Question

Data on small maintenance project is given as below Normal Activity Cost $700 Cost 6 days 4 days 4 days$800 4 days 4 davs 5 days 700 7 days 5 days 650 625 8 days 10 days 7 days 3 days 6 days 7 days 200 350 600 3 days 600 300 D, E F. G 5 days 4 davs 350 425 On completion, the project will give a return of S110/day. Using time-cost trade-off method how much would you like to compress the project for maximizing the return? Show all calculations
0 0
Add a comment Improve this question Transcribed image text
Know the answer?
Add Answer to:
Data on small maintenance project is given as below Normal Activity Cost $700 Cost 6 days...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Data on small maintenance project is given as below: Depend Time Normal Crash Activity on Cost Time Cost 6 days $70...

    Data on small maintenance project is given as below: Depend Time Normal Crash Activity on Cost Time Cost 6 days $700 4 days$800 4 days400 5 days 8 days 10 days 200 7 days 3 days600 6 days50 650 625 7 days 250 700 600 s 400 425 days 3 days 500 On completion, the project will give a return of S110day. Using time-cost trade-off method, how much would you like to compress the project for maximiz ng the return?...

  • Question 1: I)-What is the normal cost of this project? II)-What is the cost of the...

    Question 1: I)-What is the normal cost of this project? II)-What is the cost of the project after 2 days shortening? III)-What is the crashing cost per day for activity G? Given the following data and network, find answer the questions 18-20 if you're asked to finish this project 2 days earlier than its normal duration. Indirect cost (overhead) is $200 per day. 9.12 E 3 1.8 12. 19 10,13 B 7 1,8 13.20 0,1 1,7 8.15 20,25 15.20 F...

  • what is the normal cost of this project? what is the cost of the project after...

    what is the normal cost of this project? what is the cost of the project after 2 days shortening? what is the crashing cost per day for avtivity G? Given the following data and network, find answer the questions 18-20 if you're asked to finish this project 2 days earlier than its normal duration. Indirect cost (overhead) is $200 per day. 9.12 E 1.8 اليا 12.19 10.13 B 7 H 7 1.8 13, 20 0.1 1.7 8.15 20,25 15, 20...

  • Given below is the crashing data for a project along with other data. The project completion...

    Given below is the crashing data for a project along with other data. The project completion time is 20 davs. Determine: (a) the crash slope (i.e crash cost/day) for all activities, (b) the normal total project cost, (c) prioritized the list of activities for crashing from best to worst, (d) the best activity to crash if the project has to be completed in 19 days and alternative critical paths, if any, (e) the earliest time the project can be completed,...

  • A B Start E End C D Activity Normal time (days) Normal cost Crash time Cr...

    A B Start E End C D Activity Normal time (days) Normal cost Crash time Cr 3 1 А B с D E 7 3 6 3 2 $300 $250 $400 $200 $300 4 2 1 ive the crash cost per day per activity. (5 points) Search 36_WA_Homework_EV_Problems_v1 (1) - Protected View - Saved References Mailings Review View Help PROBLEM 1 Use the network diagram below and the additional information provided to answer the corresponding questions. (10 points) B E...

  • What is the minimum cost of crashing the following project at Sawaya Robotics by 4 days?...

    What is the minimum cost of crashing the following project at Sawaya Robotics by 4 days? IMMEDIATE PREDECESSOR(S) ACTIVITY Design (A) Wiring (B) Chip install (C) Software (D) Testing (E) NORMAL TIME (DAYS) 9 7 5 6 CRASH TIME NORMAL (DAYS) COST 7 200 6 800 4 600 4 1,100 6 1,200 CRASH COST 300 875 675 1,300 1,875 9 A,B с The minimum cost of crashing the following project at Sawaya Robotics by. 4 days is $ whole number)....

  • (iii) Determine the minimum possible project time and the total addirional cost to complete the project...

    (iii) Determine the minimum possible project time and the total addirional cost to complete the project in this time. (15 Marks) 2 2 5 5 6 6 4 زرا 4 در Normal Duration Crash Duration Activity Days Cost $ Days Cost $ 1-2 2 450 1 600 1-3 4 400 2 600 1-4 6 350 5 700 2-4 2 250 1 400 3-5 3 100 2 150 4-5 4 500 2 1000 4-6 5 500 3 800 5-6 3 400...

  • (iii) Determine the minimum possible project time and the total addirional cost to complete the project...

    (iii) Determine the minimum possible project time and the total addirional cost to complete the project in this time. (15 Marks) 2 2 5 5 6 6 4 زرا 4 در Normal Duration Crash Duration Activity Days Cost $ Days Cost $ 1-2 2 450 1 600 1-3 4 400 2 600 1-4 6 350 5 700 2-4 2 250 1 400 3-5 3 100 2 150 4-5 4 500 2 1000 4-6 5 500 3 800 5-6 3 400...

  • What is the minimum cost of crashing the following project that Roger Solano manages at Slippery...

    What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? Normal Crash Time Normal Activity Time (days) (days) Cost $800 $250 $600 $750 $1,200 Uw > A Awarw Total Cost with Crashing Immediate Predecessor(s) $1,100 $600 $650 $1,500 $1,650 OD By how many days should each activity be crashed to reduce the project completion time by 4 days? Fill in the table below. (Enter your responses as whole numbers.)...

  • Path A -> B -> F C-> D -> E ----^ Activity Normal Time Crash Time...

    Path A -> B -> F C-> D -> E ----^ Activity Normal Time Crash Time Crash Cost per day A 6 6 --- B 10 8 $100 C 5 4 $300 D 4 1 $700 E 9 7 $500 F 2 1 $650 a.     Determine which activities should be crashed to shorten the project by 3 days. b.     What is the associated crash cost?

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT