...

  • Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total...

    Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total Overhead Cost      April 54,000    $188,180        May 44,000    $163,980        June 64,000    $212,380        July 74,000    $236,580   Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 44,000-machine-hour level of activity in May is as follows:   Utilities (variable) $ 52,800     Supervisory salaries (fixed) 44,000   Maintenance (mixed) 67,180   Total overhead cost $ 163,980 The...

  • Crosshill Company's total overhead costs at various levels of activity are presented below: Month April May...

    Crosshill Company's total overhead costs at various levels of activity are presented below: Month April May Machine- Hours 49,000 39,000 59,000 69,000 Total Overhead Cost $210,730 $186,030 $ 235, 430 $260,130 June July Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 39,000-machine-hour level of activity in May is as follows: $ Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) 50, 700 70,000 65,330 Total overhead cost $ 186,030 The...

  • Problem 5A-8 High-Low Method; Predicting Cost (LO5-10] Nova Company's total overhead cost at various levels of...

    Problem 5A-8 High-Low Method; Predicting Cost (LO5-10] Nova Company's total overhead cost at various levels of activity are presented below: Total Machine- Overhead Month Hours 47,000 37,000 57,000 67,000 Cost $ 190,930 $ 167,030 $ 214,830 $ 238,730 April May June July Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 37,000 machine-hour level of activity is: $ 44,400 Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) 63,000 59,630...

  • Crosshill Company's total overhead costs at various levels of activity are presented below. Month pril May...

    Crosshill Company's total overhead costs at various levels of activity are presented below. Month pril May Machine Hours 19,000 39,000 59,000 69.000 Total Overhead Cost $191,860 $164,460 $219, 260 $246,660 July Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 39,000 machine-hour level of activity in May is as follows: Utilities variable) Supervisory salaries (fixed) Maintenance mixed) 62.400 43.000 59,060 nces Total overhead coat $164.960 The company wants to...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT