Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $127,840. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit:
Budgeted Production Volume | Direct Labor Hours Per Unit | ||||
Flutes | 2,200 | units | 0.5 | ||
Clarinets | 700 | 1.4 | |||
Oboes | 1,400 | 1.2 |
If required, round all per unit answers to the nearest cent.
a. Determine the single plantwide overhead
rate.
$ per direct labor hour
b. Use the overhead rate in (a) to determine the amount of total and per-unit overhead allocated to each of the three products.
Total Factory Overhead Cost |
Per Unit Factory Overhead Cost |
|
Flutes | $ | $ |
Clarinets | ||
Oboes | ||
Total | $ |
Requirement 1
single Plantwide overhead rate = $34 per direct labor hour
Working
Flutes | Clarinets | Oboes | Total | |
Budgeted Production Volume | 2200 | 700 | 1400 | |
Direct Labor Hours Per Unit | 0.5 | 1.4 | 1.2 | |
Total Hours needed | 1100 | 980 | 1680 | 3760 |
Overhead /Total Labor hour = Overhead rate
127840/3760= $34 per Hour
Requirement 2
Total Factory Overhead cost |
Per Unit Factory Overhead Cost |
|
Flutes | $ 37,400 | $ 17.00 |
Clarinets | $ 33,320 | $ 47.60 |
Oboes | $ 57,120 | $ 40.80 |
Total | $ 127,840 |
Working
Cost assigned to Flutes | |||
Activity name | Activity Rates | Activity | ABC Cost |
(A) | (B) | (A x B) | |
Overhead | $ 34.00 | 1,100.00 | $ 37,400.00 |
.
Cost assigned to Clarinets | |||
Activity name | Activity Rates | Activity | ABC Cost |
(A) | (B) | (A x B) | |
Overhead | $ 34.00 | 980 | $ 33,320.00 |
.
Cost assigned to Oboes | |||
Activity rate(A) | Activity Driver Incurred (B) | Overhead Assigned (C=A*B) | |
Overhead | $ 34.00 | 1680 | $ 57,120.00 |
Per unit cost = Overhead applied / units produced
Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes....
Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $112,200. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Volume Direct Labor Hours Per Unit Flutes 2,600 units 0.4 900 1.4 Clarinets Oboes 1,000 1.0 If required, round all per unit answers to the nearest cent....
Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $82,800. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Direct Labor Hours Per Volume Unit Flutes 2,300 units 0.5 Clarinets 700 1.4 Oboes 1,200 1.1 If required, round all per unit answers to the nearest cent....
Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $99,120. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Volume Direct Labor Hours Per Unit Flutes 2,200 units 0.4 Clarinets 700 1.4 Oboes 1,400 1.2 If required, round all per unit answers to the nearest cent....
Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $94,200. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Volume Direct Labor Hours Per Unit Flutes 1,900 units 0.4 Clarinets 700 1.4 Oboes 1,400 1.0 If required, round all per unit answers to the nearest cent....
Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $135,660. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Volume Direct Labor Hours Per Unit Flutes 2,100 units 0.5 Clarinets 800 1.4 Oboes 1,400 1.0 If required, round all per unit answers to the nearest cent....
Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $114,000. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Volume Direct Labor Hours Per Unit Flutes 2,400 units 0.6 Clarinets 900 1.4 Oboes 1,100 1.0 If required, round all per unit answers to the nearest cent....
Single Plantwide Factory Overhead Rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $2,948,125. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Volume Direct Labor Hours Per Unit Flutes 2,000 units 2.0 Clarinets 1,500 3.0 Oboes 1,750 1.5 a. Determine the single plantwide overhead rate. $ per direct labor...
Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $103,680. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hou per unit: Budgeted Production Direct Labor Hours Per Volume Unit Flutes 2,300 units 0.4 Clarinets 400 1.4 Oboes 1,400 1.0 If required, round all per unit answers to the nearest cent....
Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $120,000. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Direct Labor Hours Per Volume Unit Flutes 0.4 Clarinets Oboes 3,000 units 800 1,300 If required, round all per unit answers to the nearest cent. a. Determine...
Unit Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $101,040. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Direct Labor Hours Per Volume 2,700 units 0.8 500 1,300 If required, round all per unit answers to the nearest cent. a. Determine the single plantwide...