Project A |
Project B |
Incremental CF of B – A |
|
Initial Investment |
-1,000,000 |
-2,000,000 |
-1,000,000 |
Cash Flows |
300,000 |
500,000 |
200,000 |
a. Incremental discounted rate of return
Using the trial and error method
Life of the projects = 10 years
Let the rate of interest is 14%
At 14% the NPW is
NPW at 14% = -1,000,000 + 200,000 (P/A, 14%, 10)
NPW at 14% = -1,000,000 + 200,000 (5.2161) = 43,220
Since the PW is positive increase the rate of interest to 16% for getting a negative NPW
NPW at 16%
NPW at 16% = -1,000,000 + 200,000 (P/A, 16%, 10)
NPW at 16% = -1,000,000 + 200,000 (4.8332) = -33,360
Using interpolation
Rate of return = 14% + [43,220 – 0 ÷ 43,220 – (-33,360)]*2% = 15.1%
Incremental Discount rate of return will be 15%
Answer – iii. 15%
b. If MARR is 10%, at what year project B will be attractive.
Calculating the discounted payback period of Project B
Year |
CF |
PV Factor |
DCF |
CCF |
0 |
($2,000,000) |
1 |
($2,000,000) |
($2,000,000) |
1 |
$500,000 |
0.91 |
$454,545.45 |
($1,545,454.55) |
2 |
$500,000 |
0.83 |
$413,223.14 |
($1,132,231.40) |
3 |
$500,000 |
0.75 |
$375,657.40 |
($756,574) |
4 |
$500,000 |
0.68 |
$341,506.73 |
($415,067.28) |
5 |
$500,000 |
0.62 |
$310,460.66 |
($104,606.62) |
6 |
$500,000 |
0.56 |
$282,236.97 |
$177,630.35 |
Discounted Payback Period = 5 + [-104,606.62 – 0 ÷ -104,606.62 – (177,630.35)]*1 = 5.37 years
Answer – i. 5 years
For project A, the expected investment is $ 1 M and annual Cash Flows are 300K....
Capital budgeting criteria: mutually exclusive projects Project S costs $12,000 and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L costs $49,000 and its expected cash flows would be $12,900 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. I. Project L, since the NPVL > NPVS. II. Both Projects S and L, since both projects have NPV's > 0....
(Discounted payback period) Gio's Restaurants is considering a project with the following expected cash flows: Year Project Cash Flow (millions) $(210) AWNO If the project's appropriate discount rate is 11 percent, what is the project's discounted payback period? The project's discounted payback period is years. (Round to two decimal places.) (Mutually exclusive projects and NPV) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash flows: Project A Project B Year Cash Flow...
Project S costs $11,000 and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L costs $27,000 and its expected cash flows would be $7,500 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? Select the correct answer. I. Neither S or L, since each project's NPV < 0. II. Project L, since the NPVL > NPVS. III. Both Projects S and L, since both...
(b) A company is evaluating a project for which the costs and expected cash flows are as follows: Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 -$2,200,000 $400,000 $535,000 $650,000 $700,000 $880,000 The company uses a discount rate of 10% for all projects. Given the information: i. Determine NPV of the project. (2 marks) Determine payback period of the project. (1.5 marks) Determine discounted payback period of the project. (2 marks) iv. Will the payback period...
Problem 11-11 Capital budgeting criteria: mutually exclusive projects Project S costs $16,000 and its expected cash flows would be $5,500 per year for 5 years. Mutually exclusive Project L costs $35,500 and its expected cash flows would be $8,600 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. O I. Project S, since the NPVs > NPVL. O II. Both Projects S and L, since both projects...
Problem 11-11 Capital budgeting criteria: mutually exclusive projects Project S costs $15,000 and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L costs $30,000 and its expected cash flows would be $9,600 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. O I. Project S, since the NPVS > NPVL. II. Both Projects and L, since both projects have NPV's...
1) A project has annual cash flows of $5,000 for the next 10 years and then $6,500 each year for the following 10 years. The IRR of this 20-year project is 12%. If the firm's WACC is 11%, what is the project's NPV? Do not round intermediate calculations. Round your answer to the nearest cent. 2) Project S costs $12,000 and its expected cash flows would be $7,000 per year for 5 years. Mutually exclusive Project L costs $25,000 and...
Project S has a cost of $10,000 and is expected to produce benefits (cash flows) of $3,500 per year for 5 years. Project L costs $25,000 and is expected to produce cash flows of $8,000 per year for 5 years. a. Calculate the two projects' NPVS, assuming a cost of capital of 14%. Round your answers to the nearest cent Project S Project L Which project would be selected, assuming they are mutually exclusive? -Select b. Calculate the two projects'...
A project with an initial investment of $439,700 will generate equal annual cash flows over its 10-year life. The project has a required return of 8.1 percent. What is the minimum annual cash flow required to accept the project?
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S costs $18,000 and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L costs $29,500 and its expected cash flows would be $9,200 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have NPV's > 0. b. Neither Project S nor L, since each...