Question

Question 9 (1 point) On June 1, 2017, the Crocus Company began construction of a new manufacturing plant. The plant was compl

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution:

Year 2017: Weighted-Average accumulated expenditure and interest capitalized
Date Amount Capitalization period Weighted Average Accumulated Expenditures
1-Jul-17 $54,000,000 6/6 $54,000,000
1-Oct-17 $22,000,000 3/6 $11,000,000
Total $76,000,000 $65,000,000
*Interest rate 6%
Interest capitalized in 2017 $1,950,000
Year 2018: Weighted-Average accumulated expenditure
Date Amount Capitalization period Weighted Average Accumulated Expenditures
1-Jan-18 $77,950,000 10/10 $77,950,000
1-Feb-18 $30,000,000 9/10 $27,000,000
1-Apr-18 $21,000,000 7/10 $14,700,000
1-Sep-18 $20,000,000 2/10 $4,000,000
1-Oct-18 $6,000,000 1/10 $600,000
Total $154,950,000 $124,250,000
Year 2018: Interest Capitalized
Debt Amount
70000000*6%*10/12 = $3,500,000
(124250000- 70000000)*8%*10/12 = $3,616,667
Total interest capitalized in 2018 $7,116,667

Hence last option "None of these answer choices are correct" is correct.

Add a comment
Know the answer?
Add Answer to:
Question 9 (1 point) On June 1, 2017, the Crocus Company began construction of a new...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • On June 1, 2020, the Crocus Company began construction of a new manufacturing plant. The plant...

    On June 1, 2020, the Crocus Company began construction of a new manufacturing plant. The plant was completed on October 31, 2021. Expenditures on the project were as follows ($ in millions): July 1, 2020 74 October 1, 2020 42 February 1, 2021 50 April 1, 2021 31 September 1, 2021 30 October 1, 2021 16 On July 1, 2020, Crocus obtained a $90 million construction loan with a 6% interest rate. The loan was outstanding through the end of...

  • On June 1, 2020, the Crocus Company began construction of a new manufacturing plant. The plant...

    On June 1, 2020, the Crocus Company began construction of a new manufacturing plant. The plant was completed on October 31, 2021 Expenditures on the project were as follows is in millions) July 1, 2020 October 1, 2020 February 1.2021 April 1. 2021 September 1, 2021 October 1.2021 On July 1, 2020. Crocus obtained a $106 million construction loan with a 10% interest rate The loan was outstanding through the end of October, 2021 The company's only other interest-bearing debt...

  • On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $1,000,000 March 1, 2018 600,000 800,000 June 30, 2018 October 1, 2018 600,000 270,000 January 31, 2019 April 30, 2019 585,000 August 31, 2019 900,000 On January 1, 2018, the company obtained a $3 million construction loan with a 10% interest rate....

  • help please On January 1, 2018, the Mason Manufacturing Company began construction of a building to...

    help please On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019 Expenditures on the project were as follows: points 8 03:03:29 January 1, 2018 March 1, 2018 June 30, 2018 October 1, 2018 January 31, 2019 April 30, 2019 August 31, 2019 $1,070,000 840,000 380,000 710,000 1,170,000 1.485.000 2,700,000 eBook Print References On January 1, 2018, the company obtained a $3...

  • On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 March 1, 2018 June 30, 2018 October 1, 2018 January 31, 2019 April 30, 2019 August 31, 2019 $1,000.000 840,000 480.009 630.000 630,eee 945,000 1,620, DBC On January 1, 2018, the company obtained a $3 million construction loan with a 11% interest...

  • On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 2,020,000 March 1, 2018 1,740,000 June 30, 2018 1,940,000 October 1, 2018 1,740,000 January 31, 2019 441,000 April 30, 2019 774,000 August 31, 2019 1,071,000 On January 1, 2018, the company obtained a $4,900,000 construction loan with a 12% interest rate....

  • help please On January 1, 2018, the Mason Manufacturing Company began construction of a building to...

    help please On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019 Expenditures on the project were as follows: January 1, 2018 March 1, 2018 June 30, 2018 October 1, 2018 January 31, 2019 April 30, 2019 August 31, 2019 $1,070,e00 840,000 380, e00 Dok nt 710,000 1,170,000 1,485,000 2,700,e0e nces On January 1, 2018, the company obtained a $3 million construction...

  • explain it please Check my work On January 1, 2018, the Mason Manufacturing Company began construction...

    explain it please Check my work On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019 Expenditures on the project were as follows: January 1, 2018 March 1, 2018 June 30, 2018 October 1, 2018 January 31, 2019 April 30, 2019 August 31, 2019 $1,000,000 600,000 800,000 600.000 270,000 585,000 900,000 On January 1, 2018, the company obtained a $3 million construction...

  • On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 March 1, 2018 June 30, 2018 October 1, 2018 January 31, 2019 April 30, 2019 August 31, 2019 $1,350,000 1, 080, 000 1, 280,000 1,080,000 342, 000 675, 000 972, 000 On January 1, 2018, the company obtained a $3,800,000 construction loan...

  • On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 March 1, 2018 June 30, 2018 October 1, 2018 January 31, 2019 April 30, 2019 August 31, 2019 $1,350,000 1, 080, 000 1, 280,000 1,080,000 342, 000 675, 000 972, 000 On January 1, 2018, the company obtained a $3,800,000 construction loan...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT