Single plantwide factory overhead rate
Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $99,120. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit:
Budgeted Production Volume | Direct Labor Hours Per Unit | ||||
Flutes | 2,200 | units | 0.4 | ||
Clarinets | 700 | 1.4 | |||
Oboes | 1,400 | 1.2 |
If required, round all per unit answers to the nearest cent.
a. Determine the single plantwide overhead
rate.
$ per direct labor hour
b. Use the overhead rate in (a) to determine the amount of total and per-unit overhead allocated to each of the three products.
Total Factory Overhead Cost |
Per Unit Factory Overhead Cost |
|
Flutes | $ | $ |
Clarinets | ||
Oboes | ||
Total | $ |
a. Determine the single plantwide overhead rate. | ||||||
Total Direct Labor Hours | ||||||
Flutes | =2200 units *0.4 hour per unit | 880 | ||||
Clarinets | =700 units *1.4 hours per unit | 980 | ||||
Oboes | =1400 units *1.2 hour per unit | 1680 | ||||
Total Hours | 3540 | |||||
Plantwide overhead rate = Total Overhead Cost / Total labor hours | ||||||
=$99,120/3540 | ||||||
=$28 per hour | ||||||
b. Use the overhead rate in (a) to determine the amount of total and per-unit overhead allocated to each of the three products. | ||||||
Product | Total Labor Hours | Total Overhead | Total Units | Overhead Per Unit | ||
a | b | c=b*$28 | d | e=c/d | ||
Flutes | 880 | $ 24,640 | 2200 | $ 11.20 | ||
Clarinets | 980 | $ 27,440 | 700 | $ 39.20 | ||
Oboes | 1680 | $ 47,040 | 1400 | $ 33.60 | ||
Total | 3540 | 99120 | 4300 | |||
Kindly give a positive rating if you are satisfied with this solution and please ask if you have any queries | ||||||
Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes....
Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $127,840. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Volume Direct Labor Hours Per Unit Flutes 2,200 units 0.5 Clarinets 700 1.4 Oboes 1,400 1.2 If required, round all per unit answers to the nearest cent....
Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $112,200. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Volume Direct Labor Hours Per Unit Flutes 2,600 units 0.4 900 1.4 Clarinets Oboes 1,000 1.0 If required, round all per unit answers to the nearest cent....
Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $82,800. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Direct Labor Hours Per Volume Unit Flutes 2,300 units 0.5 Clarinets 700 1.4 Oboes 1,200 1.1 If required, round all per unit answers to the nearest cent....
Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $94,200. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Volume Direct Labor Hours Per Unit Flutes 1,900 units 0.4 Clarinets 700 1.4 Oboes 1,400 1.0 If required, round all per unit answers to the nearest cent....
Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $135,660. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Volume Direct Labor Hours Per Unit Flutes 2,100 units 0.5 Clarinets 800 1.4 Oboes 1,400 1.0 If required, round all per unit answers to the nearest cent....
Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $114,000. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Volume Direct Labor Hours Per Unit Flutes 2,400 units 0.6 Clarinets 900 1.4 Oboes 1,100 1.0 If required, round all per unit answers to the nearest cent....
Single Plantwide Factory Overhead Rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $2,948,125. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Volume Direct Labor Hours Per Unit Flutes 2,000 units 2.0 Clarinets 1,500 3.0 Oboes 1,750 1.5 a. Determine the single plantwide overhead rate. $ per direct labor...
Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $103,680. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hou per unit: Budgeted Production Direct Labor Hours Per Volume Unit Flutes 2,300 units 0.4 Clarinets 400 1.4 Oboes 1,400 1.0 If required, round all per unit answers to the nearest cent....
Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $120,000. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Direct Labor Hours Per Volume Unit Flutes 0.4 Clarinets Oboes 3,000 units 800 1,300 If required, round all per unit answers to the nearest cent. a. Determine...
Unit Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $101,040. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Direct Labor Hours Per Volume 2,700 units 0.8 500 1,300 If required, round all per unit answers to the nearest cent. a. Determine the single plantwide...