Single Plantwide Factory Overhead Rate
Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $2,948,125. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit:
Budgeted Production Volume | Direct Labor Hours Per Unit | ||||
Flutes | 2,000 | units | 2.0 | ||
Clarinets | 1,500 | 3.0 | |||
Oboes | 1,750 | 1.5 |
a.
Determine the single plantwide overhead rate.
$ per direct labor hour
b. Use the overhead rate in (a) to determine the amount of total and per-unit overhead allocated to each of the three products, rounded to the nearest dollar.
Total Factory Overhead Cost |
Per Unit Factory Overhead Cost |
|
Flutes | $ | $ |
Clarinets | ||
Oboes | ||
Total | $ |
Budgeted Production Volumes | Direct Labor Hours | Total Direct Labor Hours | ||
Flutes | 2,000 | 2.00 | 4,000 | |
Clarinets | 1,500 | 3.00 | 4,500 | |
Oboes | 1,750 | 1.50 | 2,625 | |
11,125 | ||||
A | ||||
Total Factory OH | 29,48,125 | a | ||
Total Direct Labor Hours | 11,125 | b | ||
Plantwide OH Rate | 265.00 | a/b | ||
B | ||||
Total Factory OH Cost | Per Unit Factory OH Cost | |||
Flutes(4000*265) | 10,60,000 | 530.00 | ||
Clarinets(4500*265) | 11,92,500 | 795.00 | ||
Oboes(2625*265) | 6,95,625 | 397.50 | ||
Total | 29,48,125 | |||
Single Plantwide Factory Overhead Rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes....
Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $112,200. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Volume Direct Labor Hours Per Unit Flutes 2,600 units 0.4 900 1.4 Clarinets Oboes 1,000 1.0 If required, round all per unit answers to the nearest cent....
Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $82,800. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Direct Labor Hours Per Volume Unit Flutes 2,300 units 0.5 Clarinets 700 1.4 Oboes 1,200 1.1 If required, round all per unit answers to the nearest cent....
Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $99,120. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Volume Direct Labor Hours Per Unit Flutes 2,200 units 0.4 Clarinets 700 1.4 Oboes 1,400 1.2 If required, round all per unit answers to the nearest cent....
Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $127,840. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Volume Direct Labor Hours Per Unit Flutes 2,200 units 0.5 Clarinets 700 1.4 Oboes 1,400 1.2 If required, round all per unit answers to the nearest cent....
Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $94,200. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Volume Direct Labor Hours Per Unit Flutes 1,900 units 0.4 Clarinets 700 1.4 Oboes 1,400 1.0 If required, round all per unit answers to the nearest cent....
Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $135,660. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Volume Direct Labor Hours Per Unit Flutes 2,100 units 0.5 Clarinets 800 1.4 Oboes 1,400 1.0 If required, round all per unit answers to the nearest cent....
Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $114,000. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Volume Direct Labor Hours Per Unit Flutes 2,400 units 0.6 Clarinets 900 1.4 Oboes 1,100 1.0 If required, round all per unit answers to the nearest cent....
Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $103,680. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hou per unit: Budgeted Production Direct Labor Hours Per Volume Unit Flutes 2,300 units 0.4 Clarinets 400 1.4 Oboes 1,400 1.0 If required, round all per unit answers to the nearest cent....
Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $120,000. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Direct Labor Hours Per Volume Unit Flutes 0.4 Clarinets Oboes 3,000 units 800 1,300 If required, round all per unit answers to the nearest cent. a. Determine...
Unit Single plantwide factory overhead rate Bach Instruments Inc. makes three musical instruments: flutes, clarinets, and oboes. The budgeted factory overhead cost is $101,040. Overhead is allocated to the three products on the basis of direct labor hours. The products have the following budgeted production volume and direct labor hours per unit: Budgeted Production Direct Labor Hours Per Volume 2,700 units 0.8 500 1,300 If required, round all per unit answers to the nearest cent. a. Determine the single plantwide...