The answer has been presented in the supporting sheet. All the parts has been solved with detailed explanation and calculation. For detailed answer refer to the supporting sheet.
Part 1: Below is the company Information that you will use in completing Part 1. The...
Part 1: Below is the company Information that you will use in completing Part 1. The requirements are listed after this company information and you should provide your solution below each of the requirements. 6. Completed jobs 25 and 27 in January. 7. Customer for Job 25 picked up completed job and was billed the following: Sheds, Inc. designs and builds sheds and outbuildings for individual customers. The company uses a job cost system and treats each customer's order as...
Part 1: Information to use in completing is below and the requirements follow where you will answer the questions. Sheds, Inc. designs and builds sheds and outbuildings for individual customers. The company uses a job cost system and treats each customer's order as a separate job. At the beginning of January the company had the following raw material inventory: At the beginning of January the company had the following work-in-process inventories: Job 21 $3,000 Job 25 $2,000 During January, the...
Part 1: Information to use in completing is below and the requirements follow where you will answer the questions. Sheds, Inc. designs and builds sheds and outbuildings for individual customers. The company uses a job cost system and treats each customer's order as a separate job. At the beginning of January the company had the following raw material inventory: 500 At the beginning of January the company had the following work-in-process inventories: Job 21 $3,000 Job 25 $2,000 During January,...
Glass Company makes glass orders based on the customer
specifications, so the company uses job costing to track costs.
The company uses direct labor hours as the cost driver for
manufacturing overhead application.
The company estimated the following manufacturing overhead costs
for the year: $594,500
The company estimated the following usage of direct-labor hours
for the year: $205,000
2.. Beginning Work-in-process, March 1 (Job 57) $100,000
3.. Beginning Finished Goods, March 1 (Job 55) $120,000
4.. Labor Information for March:...
Question 1 A job cost sheet for Rolen Company is shown below. Job No. 92 Direct Materials Direct Labour For 2,000 Units Manufacturing Overhead Date Beginning Balance January 1 $5,000 $2,500 $3,920 6,000 8 12 8,500 5,950 25 2,000 27 3,900 17,400 2,730 11,180 11,920 Cost of completed job: Direct materials Direct labour Manufacturing overhead $11,920 17,400 11,180 $40,500 Total cost Unit cost ($40,500 - 2,000) $20.25 (a) Your answer is correct. On the basis of the foregoing data, answer...
The following information applies to the questions displayed below. Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March-Job P and Job Q. Job P was completed and sold by the end of the March and Job Q was incomplete at the end of the March. The company uses a plantwide predetermined overhead rate based on direct labor-hours. The following additional information is available for the company...
[The following information applies to the questions displayed below.] Bunnell Corporation is a manufacturer that uses job-order costing. On January 1, the company’s inventory balances were as follows: Raw materials $ 60,500 Work in process $ 20,800 Finished goods $ 57,600 The company applies overhead cost to jobs on the basis of direct labor-hours. For the current year, the company’s predetermined overhead rate of $11.25 per direct labor-hour was based on a cost formula that estimated $450,000 of total manufacturing...
Vanwagenen Inc. uses a job costing system. The company applies manufacturing overhead to jobs using a predetermined overhead rate based on direct labor cost. The company has provided the following data for the month of April: Inventories: Beginning Ending Raw materials (all materials are direct materials) ............................... $13,500 $17,500 Work in process……………………………………………...................... $12,000 $16,000 Finished goods………………………………………………..................... $27,000 $25,000 Addition information is given below. Direct materials used in production..………………………..... $66,000 Total manufacturing costs charged to production (includes direct materials, direct labor,...
Required information [The following information applies to the questions displayed below.] Bunnell Corporation is a manufacturer that uses job-order costing. On January 1, the company’s inventory balances were as follows: Raw materials $ 40,000 Work in process $ 18,000 Finished goods $ 35,000 The company applies overhead cost to jobs on the basis of direct labor-hours. For the current year, the company’s predetermined overhead rate of $16.25 per direct labor-hour was based on a cost formula that estimated $650,000 of...
I need help with question 7
Sampson Company uses a job order cost system with overhead applied based on direct labor hours. See estimated amounts below. Note the beginning balances for Finished Goods (Job 101) and Work-in-Process (Jobs 102 & 103) for the costs accumulated to date. Also note, the beginning balances in the other balance sheet accounts. Estimated Overhead for 2014 720,000 Estimated Direct Labor Hours for 2014 24,000 During January the comapny had the following transactions: Purchased $10,000...