Question

It is possible to have two different breakdowns of the same project tasks. True False
0 0
Add a comment Improve this question Transcribed image text
Answer #1

OPTION: True

REASON:

There is more than one way to organize tasks on project. For example work packages may be placed under different summary task headings.

Add a comment
Know the answer?
Add Answer to:
It is possible to have two different breakdowns of the same project tasks. True False
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT