Exercise 10-4 (Static) Cost of a natural resource; asset retirement obligation [LO10-1] Jackpot Mining Company operates a cop

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Computation of Cost of Copper Mine
Particular Amount
Cash Paid for Mining site $1,000,000
Additional Development cost $600,000
Restoration cost (workingNote) $303,935
Total Cost of Copper Mines $1,903,935
Working Note : Computation of Expected Restoration cost
($ 300,000 * 25 % + $400,000 *40% + $ 600,000*35%) *0.6830 = $303,935
Journal Entry- Jackpot Mining Company
Date Account Tittle Debit Credit
2021 Copper Mine $1,903,935.00
Cash (1000000+600000) $1,600,000.00
Assets Retirement Liability $303,935.00
To record acquisition costs of the mine
1-Jul-21 Equipment $120,000.00
Cash $120,000.00
To record purchase of equipment
Add a comment
Know the answer?
Add Answer to:
Exercise 10-4 (Static) Cost of a natural resource; asset retirement obligation [LO10-1] Jackpot Mining Company operates...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Exercise 10-4 Cost of a natural resource; asset retirement obligation (LO10-1] Jackpot Mining Company operates a...

    Exercise 10-4 Cost of a natural resource; asset retirement obligation (LO10-1] Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,700,000 in 2018 for the mining site and spent an additional $740,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately 4 years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following...

  • Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,350,000 in 2021...

    Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,350,000 in 2021 for the mining site and spent an additional $670,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs: (FV of $1,...

  • Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,750,000 in 2021...

    Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,750,000 in 2021 for the mining site and spent an additional $750,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs: (FV of $1,...

  • Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,750,000 in 2021...

    Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,750,000 in 2021 for the mining site and spent an additional $750,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs: (FV of $1,...

  • Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,150,000 in 2018...

    Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,150,000 in 2018 for the mining site and spent an additional $630,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately 4 years the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs: (FV of $1,...

  • Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,650,000 in 2021...

    Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,650,000 in 2021 for the mining site and spent an additional $730,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs: (FV of $1,...

  • I will give thumbs up for correct answers! Thank you! Jackpot Mining Company operates a copper...

    I will give thumbs up for correct answers! Thank you! Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,800,000 in 2021 for the mining site and spent an additional $760,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three...

  • Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,150,000 in 2018...

    Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,150,000 in 2018 for the mining site and spent an additional $630,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs (FV of $1,...

  • Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,400,000 in 2021...

    Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,400,000 in 2021 for the mining site and spent an additional $680,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs: (FV of $1,...

  • Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,000,000 in 2018...

    Jackpot Mining Company operates a copper mine in central Montana. The company paid $1,000,000 in 2018 for the mining site and spent an additional $600,000 to prepare the mine for extraction of the copper. After the copper is extracted in approximately four years, the company is required to restore the land to its original condition, including repaving of roads and replacing a greenbelt. The company has provided the following three cash flow possibilities for the restoration costs (FV of $1....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT