Question

Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. T
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer.a. Plantwide overhead rate=Budgeted Overheads/Budgeted labor hours for the whole plant.

Budgeted Overheads=82,800

Budgeted production volume(x) Direct Labor Hours(y) Budgeted labor hours(x*y)
2300 0.5 1150 hours
700 1.4 980 hours
1200 1.1 1320 hours

Total budgeted labor hours=1150+980+1320=3450 hrs

Single plantwide overhead rate=82,800/3450=24 per labor hour.

b.

Total Factory Overhead cost Per Unit Factory Overhead Cost
Flutes 1150*24=27600 27600/2300=12
Clarinets 980*24=23520 23520/700=33.6
Oboes 1320*24=31680 31680/1200=26.4
Total 82,800
Add a comment
Know the answer?
Add Answer to:
Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes....

    Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $112,200. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Volume Direct Labor Hours Per Unit Flutes 2,600 units 0.4 900 1.4 Clarinets Oboes 1,000 1.0 If required, round all per unit answers to the nearest cent....

  • Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes....

    Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $99,120. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Volume Direct Labor Hours Per Unit Flutes 2,200 units 0.4 Clarinets 700 1.4 Oboes 1,400 1.2 If required, round all per unit answers to the nearest cent....

  • Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes....

    Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $127,840. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Volume Direct Labor Hours Per Unit Flutes 2,200 units 0.5 Clarinets 700 1.4 Oboes 1,400 1.2 If required, round all per unit answers to the nearest cent....

  • Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes....

    Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $94,200. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Volume Direct Labor Hours Per Unit Flutes 1,900 units 0.4 Clarinets 700 1.4 Oboes 1,400 1.0 If required, round all per unit answers to the nearest cent....

  • Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes....

    Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $135,660. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Volume Direct Labor Hours Per Unit Flutes 2,100 units 0.5 Clarinets 800 1.4 Oboes 1,400 1.0 If required, round all per unit answers to the nearest cent....

  • Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes....

    Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $114,000. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Volume Direct Labor Hours Per Unit Flutes 2,400 units 0.6 Clarinets 900 1.4 Oboes 1,100 1.0 If required, round all per unit answers to the nearest cent....

  • Single Plantwide Factory Overhead Rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes....

    Single Plantwide Factory Overhead Rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $2,948,125. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Volume Direct Labor Hours Per Unit Flutes 2,000 units 2.0 Clarinets 1,500 3.0 Oboes 1,750 1.5 a. Determine the single plantwide overhead rate. $ per direct labor...

  • Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes....

    Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $103,680. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hou per unit: Budgeted Production Direct Labor Hours Per Volume Unit Flutes 2,300 units 0.4 Clarinets 400 1.4 Oboes 1,400 1.0 If required, round all per unit answers to the nearest cent....

  • Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes....

    Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $120,000. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Direct Labor Hours Per Volume Unit Flutes 0.4 Clarinets Oboes 3,000 units 800 1,300 If required, round all per unit answers to the nearest cent. a. Determine...

  • Unit Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and...

    Unit Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $101,040. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Direct Labor Hours Per Volume 2,700 units 0.8 500 1,300 If required, round all per unit answers to the nearest cent. a. Determine the single plantwide...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT