3. [The following information applies to the questions
displayed below.]
A manufactured product has the following information for
June.
Standard | Actual | |||
Direct materials | 6 lbs. @ $8 per lb. | 52,700 | lbs. @ $8.20 per lb. | |
Direct labor | 2 hrs. @ $16 per hr. | 17,100 | hrs. @ $16.60 per hr. | |
Overhead | 2 hrs. @ $11 per hr. | $ | 196,500 | |
Units manufactured | 8,700 | |||
(1) Compute the standard cost per unit.
(2) Compute the total cost variance for June.
Direct Materials _______
Direct Labor ________
Overhead _______
Total _______
Total Cost Variance _______
1) standard cost per unit | |||
Direct material (6lbs*8 per lbs ) | 48 | ||
direct labor (2 hrs*16 per hr) | 32 | ||
overhead (2hrs*11 per hr) | 22 | ||
total | 102 | ||
2) total cost variance | |||
Direct material (52700*8.20) | 432140 | ||
direct labor (17100*16.60) | 283860 | ||
overhead | 196500 | ||
total actual manufacturing cost | 912500 | ||
standard cost | |||
direct material (6*8*8700) | 417600 | ||
direct labor (2*16*8700) | 278400 | ||
overhead (2*11*8700) | 191400 | ||
total standard manufacturing cost | 887400 | ||
calculation of total cost variance | |||
total actual manufacturing cost | 912500 | ||
less: total standard manufacturing cost | 887400 | ||
total cost variance -UNFAVORABLE | 25100 |
Please give a thumbs up if it is helpful & let me know if any doubt
3. [The following information applies to the questions displayed below.] A manufactured product has the following...
Required information [The following information applies to the questions displayed below.) A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard (5 lbs. @ $8 per lb.) (2 hrs. @ $17 per hr.) (2 hrs. @ $12 per hr.) Actual 43,900 lbs. @ $8.10 per lb. 17,100 hrs. @ $17.40 per hr. $214,700 8,700 (1) Compute the standard cost per unit. Direct materials Direct labor Overhead Total (2) Compute the total cost variance...
Required information [The following information applies to the questions displayed below.) A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard 5 lbs. @ $7 per lb. 3 hrs. @ $16 per hr. 3 hrs. @ $11 per hr. Actual 43, 600 lbs. @ $7.10 per lb. 25,600 hrs. @ $16.60 per hr. $290,400 8,600 (1) Compute the standard cost per unit. (2) Compute the total cost variance for June. Complete this question...
Required information [The following information applies to the questions displayed below.) A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard (6 lbs. $8 per lb.) (2 hrs. @ $16 per hr.) (2 hrs. @ $12 per hr.) Actual 49,700 lbs. @ $8.10 per lb. 16,000 hrs. @ $16.60 per hr $202,300 8,200 (1) Compute the standard cost per unit. Direct materials Direct labor Overhead Total (2) Compute the total cost variance for...
Required information [The following information applies to the questions displayed below.] A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard 7 lbs. @ $8 per lb. 2 hrs. @ $15 per hr. 2 hrs. @ $11 per hr. Actual 61,300 lbs. @ $8.10 per lb. 17,100 hrs. @ $15.40 per hr. $ 197,500 8,700 Compute the direct materials price variance and the direct materials quantity variance. (Indicate the effect of each variance...
Help Sav Required information The following information applies to the questions displayed below.) A manufactured product has the following information for June Direct materials Direct labor Overhead Units manufactured Standard (5 lbs. $7 per lb.) (2 hrs. $16 per hr.) (2 hen. $12 per hr.) Actual 40,400 lbs. $7.10 per lb. 15,800 hrs. $16.60 per hr. $198.000 8.000 (1) Compute the standard cost per unit Direct materials Direct labor Overhead Total (2) Compute the total cost variance for June, Indicate...
Required information [The following information applies to the questions displayed below] A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard (6 lbs. @ $7 per lb.) (2 hrs. $16 per hr.) (2 hrs. @ $13 per hr.) Actual 44.3e9 lbs. @ $7.10 per lb. 14,300 hrs. $16.50 per hr. $196,700 7,300 (1) Compute the standard cost per unit Direct materials Direct labor Overhead Total (2) Compute the total cost variance for June,...
- Required information [The following information applies to the questions displayed below.) A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard 7 lbs. @ $8 per lb. 2 hrs. @ $15 per hr. 2 hrs. @ $13 per hr. Actual 52,900 lbs. @ $8.20 per lb. 14,700 hrs. @ $15.50 per hr. $200,600 7,500 (1) Compute the standard cost per unit. (2) Compute the total cost variance for June. Complete this question...
Please show steps Required information [The following information applies to the questions displayed below.] A manufactured product has the following information for June. Standard Actual Direct materials (5 lbs. $8 per Ib., (2 hrs. $16 per hr.) 41,900 lbs. $8.20 per lb 16,300 hrs. $16.40 per hr. Dverht e s bor(2 hnrs. 8 $12 per hr205,30 hs.e $6.4 per hr Overhead Units manufactured (2 hrs. $12 per hr.) $205, 50e 8,300 (1) Compute the standard cost per unit. Direct materials...
[The following information applies to the questions displayed below.] A manufactured product has the following information for June. Standard (6 lbs. @ $8 per lb.) (2 hrs. @ $16 per hr.) |(2 hrs. @ $12 per hr.) Actual 48,500 lbs. @ $8.10 per lb 15,700 hrs. @ $16.50 per hr. $198,000 8,000 Direct materials Direct labor Overhead Units manufactured (1) Compute the standard cost per unit. Direct materials Direct labor Overhead Total $ 0 (2) Compute the total cost variance...
Required information [The following information applies to the questions displayed below. A manufactured product has the following information for June. Direct materials 1 Actual lbs. @ $7.20 per 9 54,400 lb. Standard (7 lbs. @ $7 per lb.) (3 hrs. @ $15 per hr.) (3 hrs. @ $12 per hr.) Direct labor Overhead Units manufactured 32 saa hrs. @ $15.50 per 22,8001 hr. $283,300 7,700 (1) Compute the standard cost per unit. Direct materials Direct labor Overhead Total (2) Compute...