1. Predetermined overhead rate = Estimated construction overhead/Estimated direct labor costs = $1150000/$5750000 = 20% of direct labor cost
2.
No | Account Titles and Explanation | Debit | Credit |
a. | Materials inventory | 400000 | |
Accounts payable | 400000 | ||
(To record materials purchased on account) | |||
b. | Work in process inventory | 267000 | |
Materials inventory | 267000 | ||
(To record materials requisitioned) | |||
c. | Work in process inventory | 191000 | |
Construction overhead | 109000 | ||
Wages payable | 300000 | ||
(To record total wages incurred) | |||
d. | Construction overhead | 6700 | |
Accumulated depreciation-equipment | 6700 | ||
(To record depreciation on construction equipment) | |||
e. | Construction overhead | 37000 | |
Cash | 30000 | ||
Prepaid insurance | 7000 | ||
(To record other overhead costs incurred) | |||
f. | Work in process inventory (20% x $191000) | 38200 | |
Construction overhead | 38200 | ||
(To record overhead allocated to jobs) | |||
g. | Finished goods inventory ($110800 + 130600) | 241400 | |
Work in process inventory | 241400 | ||
(To record jobs completed) | |||
h(1) | Accounts receivable | 250000 | |
Sales revenue | 250000 | ||
(To record sales on account) | |||
h(2) | Cost of goods sold | 130600 | |
Finished goods inventory | 130600 | ||
(To record the cost of jobs sold) |
Working:
House 402 | House 403 | House 404 | House 405 | Total | |
Direct materials | 58000 | 62000 | 61000 | 86000 | 267000 |
Direct labor | 44000 | 32000 | 58000 | 57000 | 191000 |
Overhead | 8800 | 6400 | 11600 | 11400 | 38200 |
Total job cost $ | 110800 | 100400 | 130600 | 154400 | 496200 |
3.
Work in Process Inventory | |||
Beg. Bal. | 0 | ||
b. | 267000 | 241400 | g. |
c. | 191000 | ||
f. | 38200 | ||
End. Bal. | 254800 | ||
Finished Goods Inventory | |||
Beg. Bal. | 0 | ||
g. | 241400 | 130600 | h(2) |
End. Bal. | 110800 |
4.
Work in process inventory: | |
House 403 | 100400 |
House 405 | 154400 |
Total $ | 254800 |
Balance $ | 254800 |
5.
Finished goods inventory: | |
House 402 | 110800 |
Balance $ | 110800 |
6.
Sales revenue | 250000 |
Less: Cost of goods sold | 130600 |
Gross profit $ | 119400 |
The gross profit must cover the selling, general, and administrative expenses for Superior Construction to generate a net income.
countitled Construction Overhead The mated direct labor cost for the year, it estimated $1,150,000 and total...
"17-30A Accounting for transactions, construction company Superior Construction, Inc. is a home builder in Arizona, Superior uses a job order costing system in which each house is a job. Because it constructs houses, the com pany uses an account titled Construction Overhead. The company applies overhead based on estimated direct labor costs. For the year, it estimated construction over. head of $1,150,000 and total direct labor costs of $5,750,000. The following events occurred during August: a. Purchased materials on account,...
#2
i forgot how to calculate C
of direct labor and the allocation of manufacturine overhead to Job 423. Wages are not yet paid. 1. Journalize completion of the job and the sale of the 5.200 DVDs on account Learning Objectives 2.3 Bal5284,000 .30A Accounting for transactions, construction company Sunset Construction, Inc. is a home builder in Arizona Sunset uses a job order costing system in which each house is a job. Because it constructs houses, the company uses an...
Uudul ULUSL ULU.. why * Requirements e year Pre 1. Calculate Memory's predetermined overhead allocation rate for the year. 2. Prepare journal entries to record the events in the general journal. 3. T-accounts for Work-in-Process Inventory and Finished Goods Inventory have been opened for you. Post the appropriate entries to these accounts, identifying each entry by letter. Determine the ending account balances, assuming that the beginning balances were zero. 4. Add the costs of the unfinished houses, and show that...
P19-30A
Construction, Inc. is a home builder in Arizona.
MemoryMemory uses a job order costing system in which each house
is a job. Because it constructs houses, the company uses an
account titled Construction Overhead. The company applies overhead
based on estimated direct labor costs. For the year, it estimated
construction overhead of $1,050,000 and total direct labor cost of
$2,100,000.The following events occurred during August:
a.
Purchased materials on account, $ 420 comma 000$420,000
b.
Requisitioned direct materials and...
choose from:
Please make sure to provide answers to fulfill the boxes
above.
More Info a. Purchased materials on account, $490,000 b. Requisitioned direct materials and used direct labor in construction Recorded the materials requisitioned. Direct Materials Direct Labor House 402 $ 51,000 $ 43,000 House 403 69,000 39,000 House 404 61,000 56,000 House 405 85,000 54,000 c. The company incurred total wages of $250,000. Use the data from Item b to assign the wages. Wages are not yet paid....
ry uses a job order casting system in which each house is a it estimated constru More Info b Because it contact houses the company uses an account titled ng events occurred during Aug allocation rate for Purchased materials on account, $420,000 Requisitioned direct materials and used direct labor in construction. Recorded the materials requisitioned. Direct Materials Direct Labor House 402 $ 55,000 $ 46,000 House 403 66,000 32,000 House 404 64,000 55,000 House 405 88,000 54,000 C. The company...
choose from:
Please make sure to provide answers to fulfill the boxes
above.
More Info a. Purchased materials on account, $490,000 b. Requisitioned direct materials and used direct labor in construction Recorded the materials requisitioned. Direct Materials Direct Labor House 402 $ 51,000 $ 43,000 House 403 69,000 39,000 House 404 61,000 56,000 House 405 85,000 54,000 c. The company incurred total wages of $250,000. Use the data from Item b to assign the wages. Wages are not yet paid....
g. Houses completed: 402, 404 Credit Debit Accounts Date g. Finished Goods Inventory Work-in-Process Inventory Choose from any list or enter any number in the input fields and then click Check Answer Clear All 7 parts remaining ann IM to search More Info a. Purchased materials on account, $400,000 b. Requisitioned direct materials and used direct labor in construction Recorded the materials requisitioned. Direct Materials Direct Labor House 402 $ 58,000 $ 44,000 House 403 62.000 32.000 House 404 61,000...
Direct materials costs to Work in Process Inventory.
Direct labor costs to Work in Process Inventory.
Overhead costs to Work in Process Inventory.
Indirect materials costs to the Factory Overhead account.
Indirect labor costs to the Factory Overhead account.
Required: Prepare journal entries to assign the above
costs.
Required information Problem 2-2A Source documents, journal entries, overhead, and financial reports LO P1, P2, P3, P4 The following information applies to the questions displayed below.) Bergamo Bay's computer system generated the...
Clemmens Company applies overhead based on direct labor cost. Estimated overhead and direct labor costs for the year were $115,500 and $124,600, respectively. During the year, actual overhead was $107.000 and actual direct labor cost was $116,000. The entry to close the over- or underapplied overhead at year-end, assuming an immaterial amount would include (Round predetermined overhead rate to nearest whole percentage.) Multiple Choice 0 A credit to Factory Overhead for $880. A credit to Cost of Goods Sold for...