Question

Verizox Company uses a job order cost system with manufacturing overhead applied to products based on direct labor hours. At the beginning of the most recent year, the company estimated its manufacturing overhead cost at $180,420. Estimated direct labor cost was $469,480 for 19,400 hours. Actual costs for the most recent month are summarized here: Item Description Direct labor (1,940 hours) Indirect costs Total Cost $46,949 Indirect labor Indirect materials Factory rent Factory supervision Factory depreciation Factory janitorial work Factory insurance General and administrative salaries Selling expenses 2,450 3,430 4,790 5,700 1,240 1,820 4,130 5,370 Required 1. Calculate the predetermined overhead rate. (Round your answer to 2 decimal places.) ined Overhead Rate Per DL Hour 2. Calculate the amount of applied manufacturing overhead. 3. Calculate actual manufacturing overhead costs. Overhead Costs

4. Compute over- or underapplied overhead. (Input the amount as positive value.) Overhead

0 0
Add a comment Improve this question Transcribed image text
Answer #1
1 Predetermined overhead rate = Estimated Manufacturing cost/Direct labour hours
= $180,420/19,400 hours
= 9.30 Per DL hours
2 Applied manufacturing overhead = Predetermined overhead rate * Actual Direct Labour hours
= 9.30 per DL hours * 1940 hours
= $18,042
3 Actual Manufacturing overhead
Indirect Labour =                          2,450
Indirect material =                          3,430
Factory Rent =                          3,310
Factory Supervision =                          4,790
Factory Depreciation =                          5,700
Factory Janital work =                          1,240
Factory Insuracne =                          1,820
Actual Manufacturing overhead $22,740
4 Actual overhead = $22,740
Applied overhead = $18,042
Balance(Underapplied) = $4,698
Add a comment
Know the answer?
Add Answer to:
Verizox Company uses a job order cost system with manufacturing overhead applied to products based on...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Verizox Company uses a job order cost system with manufacturing overhead applied to products based on...

    Verizox Company uses a job order cost system with manufacturing overhead applied to products based on direct labor hours. At the beginning of the most recent year, the company estimated its manufacturing overhead cost at $171,990. Estimated direct labor cost was $455,490 for 18,900 hours. Actual costs for the most recent month are summarized here: Item Description Total Cost Direct labor (1,890 hours) $ 45,550 Indirect costs Indirect labor 2,550 Indirect materials 3,360 Factory rent 3,390 Factory supervision 4,850 Factory...

  • Verizox Company uses a job order cost system with manufacturing overhead applied to products based on...

    Verizox Company uses a job order cost system with manufacturing overhead applied to products based on direct labor hours. At the beginning of the most recent year, the company estimated its manufacturing overhead cost at $169,260. Estimated direct labor cost was $453,180 for 18,200 hours. Actual costs for the most recent month are summarized here: Total Cost $ 45,319 Item Description Direct labor (1,820 hours) Indirect costs Indirect labor Indirect materials Factory rent Factory supervision Factory depreciation Factory janitorial work...

  • Verizox Company uses a job order cost system with manufacturing overhead applied to products based on...

    Verizox Company uses a job order cost system with manufacturing overhead applied to products based on direct labor hours. At the beginning of the most recent year, the company estimated its manufacturing overhead cost at $197,000. Estimated direct labor cost was $486,590 for 19,700 hours. Actual costs for the most recent month are summarized here:    Item Description Total Cost Direct labor (1,970 hours) $ 48,660 Indirect costs Indirect labor 2,410 Indirect materials 3,320 Factory rent 3,340 Factory supervision 4,780 Factory...

  • Verizox Company uses a job order cost system with manufacturing overhead applied to products based on...

    Verizox Company uses a job order cost system with manufacturing overhead applied to products based on direct labor hours. At the beginning of the most recent year, the company estimated its manufacturing overhead cost at $181.240 Estimated direct labor cost was $490,530 for 19,700 hours Actual costs for the most recent month are summarized here Total Cost 49.054 hem Description Direct labor (1,970 hours) Indirect oosts Indirect labor Indirect materials Factory rent Factory supervision Factory depreciation Factory janitorial work Factory...

  • Verizox Company uses a job order cost system with manufacturing overhead applied to products based on...

    Verizox Company uses a job order cost system with manufacturing overhead applied to products based on direct labor hours. At the beginning of the most recent year, the company estimated its manufacturing overhead cost at $173,810. Estimated direct labor cost was $441,210 for 19,100 hours. Actual costs for the most recent month are summarized here: Total Cost $44,122 Item Description Direct labor (1,910 hours) Indirect costs Indirect labor Indirect materials Factory rent Factory supervision Factory depreciation Factory janitorial work Factory...

  • Verizox Company uses a job order cost system with manufacturing overhead applied to products based on...

    Verizox Company uses a job order cost system with manufacturing overhead applied to products based on direct labor hours. At the beginning of the most recent year, the company estimated its manufacturing overhead cost at $177,510. Estimated direct labor cost was $435,540 for 18,300 hours. Actual costs for the most recent month are summarized here: Item Description Total Cost Direct labor (1,830 hours) $ 43,555 Indirect costs Indirect labor 2,420 Indirect materials 3,420 Factory rent 3,390 Factory supervision 4,770 Factory...

  • Verizox Company uses a job order cost system with manufacturing overhead applied to products based on...

    Verizox Company uses a job order cost system with manufacturing overhead applied to products based on direct labor hours. At the beginning of the most recent year, the company estimated its manufacturing overhead cost at $173,880. Estimated direct labor cost was $438,480 for 18,900 hours. Actual costs for the most recent month are summarized here: Total Cost $43,849 Item Description Direct labor (1,890 hours) Indirect costs Indirect labor Indirect materials Factory rent Factory supervision Factory depreciation Factory janitorial work Factory...

  • Verizox Company uses a job order cost system with manufacturing overhead applied to products based on...

    Verizox Company uses a job order cost system with manufacturing overhead applied to products based on direct labor hours. At the beginning of the most recent year, the company estimated its manufacturing overhead cost at $172,040. Estimated direct labor cost was $437,580 for 18,700 hours. Actual costs for the most recent month are summarized here: Item Description Total Cost Direct labor (1,870 hours) $ 43,759 Indirect costs Indirect labor 2,530 Indirect materials 3,340 Factory rent 3,360 Factory supervision 4,710 Factory...

  • Verizox Company uses a job order cost system with manufacturing overhead applied to products based on...

    Verizox Company uses a job order cost system with manufacturing overhead applied to products based on direct labor hours. At the beginning of the most recent year, the company estimated its manufacturing overhead cost at $192,910. Estimated direct labor cost was $456,490 for 19,100 hours. Actual costs for the most recent month are summarized here: Total Cost $45, 650 Item Description Direct labor (1,910 hours) Indirect costs Indirect labor Indirect materials Factory rent Factory supervision Factory depreciation Factory janitorial work...

  • Verizox Company uses a job order cost system with manufacturing overhead applied to products based on...

    Verizox Company uses a job order cost system with manufacturing overhead applied to products based on direct labor hours. At the beginning of the most recent year, the company estimated its manufacturing overhead cost at $185,000. Estimated direct labor cost was $460,650 for 18,500 hours. Actual costs for the most recent month are summarized here:    Item Description Total Cost Direct labor (1,850 hours) $ 46,066 Indirect costs Indirect labor 2,410 Indirect materials 3,340 Factory rent 3,370 Factory supervision 4,820 Factory...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT