Answer Step Wise: | ||||||
Production volume variance: | ||||||
The production volume variance measures the amount of overhead applied to the number of units produced. | ||||||
It is the difference between the actual number of units produced in a period and the budgeted number of units that should have been produced, multiplied by the budgeted overhead rate. | ||||||
Steps: | Hours | |||||
1 | Actual number of hours produced | 845 | ||||
2 | Budgeted Hours | 910 | ||||
1-2 | Difference | 65 | ||||
Predertermined Overhead rate | 6 | |||||
Production volume variance: | ||||||
=(Actual Hours - Budgeted Hours)*Overhead Rate | ||||||
-390 | ||||||
Answer is $ 390. | ||||||
10.00 points Actual foed overheed costs Budgeted fixed overheed costs Predetemined overheed rate (52 variable 845...
1,020 Actual machine hours Standard machine hours allowed Denominator activity machine hours) Actual fixed overhead costs Budgeted faxed overhead costs Predetermined overhead rate ($2 variable 3.000 4080 $4 foed What is the production volume variance? $180 $440 $390 5260
Into 1 | Question 43 (of 50) < velok 10.00 points Actuel machire hours Stundard machine hours alowed Denomineror acevty (machine hours) Actuel foxed overhead costs 845 910 1020 $ 3,900 $ 4,080 budgeted foxed avetheed costs Predetermined overhead rate ($2 vortabie $4 foed) Whet is the production volume varience? O S180 O S440. O s390 O $260
Actual Fixed Costs = $300,000 Actual Variable Cost = $800,000 Budgeted Fixed Cost = $280,000 Capacity Level = 80% Variable Cost per Hour = $200 Total Hours = 10,000 Compute budget variance for fixed and variable costs
Direct Materials, Direct Labor, and Reports budgeted and actual costs for variable and fixed factory overhead along with the related controllable and volume variances.Factory Overhead Cost Variance Analysis Mackinaw Inc. processes a base chemical into plastic. A detailed estimate of what a product should cost.Standard costs and actual costs for direct materials, direct labor, and factory overhead incurred for the manufacture of 70,000 units of product were as follows: Standard Costs Actual Costs Direct materials 189,000 lbs. at $6.00 187,100...
Actual machine hours Standard machine hours allowed Denominator activity (machine hours) Actual foxed overhead costs Budgeted foed overhead costs Predetermined overhead rate ($i variable - $5 fixed 1075 4.800 What is the fixed overhead spending (budget, variance? $575 $575 $420 O $350
Actual machine hours Standard machine hours allowed Denominator activity (machine hours) Actual foxed overhead costs Budgeted foed overhead costs Predetermined overhead rate ($i variable - $5 fixed 1075 4.800 What is the fixed overhead spending (budget, variance? $575 $575 $420 O $350
tual mochine hours Standard mochine hours allowed Denominator activity (machine hours) Actual fixed overhead costs Budgeted fixed overhend costs Predetermined overhead rate ($2 variable $8 fixed 50 8,750 10 What is the fixed overhead production volume variance? $450 favorable $1.840 unfavorable O $220 favorable O $450 unfavorable O $880 favorable $1,840 favorable. some other amount favorable some other amount unfavorable O $220 unfavorable O $880 unfavorable
Information on Carney Company's fixed overhead costs follows: Overhead applied Actual overhead Budgeted overhead $360, eee 385,500 369,800 Required: What are the fixed overhead price and production volume variances? (Indicate the effect of each varlance by selecting "F" for favorable, or "U" for unfavorable. If there is no effect, do not select elther option.) Fixed overhead price variance Fixed overhead production volume variance
The following information relating to a company's overhead costs is available. Budgeted fixed overhead rate per machine hour Actual variable overhead Budgeted variable overhead rate per machine hour Actual fixed overhead Budgeted hours allowed for actual output achieved $ 2.00 $95,000 $ 2.00 $20,000 41,000 Based on this information, the total overhead variance is: Multiple Choice $13,000 favorable. o $49,000 favorable. o $36,000 unfavorable. o O $49,000 $49,000 unfavorable. o
Acme Company's production budget for August is 18,000 units and includes the following component unit costs: direct materials. 58.0 direct labor, 510.5, variable overhead, $6.4. Budgeted fixed overhead is $37,000. Actual production in August was 19.950 units. Actual unit component costs incurred during August include direct materials, $8.70; direct labor, $9.90: variable overhead, 5730. Actual fixed overhead was $39.000. The standard variable overhead rate per unit consists of $6.4 per machine hour and each unit is allowed a standard of...