Question

(iii) Determine the minimum possible project time and the total addirional cost to complete the project in this time. (15 Mar

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Crash duration for 4 5 2 days Crash duration duration for 5 5 6 a days Total duration of 1 ₃ 4 5 6 After crashing is 5+2+2 9Now the path along 4 6 has to be Crashed to reduce the o time duration duration of 4 - 6 After crashing = 3 days Now time durAdditional Cost Required crash cost - Normal Cost Additional cost for 7 4 = 700-350 350 $ Additional Cost for 4 - 5 11 1ooo -

Add a comment
Know the answer?
Add Answer to:
(iii) Determine the minimum possible project time and the total addirional cost to complete the project...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • (iii) Determine the minimum possible project time and the total addirional cost to complete the project...

    (iii) Determine the minimum possible project time and the total addirional cost to complete the project in this time. (15 Marks) 2 2 5 5 6 6 4 زرا 4 در Normal Duration Crash Duration Activity Days Cost $ Days Cost $ 1-2 2 450 1 600 1-3 4 400 2 600 1-4 6 350 5 700 2-4 2 250 1 400 3-5 3 100 2 150 4-5 4 500 2 1000 4-6 5 500 3 800 5-6 3 400...

  • Question 1: I)-What is the normal cost of this project? II)-What is the cost of the...

    Question 1: I)-What is the normal cost of this project? II)-What is the cost of the project after 2 days shortening? III)-What is the crashing cost per day for activity G? Given the following data and network, find answer the questions 18-20 if you're asked to finish this project 2 days earlier than its normal duration. Indirect cost (overhead) is $200 per day. 9.12 E 3 1.8 12. 19 10,13 B 7 1,8 13.20 0,1 1,7 8.15 20,25 15.20 F...

  • what is the normal cost of this project? what is the cost of the project after...

    what is the normal cost of this project? what is the cost of the project after 2 days shortening? what is the crashing cost per day for avtivity G? Given the following data and network, find answer the questions 18-20 if you're asked to finish this project 2 days earlier than its normal duration. Indirect cost (overhead) is $200 per day. 9.12 E 1.8 اليا 12.19 10.13 B 7 H 7 1.8 13, 20 0.1 1.7 8.15 20,25 15, 20...

  • Data on small maintenance project is given as below: Depend Time Normal Crash Activity on Cost Time Cost 6 days $70...

    Data on small maintenance project is given as below: Depend Time Normal Crash Activity on Cost Time Cost 6 days $700 4 days$800 4 days400 5 days 8 days 10 days 200 7 days 3 days600 6 days50 650 625 7 days 250 700 600 s 400 425 days 3 days 500 On completion, the project will give a return of S110day. Using time-cost trade-off method, how much would you like to compress the project for maximiz ng the return?...

  • Given the data table below develop the precedence network and perform the CPM calculations. Then, using...

    Given the data table below develop the precedence network and perform the CPM calculations. Then, using the proposed crashing strategy calculate the normal, least-cost, and crash duration for the project below. Calculate the cost associated with each duration. Indirect cost (overhead) is $120 per day. Activity IPA Duration Cost $ Normal Crash Normal Crash A 5 4 $770 $900 3 2 B C P 7 4 $660 $700 $800 $1,070 $1,000 $1,110 $800 $920 D AB 4 3 E B...

  • A B Start E End C D Activity Normal time (days) Normal cost Crash time Cr...

    A B Start E End C D Activity Normal time (days) Normal cost Crash time Cr 3 1 А B с D E 7 3 6 3 2 $300 $250 $400 $200 $300 4 2 1 ive the crash cost per day per activity. (5 points) Search 36_WA_Homework_EV_Problems_v1 (1) - Protected View - Saved References Mailings Review View Help PROBLEM 1 Use the network diagram below and the additional information provided to answer the corresponding questions. (10 points) B E...

  • What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 da...

    What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? Please show work and calculations. NORMAL CRASH TIME ACTIVITY (DAYS) (DAYS) TIME NORMAL CRASH COST IMMEDIATE COST PREDECESSOR(S) 900 $1,000 B 300 400 C 4 3 500 600 5 3 900 1,200 A 5 1,000 1,600 C LO LO C Ln LLI NORMAL CRASH TIME ACTIVITY (DAYS) (DAYS) TIME NORMAL CRASH COST IMMEDIATE COST PREDECESSOR(S) 900 $1,000 B 300...

  • Question 6 - 8 Activity Depends on А B C D E F G A A...

    Question 6 - 8 Activity Depends on А B C D E F G A A А B C,D D, E, F Duration (Days) Normal Crash 5 4 7 5 8 5 11 8 6 4 4 3 7 5 Cost ($) Normal Crash 500 620 350 500 800 920 1000 1300 600 750 420 500 700 1000 6. Draw the node network for the above project using the following template. For each activity, show the computed value of early...

  • Question 2. (30%) The following table provides the information necessary to construct project network and calculate...

    Question 2. (30%) The following table provides the information necessary to construct project network and calculate a total project cost. In case of activity crash, the information includes crash cost for each activity. Activity Immediate predecessor(s) Activity time (weeks) Normal cost (x1000$) Additional cost for crashing one week (x1000$) Normal After maximum crash A - 16 12 2,000 300 B - 14 9 1,000 160 C A 8 6 500 100 D A 5 4 600 700 E B 4...

  • Data on small maintenance project is given as below Normal Activity Cost $700 Cost 6 days...

    Data on small maintenance project is given as below Normal Activity Cost $700 Cost 6 days 4 days 4 days$800 4 days 4 davs 5 days 700 7 days 5 days 650 625 8 days 10 days 7 days 3 days 6 days 7 days 200 350 600 3 days 600 300 D, E F. G 5 days 4 davs 350 425 On completion, the project will give a return of S110/day. Using time-cost trade-off method how much would you...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT