Question

countitled Construction Overhead The mated direct labor cost for the year, it estimated $1,150,000 and total direct labor cos
0 0
Add a comment Improve this question Transcribed image text
Answer #1

1. Predetermined overhead rate = Estimated construction overhead/Estimated direct labor costs = $1150000/$5750000 = 20% of direct labor cost

2.

No Account Titles and Explanation Debit Credit
a. Materials inventory 400000
Accounts payable 400000
(To record materials purchased on account)
b. Work in process inventory 267000
Materials inventory 267000
(To record materials requisitioned)
c. Work in process inventory 191000
Construction overhead 109000
Wages payable 300000
(To record total wages incurred)
d. Construction overhead 6700
Accumulated depreciation-equipment 6700
(To record depreciation on construction equipment)
e. Construction overhead 37000
Cash 30000
Prepaid insurance 7000
(To record other overhead costs incurred)
f. Work in process inventory (20% x $191000) 38200
Construction overhead 38200
(To record overhead allocated to jobs)
g. Finished goods inventory ($110800 + 130600) 241400
Work in process inventory 241400
(To record jobs completed)
h(1) Accounts receivable 250000
Sales revenue 250000
(To record sales on account)
h(2) Cost of goods sold 130600
Finished goods inventory 130600
(To record the cost of jobs sold)

Working:

House 402 House 403 House 404 House 405 Total
Direct materials 58000 62000 61000 86000 267000
Direct labor 44000 32000 58000 57000 191000
Overhead 8800 6400 11600 11400 38200
Total job cost $ 110800 100400 130600 154400 496200

3.

Work in Process Inventory
Beg. Bal. 0
b. 267000 241400 g.
c. 191000
f. 38200
End. Bal. 254800
Finished Goods Inventory
Beg. Bal. 0
g. 241400 130600 h(2)
End. Bal. 110800

4.

Work in process inventory:
House 403 100400
House 405 154400
Total $ 254800
Balance $ 254800

5.

Finished goods inventory:
House 402 110800
Balance $ 110800

6.

Sales revenue 250000
Less: Cost of goods sold 130600
Gross profit $ 119400

The gross profit must cover the selling, general, and administrative expenses for Superior Construction to generate a net income.

Add a comment
Know the answer?
Add Answer to:
countitled Construction Overhead The mated direct labor cost for the year, it estimated $1,150,000 and total...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • "17-30A Accounting for transactions, construction company Superior Construction, Inc. is a home builder in Arizona, Superior...

    "17-30A Accounting for transactions, construction company Superior Construction, Inc. is a home builder in Arizona, Superior uses a job order costing system in which each house is a job. Because it constructs houses, the com pany uses an account titled Construction Overhead. The company applies overhead based on estimated direct labor costs. For the year, it estimated construction over. head of $1,150,000 and total direct labor costs of $5,750,000. The following events occurred during August: a. Purchased materials on account,...

  • #2 i forgot how to calculate C of direct labor and the allocation of manufacturine overhead...

    #2 i forgot how to calculate C of direct labor and the allocation of manufacturine overhead to Job 423. Wages are not yet paid. 1. Journalize completion of the job and the sale of the 5.200 DVDs on account Learning Objectives 2.3 Bal5284,000 .30A Accounting for transactions, construction company Sunset Construction, Inc. is a home builder in Arizona Sunset uses a job order costing system in which each house is a job. Because it constructs houses, the company uses an...

  • Uudul ULUSL ULU.. why * Requirements e year Pre 1. Calculate Memory's predetermined overhead allocation rate...

    Uudul ULUSL ULU.. why * Requirements e year Pre 1. Calculate Memory's predetermined overhead allocation rate for the year. 2. Prepare journal entries to record the events in the general journal. 3. T-accounts for Work-in-Process Inventory and Finished Goods Inventory have been opened for you. Post the appropriate entries to these accounts, identifying each entry by letter. Determine the ending account balances, assuming that the beginning balances were zero. 4. Add the costs of the unfinished houses, and show that...

  • P19-30A ​Construction, Inc. is a home builder in Arizona. MemoryMemory uses a job order costing system in which each hou...

    P19-30A ​Construction, Inc. is a home builder in Arizona. MemoryMemory uses a job order costing system in which each house is a job. Because it constructs​ houses, the company uses an account titled Construction Overhead. The company applies overhead based on estimated direct labor costs. For the​ year, it estimated construction overhead of $1,050,000 and total direct labor cost of $2,100,000.The following events occurred during August​: a. Purchased materials on​ account, $ 420 comma 000$420,000 b. Requisitioned direct materials and...

  • choose from: Please make sure to provide answers to fulfill the boxes above. More Info a....

    choose from: Please make sure to provide answers to fulfill the boxes above. More Info a. Purchased materials on account, $490,000 b. Requisitioned direct materials and used direct labor in construction Recorded the materials requisitioned. Direct Materials Direct Labor House 402 $ 51,000 $ 43,000 House 403 69,000 39,000 House 404 61,000 56,000 House 405 85,000 54,000 c. The company incurred total wages of $250,000. Use the data from Item b to assign the wages. Wages are not yet paid....

  • ry uses a job order casting system in which each house is a it estimated constru...

    ry uses a job order casting system in which each house is a it estimated constru More Info b Because it contact houses the company uses an account titled ng events occurred during Aug allocation rate for Purchased materials on account, $420,000 Requisitioned direct materials and used direct labor in construction. Recorded the materials requisitioned. Direct Materials Direct Labor House 402 $ 55,000 $ 46,000 House 403 66,000 32,000 House 404 64,000 55,000 House 405 88,000 54,000 C. The company...

  • choose from: Please make sure to provide answers to fulfill the boxes above. More Info a. Purchased materials on accou...

    choose from: Please make sure to provide answers to fulfill the boxes above. More Info a. Purchased materials on account, $490,000 b. Requisitioned direct materials and used direct labor in construction Recorded the materials requisitioned. Direct Materials Direct Labor House 402 $ 51,000 $ 43,000 House 403 69,000 39,000 House 404 61,000 56,000 House 405 85,000 54,000 c. The company incurred total wages of $250,000. Use the data from Item b to assign the wages. Wages are not yet paid....

  • g. Houses completed: 402, 404 Credit Debit Accounts Date g. Finished Goods Inventory Work-in-Process Inventory Choose...

    g. Houses completed: 402, 404 Credit Debit Accounts Date g. Finished Goods Inventory Work-in-Process Inventory Choose from any list or enter any number in the input fields and then click Check Answer Clear All 7 parts remaining ann IM to search More Info a. Purchased materials on account, $400,000 b. Requisitioned direct materials and used direct labor in construction Recorded the materials requisitioned. Direct Materials Direct Labor House 402 $ 58,000 $ 44,000 House 403 62.000 32.000 House 404 61,000...

  • Direct materials costs to Work in Process Inventory. Direct labor costs to Work in Process Inventory....

    Direct materials costs to Work in Process Inventory. Direct labor costs to Work in Process Inventory. Overhead costs to Work in Process Inventory. Indirect materials costs to the Factory Overhead account. Indirect labor costs to the Factory Overhead account. Required: Prepare journal entries to assign the above costs. Required information Problem 2-2A Source documents, journal entries, overhead, and financial reports LO P1, P2, P3, P4 The following information applies to the questions displayed below.) Bergamo Bay's computer system generated the...

  • Clemmens Company applies overhead based on direct labor cost. Estimated overhead and direct labor costs for...

    Clemmens Company applies overhead based on direct labor cost. Estimated overhead and direct labor costs for the year were $115,500 and $124,600, respectively. During the year, actual overhead was $107.000 and actual direct labor cost was $116,000. The entry to close the over- or underapplied overhead at year-end, assuming an immaterial amount would include (Round predetermined overhead rate to nearest whole percentage.) Multiple Choice 0 A credit to Factory Overhead for $880. A credit to Cost of Goods Sold for...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT