Question

Verizox Company uses a job order cost system with manufacturing overhead applied to products based on...

Verizox Company uses a job order cost system with manufacturing overhead applied to products based on direct labor hours. At the beginning of the most recent year, the company estimated its manufacturing overhead cost at $185,000. Estimated direct labor cost was $460,650 for 18,500 hours.

Actual costs for the most recent month are summarized here:   

Item Description Total Cost
Direct labor (1,850 hours) $ 46,066
Indirect costs
Indirect labor 2,410
Indirect materials 3,340
Factory rent 3,370
Factory supervision 4,820
Factory depreciation 5,720
Factory janitorial work 1,290
Factory insurance 1,850
General and administrative salaries 4,150
Selling expenses 5,420


Required:
1.
Calculate the predetermined overhead rate. (Round your answer to 2 decimal places.)



2. Calculate the amount of applied manufacturing overhead.



3. Calculate actual manufacturing overhead costs.



4. Compute over- or underapplied overhead. (Input the amount as positive value.)

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer :-

1. Predetermined Overhead Rate = Estimated Overhead Cost / Estimated Direct Labor Hour

Predetermined Overhead Rate = $185,000 / 18,500

Predetermined Overhead Rate = $10

2. Applied Manufacturing Overhead = $10 * 1850

Applied Manufacturing Overhead = $18,500

3. Actual Manufacturing Overhead Cost = Indirect Labor + Indirect Material + Factory rent + Factory supervision + Factory Depreciation + Factory Janitorial work + Factory Insurance

Actual Manufacturing overhead cost = $2,410 + $3,340 + $3,370 + $4,820 + $5,720 + $1,290 + $1,850

Actual Manufacturing overhead cost = $22,800

4. Over-or underapplied overhead = Actual Manufacturing overhead - Applied Manufacturing overhead

Underapplied Manufacturing Overhead = $22,800 - $18,500

Underapplied Manufacturing Overhead = $4,300

If you have any query ask in comment section. If you like the answer plz rate. Thanks

Add a comment
Know the answer?
Add Answer to:
Verizox Company uses a job order cost system with manufacturing overhead applied to products based on...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Verizox Company uses a job order cost system with manufacturing overhead applied to products based on...

    Verizox Company uses a job order cost system with manufacturing overhead applied to products based on direct labor hours. At the beginning of the most recent year, the company estimated its manufacturing overhead cost at $197,000. Estimated direct labor cost was $486,590 for 19,700 hours. Actual costs for the most recent month are summarized here:    Item Description Total Cost Direct labor (1,970 hours) $ 48,660 Indirect costs Indirect labor 2,410 Indirect materials 3,320 Factory rent 3,340 Factory supervision 4,780 Factory...

  • Verizox Company uses a job order cost system with manufacturing overhead applied to products based on...

    Verizox Company uses a job order cost system with manufacturing overhead applied to products based on direct labor hours. At the beginning of the most recent year, the company estimated its manufacturing overhead cost at $173,810. Estimated direct labor cost was $441,210 for 19,100 hours. Actual costs for the most recent month are summarized here: Total Cost $44,122 Item Description Direct labor (1,910 hours) Indirect costs Indirect labor Indirect materials Factory rent Factory supervision Factory depreciation Factory janitorial work Factory...

  • Verizox Company uses a job order cost system with manufacturing overhead applied to products based on...

    Verizox Company uses a job order cost system with manufacturing overhead applied to products based on direct labor hours. At the beginning of the most recent year, the company estimated its manufacturing overhead cost at $169,260. Estimated direct labor cost was $453,180 for 18,200 hours. Actual costs for the most recent month are summarized here: Total Cost $ 45,319 Item Description Direct labor (1,820 hours) Indirect costs Indirect labor Indirect materials Factory rent Factory supervision Factory depreciation Factory janitorial work...

  • Verizox Company uses a job order cost system with manufacturing overhead applied to products based on...

    Verizox Company uses a job order cost system with manufacturing overhead applied to products based on direct labor hours. At the beginning of the most recent year, the company estimated its manufacturing overhead cost at $173,880. Estimated direct labor cost was $438,480 for 18,900 hours. Actual costs for the most recent month are summarized here: Total Cost $43,849 Item Description Direct labor (1,890 hours) Indirect costs Indirect labor Indirect materials Factory rent Factory supervision Factory depreciation Factory janitorial work Factory...

  • Verizox Company uses a job order cost system with manufacturing overhead applied to products based on...

    Verizox Company uses a job order cost system with manufacturing overhead applied to products based on direct labor hours. At the beginning of the most recent year, the company estimated its manufacturing overhead cost at $169,260. Estimated direct labor cost was $457,560 for 18,600 hours. Actual costs for the most recent month are summarized here: Item Description Total Cost Direct labor (1,860 hours) $ 45,757 Indirect costs Indirect labor 2,520 Indirect materials 3,470 Factory rent 3,350 Factory supervision 4,840 Factory...

  • 4. Verizox Company uses a job order cost system with manufacturing overhead applied to products based...

    4. Verizox Company uses a job order cost system with manufacturing overhead applied to products based on direct labor hours. At the beginning of the most recent year, the company estimated its manufacturing overhead cost at $188,160. Estimated direct labor cost was $491,960 for 19,600 hours. Actual costs for the most recent month are summarized here: $ Total Cost 49,197 Item Description Direct labor (1,960 hours) Indirect costs Indirect labor Indirect materials Factory rent Factory supervision Factory depreciation Factory janitorial...

  • Verizox Company uses a job order cost system with manufacturing overhead applied to products based on...

    Verizox Company uses a job order cost system with manufacturing overhead applied to products based on direct labor hours. At the beginning of the most recent year, the company estimated its manufacturing overhead cost at $171,120. Estimated direct labor cost was $448,960 for 18,400 hours. Actual costs for the most recent month are summarized here: Total Cost $44,897 Item Description Direct labor (1,840 hours) Indirect costs Indirect labor Indirect materials Factory rent Factory supervision Factory depreciation Factory janitorial work Factory...

  • Verizox Company uses a job order cost system with manufacturing overhead applied to products based on...

    Verizox Company uses a job order cost system with manufacturing overhead applied to products based on direct labor hours. At the beginning of the most recent year, the company estimated its manufacturing overhead cost at $171,990. Estimated direct labor cost was $455,490 for 18,900 hours. Actual costs for the most recent month are summarized here: Item Description Total Cost Direct labor (1,890 hours) $ 45,550 Indirect costs Indirect labor 2,550 Indirect materials 3,360 Factory rent 3,390 Factory supervision 4,850 Factory...

  • Verizox Company uses a job order cost system with manufacturing overhead applied to products based on...

    Verizox Company uses a job order cost system with manufacturing overhead applied to products based on direct labor hours. At the beginning of the most recent year, the company estimated its manufacturing overhead cost at $177,510. Estimated direct labor cost was $435,540 for 18,300 hours. Actual costs for the most recent month are summarized here: Item Description Total Cost Direct labor (1,830 hours) $ 43,555 Indirect costs Indirect labor 2,420 Indirect materials 3,420 Factory rent 3,390 Factory supervision 4,770 Factory...

  • Verizox Company uses a job order cost system with manufacturing overhead applied to products based on...

    Verizox Company uses a job order cost system with manufacturing overhead applied to products based on direct labor hours. At the beginning of the most recent year, the company estimated its manufacturing overhead cost at $172,040. Estimated direct labor cost was $437,580 for 18,700 hours. Actual costs for the most recent month are summarized here: Item Description Total Cost Direct labor (1,870 hours) $ 43,759 Indirect costs Indirect labor 2,530 Indirect materials 3,340 Factory rent 3,360 Factory supervision 4,710 Factory...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT