On June 1, 2020, the Crocus Company began construction of a new manufacturing plant. The plant...

On June 1, 2020, the Crocus Company began construction of a new manufacturing plant. The plant was completed on October 31, 2021. Expenditures on the project were as follows ($ in millions):

July 1, 2020 74
October 1, 2020 42
February 1, 2021 50
April 1, 2021 31
September 1, 2021 30
October 1, 2021 16


On July 1, 2020, Crocus obtained a $90 million construction loan with a 6% interest rate. The loan was outstanding through the end of October, 2021. The company's only other interest-bearing debt was a long-term note for $100 million with an interest rate of 8%. This note was outstanding during all of 2020 and 2021. The company's fiscal year-end is December 31.

In computing the capitalized interest for 2021, Crocus' average accumulated expenditures are:

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Crocus' average accumulated expenditures = $193.15

Average expenditures for 2020: ($74 million x 6/6) + $42 million x 3/6) = $955 million. The interest is: $95 million x 6% x 6/12 = $2.85 million

Average expenditures for 2021:

Expenditures

Proportion of year

Average accumulated expenditures

118.85 (74+42+2.85)

10/10

118.85

50

9/10

45.00

31

7/10

21.70

30

2/10

6.00

16

1/10

1.60

$193.15

Add a comment
Know the answer?
Add Answer to:
On June 1, 2020, the Crocus Company began construction of a new manufacturing plant. The plant...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • On June 1, 2020, the Crocus Company began construction of a new manufacturing plant. The plant...

    On June 1, 2020, the Crocus Company began construction of a new manufacturing plant. The plant was completed on October 31, 2021 Expenditures on the project were as follows is in millions) July 1, 2020 October 1, 2020 February 1.2021 April 1. 2021 September 1, 2021 October 1.2021 On July 1, 2020. Crocus obtained a $106 million construction loan with a 10% interest rate The loan was outstanding through the end of October, 2021 The company's only other interest-bearing debt...

  • Question 9 (1 point) On June 1, 2017, the Crocus Company began construction of a new...

    Question 9 (1 point) On June 1, 2017, the Crocus Company began construction of a new manufacturing plant. The plant was completed on October 31, 2018. Expenditures on the project were as follows ($ in millions): 5 4 July 1, 2017 October 1, 2017 February 1, 2018 April 1, 2018 September 1, 2018 October 1, 2018 On July 1, 2017. Crocus obtained a $ 70 million construction loan with a 6% interest rate. The loan was outstanding through the end...

  • On January 2, 2020, Vaughn Manufacturing began construction of a new citrus processing plant. The automated...

    On January 2, 2020, Vaughn Manufacturing began construction of a new citrus processing plant. The automated plant was finished and ready for use on September 30, 2021. Expenditures for the construction were as follows: January 2, 2020 $ 599000 September 1, 2020 1801200 December 31, 2020 1801200 March 31, 2021 1801200 September 30, 2021 1220000 Vaughn Manufacturing borrowed $3230000 on a construction loan at 10% interest on January 2, 2020. This loan was outstanding during the construction period. The company...

  • Sheridan Landscaping began construction of a new plant on December 1, 2020. On this date, the...

    Sheridan Landscaping began construction of a new plant on December 1, 2020. On this date, the company purchased a parcel of land for $138,000 in cash. In addition, it paid $2,880 in surveying costs and $4,560 for a title insurance policy. An old dwelling on the premises was demolished at a cost of $3,360, with $960 being received from the sale of materials. Architectural plans were also formalized on December 1, 2020, when the architect was paid $32,400. The necessary...

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,280,000 960,000 1,160,000 960,000 324,000 657,000 954,000 On January 1, 2021, the company obtained a $3,600,000 construction loan with a 15% interest rate. The...

  • Please separate each part. On January 1, 2021, the Mason Manufacturing Company began construction of a...

    Please separate each part. On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,680,000 1,260,000 1,460,000 1,260,000 369,000 702,000 999,000 On January 1, 2021, the company obtained a $4,000,000 construction loan with a...

  • On January 2, 2020, Bonita Industries began construction of a new citrus processing plant. The automated...

    On January 2, 2020, Bonita Industries began construction of a new citrus processing plant. The automated plant was finished and ready for use on September 30, 2021. Expenditures for the construction were as follows: January 2, 2020 September 1, 2020 December 31, 2020 March 31, 2021 September 30, 2021 $ 609000 1812000 1812000 812000 198000 1 1 Bonita Industries borrowed $3290000 on a construction loan at 12% interest on January 2, 2020. This loan was outstanding during the construction period....

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,000,000 March 1, 2021 600,000 June 30, 2021 800,000 October 1, 2021 600,000 January 31, 2022 270,000 April 30, 2022 585,000 August 31, 2022 900,000 On January 1, 2021, the company obtained a $3 million construction loan with a 10% interest...

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,740,000 1,380,000 1, 580,000 1, 380,000 387,000 720,000 1, 017, 000 On January 1, 2021, the company obtained a $4,300,000 construction loan with a...

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,280,000 720,000 920,000 720,000 288,000 621,000 918,000 On January 1, 2021, the company obtained a $3,200,000 construction loan with a 15% interest rate. The...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT