Question

Sheridan Landscaping began construction of a new plant on December 1, 2020. On this date, the...

Sheridan Landscaping began construction of a new plant on December 1, 2020. On this date, the company purchased a parcel of land for $138,000 in cash. In addition, it paid $2,880 in surveying costs and $4,560 for a title insurance policy. An old dwelling on the premises was demolished at a cost of $3,360, with $960 being received from the sale of materials.


Architectural plans were also formalized on December 1, 2020, when the architect was paid $32,400. The necessary building permits costing $3,360 were obtained from the city and paid for on December 1 as well. The excavation work began during the first week in December with payments made to the contractor in 2021 as follows.

Date of Payment

Amount of Payment

March 1

$253,200

May 1

339,600

July 1

67,200


The building was completed on July 1, 2021.

To finance construction of this plant, Sheridan borrowed $610,800 from the bank on December 1, 2020. Sheridan had no other borrowings. The $610,800 was a 10-year loan bearing interest at 8%.

Compute the balance in each of the following accounts at December 31, 2020, and December 31, 2021.  (Round answers to 0 decimal places, e.g. 5,275.)

Using Excel calculate the following (show your work and use formulas where appropriate):

  1. Balance in the Interest Expense account for December 31, 2020 and December 31, 2021
  2. Balance in the Building account for December 31, 2020 and December 31, 2021
  3. The amount of interest capitalized in 2018
  4. The weighted average of accumulated expenditures for 2021
  5. The amount of interest capitalized in 2020
  6. The weighted average of accumulated expenditures for 2020
  7. Balance in the Land account for December 31, 2020 and December 31, 2021
0 0
Add a comment Improve this question Transcribed image text
Answer #1
01-Dec-20
COST OF PURCHASE OF LAND 138000.00
SURVEYING COSTS 2880.00
INSURANCE POLICY 4560.00
ARCHITECT CHARGES 32400.00
BUILDING PERMIT COST 3360.00
OLD PREMISE DEMOLISHIMG COST 3360.00
RECEIPTS FROM SALE OF SCRAP -960.00
INTEREST (610800*.08*1/12) 4072.00
TOTAL COST ( 31 DEC 2020) 187672.00
01-12-2021
Mar-01 253200.00
May-01 339600.00
Jul-01 67200.00
INTEREST OF 4 MONTHS TO BE CAPATALISED 16288
TOTAL (B) 676288.00
TOTAL COST (A+B) 863960.00

1. Balance in the Interest Expense account

On 31 Dec 2020 - $4072 (610800*8/100*1/12)

On 1 dec 2021 - $ 48864 (610800*8/100)

2. Balance in the Building account for

31 Dec 2020 - $187672

On 1 dec 2021 - $ 863960

3.The amount of interest capitalized in 2018 - NIL , there is no data in the question related to 2018 year.

4. The weighted average of accumulated expenditures for 2021

Total Expenditure in 2021 -  

Mar-01 253200.00
May-01 339600.00
Jul-01 67200.00
TOTAL (B) 660000.00

Weighted Average of

March 01 exp - 0.38 (253200/660000)

May 01 Exp - 0.51 (339600/660000)

July 01 Exp - 0.10 (67200/660000)

The amount of interest capitalized in 2020 -  

INTEREST (610800*.08*1/12) - $4072

01-Dec-20 Weighted average cost
COST OF PURCHASE OF LAND 138000.00 0.75
SURVEYING COSTS 2880.00 0.02
INSURANCE POLICY 4560.00 0.02
ARCHITECT CHARGES 32400.00 0.18
BUILDING PERMIT COST 3360.00 0.02
OLD PREMISE DEMOLISHIMG COST 2400.00 0.01
TOTAL COST (A) 183600.00 1.00

Formula - Specific cost / total cost

The amount of interest capitalized in

2020 - $4072

2021 - $16288

alance in the Land account for

31/12/2020 - nil

31/12/2021 - Nil

Seperate value of land is nil because cost of land will always be included in the total cost of building hence cost of land will be included in the cost of building and there will not be any seperate account of the land in the books of the company.

Add a comment
Know the answer?
Add Answer to:
Sheridan Landscaping began construction of a new plant on December 1, 2020. On this date, the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Oriole Landscaping began construction of a new plant on December 1, 2020. On this date, the...

    Oriole Landscaping began construction of a new plant on December 1, 2020. On this date, the company purchased a parcel of land for $142,800 in cash. In addition, it paid $2,880 in surveying costs and $4,320 for a title insurance policy. An old dwelling on the premises was demolished at a cost of $3,360, with $720 being received from the sale of materials. Architectural plans were also formalized on December 1, 2020, when the architect was paid $40,800. The necessary...

  • x Your answer is incorrect. Oriole Landscaping began construction of a new plant on December 1,...

    x Your answer is incorrect. Oriole Landscaping began construction of a new plant on December 1, 2020. On this date, the company purchased a parcel of land for $142,800 in cash. In addition, it paid $2,880 in surveying costs and $4,320 for a title insurance policy. An old dwelling on the premises was demolished at a cost of $3,360, with $720 being received from the sale of materials. Architectural plans were also formalized on December 1, 2020, when the architect...

  • Problem 10-6 Larkspur Landscaping began construction of a new plant on December 1, 2017. On this date, the company purchased a parcel of land for $140,400 in cash. In addition, it paid $2,640 in surv...

    Problem 10-6 Larkspur Landscaping began construction of a new plant on December 1, 2017. On this date, the company purchased a parcel of land for $140,400 in cash. In addition, it paid $2,640 in surveying costs and $3,840 for a title insurance policy. An old dwelling on the premises was demolished at a cost of $3,120, with $1,200 being received from the sale of materials. Architectural plans were also formalized on December 1, 2017, when the architect was paid $34,800....

  • On June 1, 2020, the Crocus Company began construction of a new manufacturing plant. The plant...

    On June 1, 2020, the Crocus Company began construction of a new manufacturing plant. The plant was completed on October 31, 2021. Expenditures on the project were as follows ($ in millions): July 1, 2020 74 October 1, 2020 42 February 1, 2021 50 April 1, 2021 31 September 1, 2021 30 October 1, 2021 16 On July 1, 2020, Crocus obtained a $90 million construction loan with a 6% interest rate. The loan was outstanding through the end of...

  • On June 1, 2020, the Crocus Company began construction of a new manufacturing plant. The plant...

    On June 1, 2020, the Crocus Company began construction of a new manufacturing plant. The plant was completed on October 31, 2021 Expenditures on the project were as follows is in millions) July 1, 2020 October 1, 2020 February 1.2021 April 1. 2021 September 1, 2021 October 1.2021 On July 1, 2020. Crocus obtained a $106 million construction loan with a 10% interest rate The loan was outstanding through the end of October, 2021 The company's only other interest-bearing debt...

  • On January 2, 2020, Bonita Industries began construction of a new citrus processing plant. The automated...

    On January 2, 2020, Bonita Industries began construction of a new citrus processing plant. The automated plant was finished and ready for use on September 30, 2021. Expenditures for the construction were as follows: January 2, 2020 September 1, 2020 December 31, 2020 March 31, 2021 September 30, 2021 $ 609000 1812000 1812000 812000 198000 1 1 Bonita Industries borrowed $3290000 on a construction loan at 12% interest on January 2, 2020. This loan was outstanding during the construction period....

  • On January 2, 2020, Marigold Corp. began construction of a new citrus processing plant. The automated...

    On January 2, 2020, Marigold Corp. began construction of a new citrus processing plant. The automated plant was finished and ready for use on September 30, 2021. Expenditures for the construction were as follows: January 2, 2020 September 1, 2020 December 31, 2020 March 31, 2021 September 30, 2021 $ 592000 1806000 1806000 1806000 1219000 Marigold Corp. borrowed $3330000 on a construction loan at 10% interest on January 2, 2020. This loan was outstanding during the construction period. The company...

  • On January 2, 2020, Vaughn Manufacturing began construction of a new citrus processing plant. The automated...

    On January 2, 2020, Vaughn Manufacturing began construction of a new citrus processing plant. The automated plant was finished and ready for use on September 30, 2021. Expenditures for the construction were as follows: January 2, 2020 $ 599000 September 1, 2020 1801200 December 31, 2020 1801200 March 31, 2021 1801200 September 30, 2021 1220000 Vaughn Manufacturing borrowed $3230000 on a construction loan at 10% interest on January 2, 2020. This loan was outstanding during the construction period. The company...

  • Problem 10-5 On January 1, 2020, Sheridan Corporation purchased for $680,000 a tract of land (site...

    Problem 10-5 On January 1, 2020, Sheridan Corporation purchased for $680,000 a tract of land (site number 101) with a building. Sheridan paid a real estate broker’s commission of $48,960, legal fees of $8,160, and title guarantee insurance of $24,480. The closing statement indicated that the land value was $680,000 and the building value was $136,000. Shortly after acquisition, the building was razed at a cost of $73,440. Sheridan entered into a $4,080,000 fixed-price contract with Slatkin Builders, Inc. on...

  • Interest During Construction Matrix Inc. borrowed $1,000,000 at 8% to finance the construction of a new building for its own use. Construction began on January 1, 2016, and was completed on October...

    Interest During Construction Matrix Inc. borrowed $1,000,000 at 8% to finance the construction of a new building for its own use. Construction began on January 1, 2016, and was completed on October 31, 2016. Expenditures related to this building were: January 1 $252,000 (includes cost of purchasing land of $150,000) May 1 310,000 July 1 420,000 October 31 276,000 In addition, Matrix had additional debt (unrelated to the construction) of $500,000 at 9% and $800,000 at 10%. All debt was...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT