Dohini Manufacturing Company had the following 12 months of data on purchasing cost and number of purchase orders.
Month | Purchasing Cost | Number of Purchase Orders |
||
January | $18,860 | 370 | ||
February | 18,065 | 330 | ||
March | 19,250 | 370 | ||
April | 18,050 | 410 | ||
May | 19,345 | 400 | ||
June | 19,500 | 450 | ||
July | 19,670 | 460 | ||
August | 20,940 | 560 | ||
September | 19,430 | 440 | ||
October | 20,020 | 500 | ||
November | 18,800 | 470 | ||
December | 19,340 | 480 |
The controller for Dohini Manufacturing ran regression on the data, and the coefficients shown by the regression program are:
Intercept | 15,021 (rounded to the nearest dollar) |
X variable 1 | 9.74 (rounded to the nearest cent) |
Required:
A. Construct the cost formula for the purchasing activity showing the fixed cost and the variable rate.
Total purchasing cost | = | $ | + | ($ × Purchase orders) |
B. If Dohini Manufacturing Company estimates that next month will have 430 purchase orders, what is the total estimated purchasing cost for that month? (Round your answer to the nearest dollar.)
C. What if Dohini
Manufacturing wants to estimate purchasing cost for the coming year
and expects 5,340 purchase orders? What will estimated total
purchasing cost be? (Round your answer to the nearest dollar.) What
is the total fixed purchasing cost?
Answer A:
Working:
Given:
Intercept | 15,021 (rounded to the nearest dollar) |
X variable 1 | 9.74 (rounded to the nearest cent) |
Hence:
Fixed cost = Intercept = $15,021
Variable cost per purchase order = $9.74
Hence the equation will be:
Total purchasing cost = $15,021 + $9.74 x Number of Purchase Orders
Answer B:
Company estimates that next month will have 430 purchase orders:
Total purchasing cost = $15,021 + $9.74 x Number of Purchase Orders
= 15021 + 9.74 * 430
= $19,209.20
Total estimated purchasing cost for that month = $19,209
Answer C:
Company expects 5,340 purchase orders for coming year (12 months)
The Monthly purchase cost equation is:
Total purchasing cost = $15,021 + $9.74 x Number of Purchase Orders
Hence:
Estimated total purchasing cost for coming year = 15021 * 12 + 5340 * 9.74 = $232,263.60
Total fixed purchasing cost = 15021 * 12 =$180,252
Hence:
Estimated total purchasing cost for coming year = $232,264
Total fixed purchasing cost = $180,252
Using Regression Results to Construct and Apply a Cost Formula Dohini Manufacturing Company had the following...
Using Regression Results to Construct and Apply a Cost Formula Dohini Manufacturing Company had the following 12 months of data on purchasing cost and number of purchase orders. Number of Purchasing Purchase Orders Month Cost January $18,860 370 February 18,065 330 March 19,250 370 April 18,050 410 May 19,345 400 June 19,500 450 July 19,670 460 August 20,940 560 September 19,430 440 October 20,020 500 November 18,800 470 December 19,340 480 The controller for Dohini Manufacturing ran regression on the...
Dohini Manufacturing Company had the following 12 months of data on purchasing cost and number of purchase orders. Number of Purchasing Purchase Month Cost Orders January $18,860 370 February 18,040 330 March 19,250 370 April 18,050 410 May 19,345 400 June 19,500 450 July 19,670 460 August 20,920 570 September 19,430 440 October 20,020 500 November 18,800 470 December 19,340 480 Required: 1. Determine the high point and the low point. Month with high number of purchase orders Month with...
Using Regression to Calculate Fixed Cost, Calculate the Variable Rate, Construct a Cost Formula, and Determine Budgeted Cost Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were collected: Month Labor Cost Employee Hours January $7,100 360 February 8,140 550 March 9,899 630 April 9,787 600 May 8,490 480 June 7,450 350 July 9,490 570 August 7,531 310 Coefficients shown by a regression program for Pizza Vesuvio's data are: Intercept 4,562 X Variable 8.15 In your calculations, round...
Using Regression to Calculate Fixed Cost, Calculate the Variable Rate, Construct a Cost Formula, and Determine Budgeted Cost Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were collected: Month Labor Cost Employee Hours January $6,900 360 February 8,140 550 March 9,899 630 April 9,787 610 May 8,490 480 June 7,450 350 July 9,490 570 August 7,531 310 Coefficients shown by a regression program for Pizza Vesuvio's data are: Intercept 4,452 X Variable 8.31 In your calculations, round...
Show Me How eBook Using Regression to Calculate Fixed Cost, Calculate the Variable Rate, Construct a Cost Formula, and Determine Budgeted Cost Pizza Vesuvio makes specialty pizzas. Data for the past 8 months were colle Month Calculator Labor Cost Employee Hours 360 550 630 610 480 350 570 310 $7,000 February March April May une 8,140 9,899 9,787 8,490 7,450 9,490 7,531 August Coefficients shown by a regression program for Pizza Vesuvio's data are: 4,517 X Variable 8.20 In your...
Using High-Low to Calculate and cont Calculate the Variable Roster, and Construct a cost functie Piazza Vesuvio makes speciaky puzzas. Data for the past 3 months were collected: Month Labor Cost($) Employee Hours Lanuary 9.490 February 7,000 March 7,531 April May 9,787 June 8.490 July 11,820 August 7,500 300 Pizza Vesuvio's controller wants to calculate the fixed and variable costs associated with labor used in the restaurant In your calculations, round the variable rate per employee hour to the nearest...
Catulston Akira Company had the following transactions for the month. 120 Number Total of Units Cost Beginning inventory $1,200 Purchased Mar. 31 170 2,040 Purchased Oct. 15 140 2,100 Total goods available for sale 430 5,340 Ending inventory 70 7 Calculate the gross margin for the period for each of the following cost allocation methods, using periodic Inventory updating. Assume that all un for $27 each. Round your Intermediate calculations to 2 decimal places and final answers to the nearest...
The Boilermakers is a manufacturing company that uses gear assemblies to produce four different models of mountain bikes. One of these gear assemblies, the "Smooth Shifter," is used for the two most expensive models, and has an estimated annual demand of 540 units. The Boilermakers estimates the cost to place an order is $100, and the holding cost for each assembly is $10 per month. a) Currently, not knowing about EOQ, the purchasing manager places an order for the Smooth...
The Sanding Department of Quik Furniture Company has the following production and manufacturing cost data for March 2020, the first month of operation. Production: 6,260 units finished and transferred out; 3,000 units started that are 100% complete as to materials and 20% complete as to conversion costs. Manufacturing costs: Materials $35,188; labor $21,500; overhead $35,438. Prepare a production cost report. (Round unit costs to 2 decimal places, e.g. 2.25 and other answers to 0 decimal places, e.g. 125.) QUIK FURNITURE...
1. Botana Company constructed the following formula for monthly utility cost. Total utility cost = $1,200 + ($8.10 × labor hours) Assume that 775 labor hours are budgeted for the month of April. Calculate the total variable utility cost for the month of April. Group of answer choices a. $1,200.00 b. $6,277.50 c. $7,477.50 d. $5,077.50 . 2. Marigold Company makes furniture. The company controller wanted to calculate the fixed and variable costs associated with electricity use in the factory. Data...