Question

I am having trouble computing the NPV for this problem (A). Can you show me the...

I am having trouble computing the NPV for this problem (A). Can you show me the steps to take to calculate this?

Grace and Lydia met as engineering students and quickly discovered they both liked building things, gardening and most mountain sports.  As students they earned extra money helping to construct geodesic style greenhouse kits. The women worked on about a dozen of these projects and soon realized a couple of things:

  • The kits were expensive
  • They used all virgin materials – mostly wood and poly carbonate plastic
  • Construction was slow because the triangles were small requiring more connections

As seniors they had to do a major class project so designed a greenhouse kit that was made of mostly recycled materials, was easier to construct and would be less expensive than traditional kits.  Their school had a large 3D printer that uses plastic soda and milk bottles as its inputs.  By extruding the old bottles as ribbons they could then use thermo-molding to turn them into the triangular wall pieces.  A similar process is used to create the framing struts.  They built an eight-foot diameter dome this way, so showed proof of concept.  After college they kept tinkering with the design and materials.  Finally they found some investors and started a company.  They didn’t know much about business but their investors stepped in and developed a marketing plan.  After some market research, there was still uncertainty about what consumer appeal of the product would be.  The business advisors created this table with likely high and low demand scenarios.

Year

1

2

3

4

5

6

High Demand (50%)

After-tax cash flows

500,000

700,000

1,000,000

1,300,000

1,400,000

1,000,000

Low Demand (50%)

After-tax cash flows

100,000

100,000

100,000

100,000

100,000

100,000

Weighted average

after-tax cash flow

300,000

400,000

550,000

700,000

750,000

550,000

The equipment to make full-size greenhouse kits – 16 feet and 22 feet in diameter – would cost about $2.5 million.  If the company closes down early the after-tax cash-flow from the sale of the equipment will be $900,000 at the end of Year 1 and $650,000 at the end of Year 2.  It has no resale value beyond Year 2.

The table shows projected cash flows for high and low demand scenarios.  The cash flows include depreciation, taxes, etc.  The only thing missing is the salvage value of the equipment if the project is abandoned early.

  1. Compute the traditional NPV of the project using a 10% discount rate.
  2. Compute the NPV of the project using a 10% discount rate and assuming that if demand is low that the company can be shut down after Year 1 or Year 2, whichever is best.
  3. Should they make this investment?
  4. D.  In a very brief essay (150 words maximum) explain how the abandonment option creates value for the company.
0 0
Add a comment Improve this question Transcribed image text
Answer #1

The Excel calculation of all projection and the narrative explanation attached as snap.Flow 0 Low Demand Present value Computation @ 10% Discount Rate -2500000 -2500000 100000 90909 90909.09091 100000 82645 826We will not make this investment as the Average demand of the project leads to Negative NPV of (2,29,2 10 1-), However the ch

Add a comment
Know the answer?
Add Answer to:
I am having trouble computing the NPV for this problem (A). Can you show me the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Year 1 2 3 4 5 6 High Demand (50%) After-tax cash flows 500,000 700,000 1,000,000 1,300,000...

    Year 1 2 3 4 5 6 High Demand (50%) After-tax cash flows 500,000 700,000 1,000,000 1,300,000 1,400,000 1,000,000 Low Demand (50%) After-tax cash flows 100,000 100,000 100,000 100,000 100,000 100,000 Weighted average after-tax cash flow 300,000 400,000 550,000 700,000 750,000 550,000 . The equipment to make full-size greenhouse kits – 16 feet and 22 feet in diameter – would cost about $2.5 million. If the company closes down early the after-tax cash-flow from the sale of the equipment will...

  • In excel or Word doc please You are evaluating the following project. All $ are in millions Initial cost of the proj...

    In excel or Word doc please You are evaluating the following project. All $ are in millions Initial cost of the project at t-0 is $70. Annual cash flows from the project depends on the demand for the product and is estimated to be as follows: With probability of 30%, the demand is high and the annual cash flow is $45 With probability of 40%, the demand is average and the annual cash flow is $30 With probability of 30%,...

  • I need it the excel document, not a screenshot please I need question 3 answered please...

    I need it the excel document, not a screenshot please I need question 3 answered please You are evaluating the following project. All $ are in millions Initial cost of the project at t-0 is $70. Annual cash flows from the project depends on the demand for the product and is estimated to be as follows: With probability of 30%, the demand is high and the annual cash flow is $45 With probability of 40%, the demand is average and...

  • This is a cost accounting problem, please show all work. Payback and NPV methods, no income...

    This is a cost accounting problem, please show all work. Payback and NPV methods, no income taxes. (CMA, adapted) Andrews Construction is analyzing its capital expenditure proposals for the purchase of equipment in the coming year. The capital budget is limited to $5,000,000 for the year. Lori Bart, staff analyst at Andrews, is preparing an analysis of the three projects under consideration by Corey Andrews, the company's owner. Insert Page Layout Formulas Data Review View Home A В С D...

  • Please help me fill in the last blank UPDATE: This is all the information I have...

    Please help me fill in the last blank UPDATE: This is all the information I have been given. I just need help with the last blank. DCF analysis doesn't always lead to proper capital budgeting decisions because capital budgeting projects are not passive investments like stocks and bonds. Managers can often take positive actions after the investment has been made to alter a project's cash flows. These opportunities are real options that offer the right but not the obligation to...

  • I'm having trouble figuring out how to calculate the numbers that go into the NPV analysis...

    I'm having trouble figuring out how to calculate the numbers that go into the NPV analysis grids. The three values that I came up with in the first grid next to NPV in cells I'm not sure if it's correct. Can you help with both grids please? The questions below must be answered after. 2D. Based on your NPV Scenario / Risk Analysis Grids, is NPV more sensitive to changing cost of capital or changing salvage values? How do you...

  • Quantitative Problem: Sunshine Smoothies Company (SSC) manufactures and distributes smoothies. SSC is considering the development of...

    Quantitative Problem: Sunshine Smoothies Company (SSC) manufactures and distributes smoothies. SSC is considering the development of a new line of high-protein energy smoothies. SSC's CFO has collected the following information regarding the proposed project, which is expected to last 3 years: The project can be operated at the company's Charleston plant, which is currently vacant. The project will require that the company spend $4.9 million today (t = 0) to purchase additional equipment. This equipment is eligible for 100% bonus...

  • Problem 6-15 Project NPV and IRR A project requires an initial investment of $100,000 and is...

    Problem 6-15 Project NPV and IRR A project requires an initial investment of $100,000 and is expected to produce a cash inflow before tax of $26,700 per year for five years. Company A has substantial accumulated tax losses and is unlikely to pay taxes in the foreseeable future. Company B pays corporate taxes at a rate of 21% and can claim 100% bonus depreciation on the investment. Suppose the opportunity cost of capital is 9%. Ignore inflation. a. Calculate project...

  • Can someone please provide steps for calculating IRR on a TI Nspire CX? I can calculate npv alrea...

    can someone please provide steps for calculating IRR on a TI Nspire CX? I can calculate npv already, but I do not know how to use the irr function on ti nspire. the problem I am stuck on is number 10. thank you out-content-rid-14522766-1/courses/FINC3321-002-201 920/capital%20decisions%281 %29.pdf P9-10 Your company is considering two mutually exclusive projects-C and R-whose costs and cash flows are shown in the following table: Expected Net Cash Flows Year Project CF Project R $(14,000) 8,000 6,000 2,000...

  • Please solve it by hand so that I can understand the steps. 6. A project has...

    Please solve it by hand so that I can understand the steps. 6. A project has the following total (or net) after-tax cash flows.                ____________________________________________________         Year             Total (or net) after-tax cash flow                ____________________________________________________                   1 $1,000,000 2 1,500,000 3 2,000,000 4 2,500,000                   _______________________________________________________ The required rate of return on the project is 15 percent. The initial investment (or initial cost or initial outlay) of the project is $4,000,000. a) Find the (regular) payback period of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT