Answer 1-
Pre Determined OH rate | |||
Estimated OH cost $ | 10,00,000 | A | |
Direct labour cost $ | 20,00,000 | B | |
Pre Determined OH rate | 0.50 | (A/B) | |
% wise coverage | 50% |
Answer 2 - Journal Entries
Job wise cost determined including OH cost ( 50% of Labour cost)
Direct Material $ | Direct Labour $=b | Overhead -50% of Labour cost$(50%*b) | Total Cost($) | |
House 402 | 55,000 | 46,000 | 23,000 | 1,24,000 |
House 403 | 66,000 | 32,000 | 16,000 | 1,14,000 |
House 404 | 64,000 | 55,000 | 27,500 | 1,46,500 |
House 405 | 88,000 | 54,000 | 27,000 | 1,69,000 |
Total | 2,73,000 | 1,87,000 | 93,500 | 5,53,500 |
Need to pass following Journal Entry | ||||
No | Details | Debit($) | Credit($) | |
a | Purchase of Material | |||
Raw Material Inventory | 4,20,000 | |||
Account Payable | 4,20,000 | |||
b | Work in Process Inventory | 4,60,000 | ||
Raw Material Inventory | 2,73,000 | |||
Wages payable | 1,87,000 | |||
( Accounted direct material ^ | ||||
used labour ) | ||||
c | Overhead | 33,000 | ||
Wages payable | 33,000 | |||
( Total Wages payable $ 220,000 | ||||
so $ 187000 accounted as above , Balance | ||||
amount ( $220000-$187000) | ||||
d | Overhead | 6,300 | ||
Accumulated Depreciation | 6,300 | |||
e | Overhead | 38,000 | ||
Cash | 35,000 | |||
Prepaid Insurance( Worker liability Insurace - Expired) | 3,000 | |||
( cash incurred to Equipment rental) | ||||
f | Work in Process Inventory | 93,500 | ||
Overhead | 93,500 | |||
( as per Calculation - 50% of Direct labour cost) | ||||
( 50% *$ 187000) | ||||
g | Finished Goods Inventory | 2,70,500 | ||
Work in Process Inventory | 2,70,500 | |||
( house completed 402 and 404) | ||||
( as above calculated number) | ||||
h | Account Receivable | 2,40,000 | ||
Sales | 2,40,000 | |||
I | Cost of goods Sold | 1,46,500 | ||
Finished GoodsInventory | 1,46,500 | |||
( House 404 cost | ||||
( as above calculation) |
Answer 3 T accounts
Work In process - Inventory | ||||
No | details | Debit ($) | details | Credit ($) |
b | Raw Material Inventory | 2,73,000 | ||
Wages payable | 1,87,000 | |||
F | Overhead | 93,500 | ||
g | Finished Goods Inventory | 2,70,500 | ||
Closing Balance | 2,83,000 | |||
Total | 5,53,500 | Total | 5,53,500 | |
Finished Goods Inventory | ||||
No | details | Debit ($) | details | Credit ($) |
g | Work in process Inventory | 2,70,500 | ||
i | Cost of goods Sold | 1,46,500 | ||
Closing Balance | 1,24,000 | |||
Total | 2,70,500 | Total | 2,70,500 |
Answer 4 & 5 - As per above House jpb cost sheet - House 402 - Unsold $ 124000, House 403 and 405 - Work in process stage House 403- $ 114000 and House 405-$169000 and House 404 - Sold and cost of goods sold - $ 146500
Answer 6 - Profit of House 404 :
As per Question House 404 sold with value | ||
Amnt($) | ||
Sale Value $ | 2,40,000 | |
Less - Cost of goods sold | 1,46,500 | |
( as calculated above) | ||
Profit | 93,500 |
Uudul ULUSL ULU.. why * Requirements e year Pre 1. Calculate Memory's predetermined overhead allocation rate...
#2
i forgot how to calculate C
of direct labor and the allocation of manufacturine overhead to Job 423. Wages are not yet paid. 1. Journalize completion of the job and the sale of the 5.200 DVDs on account Learning Objectives 2.3 Bal5284,000 .30A Accounting for transactions, construction company Sunset Construction, Inc. is a home builder in Arizona Sunset uses a job order costing system in which each house is a job. Because it constructs houses, the company uses an...
countitled Construction Overhead The mated direct labor cost for the year, it estimated $1,150,000 and total direct labor costs of $5.750.000 T during Augusti .. Purchased materiale on account, $400.000 Requisitioned direct material and directe the materiale regioned head. The company applies mated construction 0.000. The following events direct labor in construction. Recorded Direct Labor 3. Hou 402 House 403 House 404 House 405 Direct Materials $50,000 62,000 61,000 86,000 $ 44,000 32.000 S8,000 57.000 c. The company incurred total...
ry uses a job order casting system in which each house is a it estimated constru More Info b Because it contact houses the company uses an account titled ng events occurred during Aug allocation rate for Purchased materials on account, $420,000 Requisitioned direct materials and used direct labor in construction. Recorded the materials requisitioned. Direct Materials Direct Labor House 402 $ 55,000 $ 46,000 House 403 66,000 32,000 House 404 64,000 55,000 House 405 88,000 54,000 C. The company...
P19-30A
Construction, Inc. is a home builder in Arizona.
MemoryMemory uses a job order costing system in which each house
is a job. Because it constructs houses, the company uses an
account titled Construction Overhead. The company applies overhead
based on estimated direct labor costs. For the year, it estimated
construction overhead of $1,050,000 and total direct labor cost of
$2,100,000.The following events occurred during August:
a.
Purchased materials on account, $ 420 comma 000$420,000
b.
Requisitioned direct materials and...
choose from:
Please make sure to provide answers to fulfill the boxes
above.
More Info a. Purchased materials on account, $490,000 b. Requisitioned direct materials and used direct labor in construction Recorded the materials requisitioned. Direct Materials Direct Labor House 402 $ 51,000 $ 43,000 House 403 69,000 39,000 House 404 61,000 56,000 House 405 85,000 54,000 c. The company incurred total wages of $250,000. Use the data from Item b to assign the wages. Wages are not yet paid....
"17-30A Accounting for transactions, construction company Superior Construction, Inc. is a home builder in Arizona, Superior uses a job order costing system in which each house is a job. Because it constructs houses, the com pany uses an account titled Construction Overhead. The company applies overhead based on estimated direct labor costs. For the year, it estimated construction over. head of $1,150,000 and total direct labor costs of $5,750,000. The following events occurred during August: a. Purchased materials on account,...
choose from:
Please make sure to provide answers to fulfill the boxes
above.
More Info a. Purchased materials on account, $490,000 b. Requisitioned direct materials and used direct labor in construction Recorded the materials requisitioned. Direct Materials Direct Labor House 402 $ 51,000 $ 43,000 House 403 69,000 39,000 House 404 61,000 56,000 House 405 85,000 54,000 c. The company incurred total wages of $250,000. Use the data from Item b to assign the wages. Wages are not yet paid....
g. Houses completed: 402, 404 Credit Debit Accounts Date g. Finished Goods Inventory Work-in-Process Inventory Choose from any list or enter any number in the input fields and then click Check Answer Clear All 7 parts remaining ann IM to search More Info a. Purchased materials on account, $400,000 b. Requisitioned direct materials and used direct labor in construction Recorded the materials requisitioned. Direct Materials Direct Labor House 402 $ 58,000 $ 44,000 House 403 62.000 32.000 House 404 61,000...
The predetermined overhead allocation rate for Freestyle, Inc., is based on estimated direct labor costs of $400,000 and estimated factory overhead of $500,000. Actual costs incurred were: Direct materials. $250,000 400,000 55,000 125,000 50,000 Direct labor Indirect materials....... Indirect labor............................... Sales commissions............. ..... Factory depreciation................. ......... Property taxes, factory.. Factory utilities..... Advertising ...... Factory equipment rental 170,000 15,000 35,000 62,500 100,000 Calculate the predetermined overhead rate and calculate the overhead applied to production during the year (6 points). A. Predetermined...
Exercise 15-17 Overhead rate calculation, allocation, and analysis LO P3 Moonrise Bakery applies factory overhead based on direct labor costs. The company incurred the following costs during the year: direct materials costs, $700,000; direct labor costs, $3,500,000; and factory overhead costs applied, $2,100,000. 1. Determine the company's predetermined overhead rate for the year. 2. Assuming that the company's $76,000 ending Work in Process Inventory account for the year had $25,000 of direct labor costs, determine the inventory's direct materials costs....