Data on small maintenance project is given as below Normal Activity Cost $700 Cost 6 days...
Data on small maintenance project is given as below: Depend Time Normal Crash Activity on Cost Time Cost 6 days $700 4 days$800 4 days400 5 days 8 days 10 days 200 7 days 3 days600 6 days50 650 625 7 days 250 700 600 s 400 425 days 3 days 500 On completion, the project will give a return of S110day. Using time-cost trade-off method, how much would you like to compress the project for maximiz ng the return?...
Question 1: I)-What is the normal cost of this project? II)-What is the cost of the project after 2 days shortening? III)-What is the crashing cost per day for activity G? Given the following data and network, find answer the questions 18-20 if you're asked to finish this project 2 days earlier than its normal duration. Indirect cost (overhead) is $200 per day. 9.12 E 3 1.8 12. 19 10,13 B 7 1,8 13.20 0,1 1,7 8.15 20,25 15.20 F...
what is the normal cost of this project? what is the cost of the project after 2 days shortening? what is the crashing cost per day for avtivity G? Given the following data and network, find answer the questions 18-20 if you're asked to finish this project 2 days earlier than its normal duration. Indirect cost (overhead) is $200 per day. 9.12 E 1.8 اليا 12.19 10.13 B 7 H 7 1.8 13, 20 0.1 1.7 8.15 20,25 15, 20...
Given below is the crashing data for a project along with other data. The project completion time is 20 davs. Determine: (a) the crash slope (i.e crash cost/day) for all activities, (b) the normal total project cost, (c) prioritized the list of activities for crashing from best to worst, (d) the best activity to crash if the project has to be completed in 19 days and alternative critical paths, if any, (e) the earliest time the project can be completed,...
A B Start E End C D Activity Normal time (days) Normal cost Crash time Cr 3 1 А B с D E 7 3 6 3 2 $300 $250 $400 $200 $300 4 2 1 ive the crash cost per day per activity. (5 points) Search 36_WA_Homework_EV_Problems_v1 (1) - Protected View - Saved References Mailings Review View Help PROBLEM 1 Use the network diagram below and the additional information provided to answer the corresponding questions. (10 points) B E...
What is the minimum cost of crashing the following project at Sawaya Robotics by 4 days? IMMEDIATE PREDECESSOR(S) ACTIVITY Design (A) Wiring (B) Chip install (C) Software (D) Testing (E) NORMAL TIME (DAYS) 9 7 5 6 CRASH TIME NORMAL (DAYS) COST 7 200 6 800 4 600 4 1,100 6 1,200 CRASH COST 300 875 675 1,300 1,875 9 A,B с The minimum cost of crashing the following project at Sawaya Robotics by. 4 days is $ whole number)....
(iii) Determine the minimum possible project time and the total addirional cost to complete the project in this time. (15 Marks) 2 2 5 5 6 6 4 زرا 4 در Normal Duration Crash Duration Activity Days Cost $ Days Cost $ 1-2 2 450 1 600 1-3 4 400 2 600 1-4 6 350 5 700 2-4 2 250 1 400 3-5 3 100 2 150 4-5 4 500 2 1000 4-6 5 500 3 800 5-6 3 400...
(iii) Determine the minimum possible project time and the total addirional cost to complete the project in this time. (15 Marks) 2 2 5 5 6 6 4 زرا 4 در Normal Duration Crash Duration Activity Days Cost $ Days Cost $ 1-2 2 450 1 600 1-3 4 400 2 600 1-4 6 350 5 700 2-4 2 250 1 400 3-5 3 100 2 150 4-5 4 500 2 1000 4-6 5 500 3 800 5-6 3 400...
What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? Normal Crash Time Normal Activity Time (days) (days) Cost $800 $250 $600 $750 $1,200 Uw > A Awarw Total Cost with Crashing Immediate Predecessor(s) $1,100 $600 $650 $1,500 $1,650 OD By how many days should each activity be crashed to reduce the project completion time by 4 days? Fill in the table below. (Enter your responses as whole numbers.)...
Path A -> B -> F C-> D -> E ----^ Activity Normal Time Crash Time Crash Cost per day A 6 6 --- B 10 8 $100 C 5 4 $300 D 4 1 $700 E 9 7 $500 F 2 1 $650 a. Determine which activities should be crashed to shorten the project by 3 days. b. What is the associated crash cost?