Question

Part 1: Information to use in completing is below and the requirements follow where you will...

Part 1: Information to use in completing is below and the requirements follow where you will answer the questions.

Sheds, Inc. designs and builds sheds and outbuildings for individual customers.
The company uses a job cost system and treats each customer's order as a separate job.

At the beginning of January the company had the following raw material inventory: 500

At the beginning of January the company had the following work-in-process inventories:
Job 21 $3,000
Job 25 $2,000

During January, the following activities took place:
1. Started jobs 26 and 27.
2. Purchased raw materials in January: $12,000
Requisitioned(or used) the following raw materials to the specific jobs:
Job 21 $2,000
Job 25 $4,000
Job 26 $1,000
Job 27 $3,000

3. Incurred January manufacturing payroll:
Direct Labor
Job 21 $750
Job 25 $2,000
Job 26 $900
Job 27 $1,500

Indirect labor $500

4. Incurred additional manufacturing overhead costs for January:
Production equipment rent. 800
Manufacturing supplies purchased and used. 750
Factory utilities. 525

5. Applied manufacturing overhead using a predetermined rate based on predicted annual overhead
and predicted annual direct material cost as follows:
Predicted Annual Overhead $25,000
Predicted Annual Direct Material cost $100,000

6. Completed jobs 26 and 27.

7. Customer for Job 27 picked up completed job and was billed the following:
Job 27 11,000

8. The company had the following period costs that they incurred:
Sales commissions $2,000
Administrative salaries $1,000

Determine the ending Work-In-Process Inventory at the end of January and provide the number of the Jobs still in Work-in-Process at the end of January and the determine total cost of ending work in process for January. Determine the Finished Goods for January and provide the number of the Jobs in Finished Goods at the end of January and determine the total cost of ending finished goods for January. Determine the underapplied or overapplied manufacturing for January.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Ending work-in-process inventory: $15250

Job 21 $         6,250
Job 25 $         9,000
$       15,250

Ending finished goods: $2150

Job 26 $         2,150
Manufacturing overhead applied $       2,500
Manufacturing overhead incurred:
Indirect labor $             500
Production equipment rent $             800
Manufacturing supplies used $             750
Factory utilities $             525
Total manufacturing overhead incurred $       2,575
Underapplied manufacturing overhead $ $             75

Working:

Predetermined overhead rate = Predicted annual overhead/Predicted annual direct material cost = $25000/$100000 = 25% of direct materials cost

Job 21 Job 25 Job 26 Job 27
Beginning balance 3000 2000 0 0
Direct materials 2000 4000 1000 3000
Direct labor 750 2000 900 1500
Manufacturing overhead 500 1000 250 750
Total cost $ 6250 9000 2150 5250
WIP FG COGS
Add a comment
Know the answer?
Add Answer to:
Part 1: Information to use in completing is below and the requirements follow where you will...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Part 1: Information to use in completing is below and the requirements follow where you will...

    Part 1: Information to use in completing is below and the requirements follow where you will answer the questions. Sheds, Inc. designs and builds sheds and outbuildings for individual customers. The company uses a job cost system and treats each customer's order as a separate job. At the beginning of January the company had the following raw material inventory: At the beginning of January the company had the following work-in-process inventories: Job 21 $3,000 Job 25 $2,000 During January, the...

  • Part 1: Below is the company Information that you will use in completing Part 1. The...

    Part 1: Below is the company Information that you will use in completing Part 1. The requirements are listed after this company information and you should provide your solution below each of the requirements. Sheds, Inc. designs and builds sheds and outbuildings for individual customers. The company uses a job cost system and treats each customer's order as a separate job. At the beginning of January the company had the following raw material inventory: $500 At the beginning of January...

  • Part 1: Below is the company Information that you will use in completing Part 1. The...

    Part 1: Below is the company Information that you will use in completing Part 1. The requirements are listed after this company information and you should provide your solution below each of the requirements. 6. Completed jobs 25 and 27 in January. 7. Customer for Job 25 picked up completed job and was billed the following: Sheds, Inc. designs and builds sheds and outbuildings for individual customers. The company uses a job cost system and treats each customer's order as...

  • Required information [The following information applies to the questions displayed below.] Bunnell Corporation is a manufacturer...

    Required information [The following information applies to the questions displayed below.] Bunnell Corporation is a manufacturer that uses job-order costing. On January 1, the company’s inventory balances were as follows: Raw materials $ 40,000 Work in process $ 18,000 Finished goods $ 35,000 The company applies overhead cost to jobs on the basis of direct labor-hours. For the current year, the company’s predetermined overhead rate of $16.25 per direct labor-hour was based on a cost formula that estimated $650,000 of...

  • ACC378 Cost Accounting Assignment CHS Perry Company employs a job-order costing system. Only three jobs Job...

    ACC378 Cost Accounting Assignment CHS Perry Company employs a job-order costing system. Only three jobs Job 205. Job W206, and Job #207- were worked on during January and February. Job #205 was completed February 10: the other two jobs were still in production on February 28, the end of the company's operating year. Job cost sheets on the three jobs follow Job #205 Job Cost Sheet Job #206 Job #207 Totals $ - January costs incurred: Direct material Direct labor...

  • [The following information applies to the questions displayed below.] Bunnell Corporation is a manufacturer that uses...

    [The following information applies to the questions displayed below.] Bunnell Corporation is a manufacturer that uses job-order costing. On January 1, the company’s inventory balances were as follows: Raw materials $ 60,500 Work in process $ 20,800 Finished goods $ 57,600 The company applies overhead cost to jobs on the basis of direct labor-hours. For the current year, the company’s predetermined overhead rate of $11.25 per direct labor-hour was based on a cost formula that estimated $450,000 of total manufacturing...

  • Pedriani Company uses a job order cost system and applies overhead on the basis of direct...

    Pedriani Company uses a job order cost system and applies overhead on the basis of direct labor hours. On Jan01, 2017, Job No. 25 was the only job in process. Costs incurred prior to Jan01 on this job were as follows: direct materials $10,000; direct labor $6,000; and manufacturing overhead $9,000.  Job No. 23 had been completed at a cost of $42,000 and was part of finished goods inventory.  There was a $5,000 balance in the Raw Materials Inventory account. During the...

  • Weinrich Manufacturing uses a job order cost system and applies overhead to production on the basis...

    Weinrich Manufacturing uses a job order cost system and applies overhead to production on the basis of direct labor hours. On January 1, 2019, Job No. 25 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $10,000; direct labor $6,000; and manufacturing overhead $9,000. Job No. 23 had been completed at a cost of $42,000 and was part of finished goods inventory. There was a $8,000 balance in...

  • Question 1 A job cost sheet for Rolen Company is shown below. Job No. 92 Direct...

    Question 1 A job cost sheet for Rolen Company is shown below. Job No. 92 Direct Materials Direct Labour For 2,000 Units Manufacturing Overhead Date Beginning Balance January 1 $5,000 $2,500 $3,920 6,000 8 12 8,500 5,950 25 2,000 27 3,900 17,400 2,730 11,180 11,920 Cost of completed job: Direct materials Direct labour Manufacturing overhead $11,920 17,400 11,180 $40,500 Total cost Unit cost ($40,500 - 2,000) $20.25 (a) Your answer is correct. On the basis of the foregoing data, answer...

  • Required information (The following information applies to the questions displayed below.) Bunnell Corporation is a manufacturer...

    Required information (The following information applies to the questions displayed below.) Bunnell Corporation is a manufacturer that uses job-order costing. On January 1, the company's inventory balances were as follows: Raw materials Work in process Finished goods $ 59,500 $ 37,600 $ 61,800 The company applies overhead cost to jobs on the basis of direct labor-hours. For the current year, the company's predetermined overhead rate of $14,25 per direct labor-hour was based on a cost formula that estimated $570,000 of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT