Answers
A |
Budgeted Factory Overhead |
$ 3,469,400.00 |
B |
Total Direct Labor Hours [DLHs] |
9,130 |
C = A/B |
Overhead rate per DLH |
$ 380.00 ANSWER |
--Working for DLHs
Units |
DLH per unit |
Total DLHs |
|
[A] |
[B] |
[C = A x B] |
|
Trumpets |
4,000 |
1.2 |
4,800 |
Tubas |
1,200 |
0.9 |
1,080 |
Trombones |
2,500 |
1.3 |
3,250 |
Total Direct Labor Hours [DLHs] |
9,130 |
--Answers, with calculation data.
No. of DLHs |
Total factory Overhead Cost |
Units |
Per unit Factory Overhead cost |
|
[A] |
[B = A x 380] |
[C] |
[D = B/C] |
|
Trumpets |
4,800 |
$ 1,824,000.00 |
4,000 |
$ 456.00 |
Tubas |
1,080 |
$ 410,400.00 |
1,200 |
$ 342.00 |
Trombones |
3,250 |
$ 1,235,000.00 |
2,500 |
$ 494.00 |
TOTAL |
$ 3,469,400.00 |
A CH 18 EX 2,3,4,8,10,12,19,20 X Single Plantwide Factory Overhead Rate Mozart Music Inc. makes three...
Single Plantwide Factory Overhead Rate Mozart Music Inc. makes three musical instruments: trumpets, tubas, and trombones. The budgeted factory overhead cost is $120,700. Factory overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Volume Direct Labor Hours Per Unit Trumpets 2,900 units 0.5 Tubas 400 1.4 Trombones 1,400 1.1 If required, round all per unit answers to the nearest...
#1
& #2
eBook Calculator Single Plantwide Factory Overhead Rate Nixon Machine Parts Inc.'s Fabrication Department incurred $124,000 of factory overhead cost in producing gears and sprockets. The two products consumed a total of 6,200 direct machine hours. Of that amount, sprockets consumed 3,100 direct machine hours. Determine the total amount of factory overhead that should be allocated to sprockets using machine hours as the allocation base. If required, round your answer to the nearest dollar. Instructions Mozart Music Inc,...
Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $112,200. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Volume Direct Labor Hours Per Unit Flutes 2,600 units 0.4 900 1.4 Clarinets Oboes 1,000 1.0 If required, round all per unit answers to the nearest cent....
Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $82,800. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Direct Labor Hours Per Volume Unit Flutes 2,300 units 0.5 Clarinets 700 1.4 Oboes 1,200 1.1 If required, round all per unit answers to the nearest cent....
Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $99,120. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Volume Direct Labor Hours Per Unit Flutes 2,200 units 0.4 Clarinets 700 1.4 Oboes 1,400 1.2 If required, round all per unit answers to the nearest cent....
Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $127,840. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Volume Direct Labor Hours Per Unit Flutes 2,200 units 0.5 Clarinets 700 1.4 Oboes 1,400 1.2 If required, round all per unit answers to the nearest cent....
Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $94,200. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Volume Direct Labor Hours Per Unit Flutes 1,900 units 0.4 Clarinets 700 1.4 Oboes 1,400 1.0 If required, round all per unit answers to the nearest cent....
Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $135,660. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Volume Direct Labor Hours Per Unit Flutes 2,100 units 0.5 Clarinets 800 1.4 Oboes 1,400 1.0 If required, round all per unit answers to the nearest cent....
Unit Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $101,040. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Direct Labor Hours Per Volume 2,700 units 0.8 500 1,300 If required, round all per unit answers to the nearest cent. a. Determine the single plantwide...
Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $114,000. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Volume Direct Labor Hours Per Unit Flutes 2,400 units 0.6 Clarinets 900 1.4 Oboes 1,100 1.0 If required, round all per unit answers to the nearest cent....