Question

Unit Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and obo
1 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution to requirement (a) :

Computation of plantwide overhead rate :

Total overhead                = $ 1,01,040

Computation of labor hours :

Particulars

Production volume

Direct labor per unit

Number of labor hours required

Flutes

2,700 units

0.8 hours

2,160 hours

(2,700 units* 0.80 hrs)

Clarinets

500 units

1.5 hours

750 hours

(500 units*1.5 hrs)

Oboes

1,300 units

1.0

1,300 hours

(1,300 units*1 hr)

Total

4,210 hours

  

Direct labor hours                          = 4,210 hours

Plantwide overhead rate = Total overhead / Direct labor hours

Plantwide overhead rate = $ 1,01,040 / 4,210 hours

Plantwide overhead rate = $ 24.00 per hour

Solution to Requirement (b):

Particulars

Total factory overhead cost

(A)

Number of units

(B)

Per unit factory overhead cost

C = A / B

Flutes

$ 51,840

(2,160 hours*$ 24)

2,700 units

$ 19.20

($ 51,840 / 2,700 units)

Clarinets

$ 18,000

(750 hours*$ 24)

500 units

$ 36.00

( $18,000 / 500 units)

Oboes

$ 31,200

(1,300 hours *$ 24)

1,300 units

$ 24.00

($ 31,200 / 1,300 units )

Total $ 1,01,040

Thankyou !!!!!!

Add a comment
Know the answer?
Add Answer to:
Unit Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Unit Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and...

    Unit Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $101,040. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Direct Labor Hours Per Volume 2,700 units 0.8 500 1,300 If required, round all per unit answers to the nearest cent. a. Determine the single plantwide...

  • Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes....

    Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $112,200. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Volume Direct Labor Hours Per Unit Flutes 2,600 units 0.4 900 1.4 Clarinets Oboes 1,000 1.0 If required, round all per unit answers to the nearest cent....

  • Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes....

    Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $82,800. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Direct Labor Hours Per Volume Unit Flutes 2,300 units 0.5 Clarinets 700 1.4 Oboes 1,200 1.1 If required, round all per unit answers to the nearest cent....

  • Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes....

    Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $99,120. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Volume Direct Labor Hours Per Unit Flutes 2,200 units 0.4 Clarinets 700 1.4 Oboes 1,400 1.2 If required, round all per unit answers to the nearest cent....

  • Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes....

    Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $127,840. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Volume Direct Labor Hours Per Unit Flutes 2,200 units 0.5 Clarinets 700 1.4 Oboes 1,400 1.2 If required, round all per unit answers to the nearest cent....

  • Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes....

    Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $94,200. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Volume Direct Labor Hours Per Unit Flutes 1,900 units 0.4 Clarinets 700 1.4 Oboes 1,400 1.0 If required, round all per unit answers to the nearest cent....

  • Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes....

    Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $135,660. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Volume Direct Labor Hours Per Unit Flutes 2,100 units 0.5 Clarinets 800 1.4 Oboes 1,400 1.0 If required, round all per unit answers to the nearest cent....

  • Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes....

    Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $114,000. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Volume Direct Labor Hours Per Unit Flutes 2,400 units 0.6 Clarinets 900 1.4 Oboes 1,100 1.0 If required, round all per unit answers to the nearest cent....

  • Single Plantwide Factory Overhead Rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes....

    Single Plantwide Factory Overhead Rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $2,948,125. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Volume Direct Labor Hours Per Unit Flutes 2,000 units 2.0 Clarinets 1,500 3.0 Oboes 1,750 1.5 a. Determine the single plantwide overhead rate. $ per direct labor...

  • Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes....

    Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $103,680. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hou per unit: Budgeted Production Direct Labor Hours Per Volume Unit Flutes 2,300 units 0.4 Clarinets 400 1.4 Oboes 1,400 1.0 If required, round all per unit answers to the nearest cent....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT