Question

Part 1: Below is the company Information that you will use in completing Part 1. The requirements are listed after this compa6. Completed jobs 25 and 27 in January. 7. Customer for Job 25 picked up completed job and was billed the following: Job 25 17. Prepare a statement of cost of goods manufactured for January below. Use Manufacturing Overhead applied in your statement.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

The answer has been presented in the supporting sheet. All the parts has been solved with detailed explanation and calculation. For detailed answer refer to the supporting sheet.

Answer Part 1) Predetermined Overhead Rate = Predicted Annual Overhead / Predicted Annual Direct Material Cost *100 = 30000 /

Add a comment
Know the answer?
Add Answer to:
Part 1: Below is the company Information that you will use in completing Part 1. The...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Part 1: Below is the company Information that you will use in completing Part 1. The...

    Part 1: Below is the company Information that you will use in completing Part 1. The requirements are listed after this company information and you should provide your solution below each of the requirements. 6. Completed jobs 25 and 27 in January. 7. Customer for Job 25 picked up completed job and was billed the following: Sheds, Inc. designs and builds sheds and outbuildings for individual customers. The company uses a job cost system and treats each customer's order as...

  • Part 1: Information to use in completing is below and the requirements follow where you will...

    Part 1: Information to use in completing is below and the requirements follow where you will answer the questions. Sheds, Inc. designs and builds sheds and outbuildings for individual customers. The company uses a job cost system and treats each customer's order as a separate job. At the beginning of January the company had the following raw material inventory: At the beginning of January the company had the following work-in-process inventories: Job 21 $3,000 Job 25 $2,000 During January, the...

  • Part 1: Information to use in completing is below and the requirements follow where you will...

    Part 1: Information to use in completing is below and the requirements follow where you will answer the questions. Sheds, Inc. designs and builds sheds and outbuildings for individual customers. The company uses a job cost system and treats each customer's order as a separate job. At the beginning of January the company had the following raw material inventory: 500 At the beginning of January the company had the following work-in-process inventories: Job 21 $3,000 Job 25 $2,000 During January,...

  • Glass Company makes glass orders based on the customer specifications, so the company uses job costing...

    Glass Company makes glass orders based on the customer specifications, so the company uses job costing to track costs. The company uses direct labor hours as the cost driver for manufacturing overhead application. The company estimated the following manufacturing overhead costs for the year: $594,500 The company estimated the following usage of direct-labor hours for the year: $205,000 2.. Beginning Work-in-process, March 1 (Job 57) $100,000 3.. Beginning Finished Goods, March 1 (Job 55) $120,000 4.. Labor Information for March:...

  • Question 1 A job cost sheet for Rolen Company is shown below. Job No. 92 Direct...

    Question 1 A job cost sheet for Rolen Company is shown below. Job No. 92 Direct Materials Direct Labour For 2,000 Units Manufacturing Overhead Date Beginning Balance January 1 $5,000 $2,500 $3,920 6,000 8 12 8,500 5,950 25 2,000 27 3,900 17,400 2,730 11,180 11,920 Cost of completed job: Direct materials Direct labour Manufacturing overhead $11,920 17,400 11,180 $40,500 Total cost Unit cost ($40,500 - 2,000) $20.25 (a) Your answer is correct. On the basis of the foregoing data, answer...

  • The following information applies to the questions displayed below. Sweeten Company had no jobs in progress...

    The following information applies to the questions displayed below. Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March-Job P and Job Q. Job P was completed and sold by the end of the March and Job Q was incomplete at the end of the March. The company uses a plantwide predetermined overhead rate based on direct labor-hours. The following additional information is available for the company...

  • [The following information applies to the questions displayed below.] Bunnell Corporation is a manufacturer that uses...

    [The following information applies to the questions displayed below.] Bunnell Corporation is a manufacturer that uses job-order costing. On January 1, the company’s inventory balances were as follows: Raw materials $ 60,500 Work in process $ 20,800 Finished goods $ 57,600 The company applies overhead cost to jobs on the basis of direct labor-hours. For the current year, the company’s predetermined overhead rate of $11.25 per direct labor-hour was based on a cost formula that estimated $450,000 of total manufacturing...

  • Vanwagenen Inc. uses a job costing system. The company applies manufacturing overhead to jobs using a...

    Vanwagenen Inc. uses a job costing system. The company applies manufacturing overhead to jobs using a predetermined overhead rate based on direct labor cost. The company has provided the following data for the month of April: Inventories: Beginning Ending Raw materials (all materials are direct materials) ............................... $13,500 $17,500 Work in process……………………………………………...................... $12,000 $16,000 Finished goods………………………………………………..................... $27,000 $25,000 Addition information is given below. Direct materials used in production..………………………..... $66,000 Total manufacturing costs charged to production (includes direct materials, direct labor,...

  • Required information [The following information applies to the questions displayed below.] Bunnell Corporation is a manufacturer...

    Required information [The following information applies to the questions displayed below.] Bunnell Corporation is a manufacturer that uses job-order costing. On January 1, the company’s inventory balances were as follows: Raw materials $ 40,000 Work in process $ 18,000 Finished goods $ 35,000 The company applies overhead cost to jobs on the basis of direct labor-hours. For the current year, the company’s predetermined overhead rate of $16.25 per direct labor-hour was based on a cost formula that estimated $650,000 of...

  • I need help with question 7 Sampson Company uses a job order cost system with overhead...

    I need help with question 7 Sampson Company uses a job order cost system with overhead applied based on direct labor hours. See estimated amounts below. Note the beginning balances for Finished Goods (Job 101) and Work-in-Process (Jobs 102 & 103) for the costs accumulated to date. Also note, the beginning balances in the other balance sheet accounts. Estimated Overhead for 2014 720,000 Estimated Direct Labor Hours for 2014 24,000 During January the comapny had the following transactions: Purchased $10,000...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT