Given the following: Project A: CF0 = -$23,000;
CF1 = $6,000; CF2 = $8,500; CF3 =
$15,100
Project B: CF0 = -$20,000; CF1 = $4,000;
CF2 = $7,550; CF3 = $14,600
What is the crossover rate (r)?
Given the following: Project A: CF0 = -$23,000; CF1 = $6,000; CF2 = $8,500; CF3 =...
Given the following: Project A: CF, = -$23,560; CF1 = $6,700; CF2 = $9,200; CF3 = $15,800 Project B: CF = -$19,860; CF1 = $4,140; CF2 = $8,110; CF3 = $15,160 What is the crossover rate (r)? (Round answer to 2 decimal places, e.g. 25.25%.) Crossover rate %
CF0 -35578 CF1 7400 CF2 42700 CF3 40400 CF4 33600 CF5 48500 CF6 24300 Investor's Rate 10 Given the above cash flows and investor's required rate of return, what is the Net Present Value? Express your answers as XXXX.XX. CF0 -118000 CF1 50,700 CF2 25,700 CF3 4,400 CF4 10,400 CF5 24,400 CF6 51,400 IRR ? Given the above cash flows, what is the internal rate of return? (express your answers as a percent without the % sign e.g. xx.xx )...
CF0 -50020 CF1 34100 CF2 45600 CF3 35700 CF4 40400 CF5 47000 CF6 23700 Investor's Rate 13 Given the above cash flows and investor's required rate of return, what is the Modified Internal Rate of Return (Financial Manager's Rate of Return)? (Express your answers as XX.XX percent without the %. For example if your calculator says 12.24 then enter that. If you use Excel and your answer in decimal is .1224, enter 12.24)
1. You must analyze the cash flows of two projects, S and L. Project S: CF0 = -1500; CF1 = 800; CF2 = 700; CF3 = 100; CF4 = 600 Project L: CF0 = -1500; CF1 = 200; CF2 = 600; CF3 = 900; CF4 = 700 Given a required rate of return of 10%, what is the IRR of the better project? (Note: the better project may not be the one with the higher IRR)
a. Find present value of the following cash flows at 3% rate: CF0 = -1000; CF1 = 300; CF2 = 560; CF3 = -90; CF4 = 250. b. What is the future value of these cash flows?
Consider a project with the following cash flows: CF0=$100 million, CF1=$-60 million, CF2=$-60 million. Should you accept or reject the project if the discount rate is 12%? Group of answer choices Flip a coin Reject Accept
Ellmann Systems is considering a project that has the following cash flow and WACC data. The WACC is 7%. The CF0 = -$1,000, CF1 = $331, CF2 = $473, and CF3 = $597. What is the project's NPV? Computer Consultants Inc. is considering a project that has the following cash flow and WACC data. The WACC is 10.2%. The CF0 = -$1,000, CF1 = $450, CF2 = $450, and CF3 = $450. What is the project's MIRR? Garner Inc. is...
Intro You've estimated the following cash flows (in $ million) for two mutually exclusive projects: Year Project A Project B 0 -28 -43 1 30 45 2 40 50 Attempt 1/5 for 10 pts. Part 1 What is the crossover rate, i.e., the discount rate at which both projects have the same NPV? The crossover rate is the discount rate at which both projects have the same NPV: NPV(A) = NPV(B) ⇔ NPV(A) - NPV(B) = 0 ⇔ NPV(A-B) =...
950 Sweet Inc. has two projects as follows: Project Initial CF CF1 CF2 CF3 CF4 А -2,450 850 1,200 1,900 -3,000 750 1,500 1,050 3,900 Sweet set 2.6 years as a cut-off period for screening projects and the discount rate is 14 percent. Which project(s) will be selected if the company uses the discounted payback period method? (Round intermediate calculations to 5 decimal places, B Project A payback period years Project B payback period years will be selected Neither project...
1. Consider two projects with the following (after-tax) cash flows. Project A: CF1 50, CF2 55, CF3 85. Project B: CF1 140. Both projects require an initial investment of 100. Assume the cost of capital for both projects is r 5%. (a) Compute NPV and IRR for project A. (b) Compute NPV and IRR for project B. (c) Assume you replicate project B twice, i.e. reinvest 100 in t 1 and t2. Compute the NPV and IRR of the replicated...