The answer is the 1st option i.e. $250.65 million
Computation:
The amount of interest that will be capitalized in 2020 = 90*6/6 + 58*3/6
= 119. Thus interest is 119 * 10% * 6/12 = 5.95
Thus avg. accumulated expenses are: (90+58+5.95)*10/10 + 66*9/10 + 39*7/10 + 38*2/10 + 24*1/10
= $250.65 million
On June 1, 2020, the Crocus Company began construction of a new manufacturing plant. The plant...
On June 1, 2020, the Crocus Company began construction of a new manufacturing plant. The plant was completed on October 31, 2021. Expenditures on the project were as follows ($ in millions): July 1, 2020 74 October 1, 2020 42 February 1, 2021 50 April 1, 2021 31 September 1, 2021 30 October 1, 2021 16 On July 1, 2020, Crocus obtained a $90 million construction loan with a 6% interest rate. The loan was outstanding through the end of...
Question 9 (1 point) On June 1, 2017, the Crocus Company began construction of a new manufacturing plant. The plant was completed on October 31, 2018. Expenditures on the project were as follows ($ in millions): 5 4 July 1, 2017 October 1, 2017 February 1, 2018 April 1, 2018 September 1, 2018 October 1, 2018 On July 1, 2017. Crocus obtained a $ 70 million construction loan with a 6% interest rate. The loan was outstanding through the end...
On January 2, 2020, Vaughn Manufacturing began construction of a new citrus processing plant. The automated plant was finished and ready for use on September 30, 2021. Expenditures for the construction were as follows: January 2, 2020 $ 599000 September 1, 2020 1801200 December 31, 2020 1801200 March 31, 2021 1801200 September 30, 2021 1220000 Vaughn Manufacturing borrowed $3230000 on a construction loan at 10% interest on January 2, 2020. This loan was outstanding during the construction period. The company...
Sheridan Landscaping began construction of a new plant on December 1, 2020. On this date, the company purchased a parcel of land for $138,000 in cash. In addition, it paid $2,880 in surveying costs and $4,560 for a title insurance policy. An old dwelling on the premises was demolished at a cost of $3,360, with $960 being received from the sale of materials. Architectural plans were also formalized on December 1, 2020, when the architect was paid $32,400. The necessary...
On January 2, 2020, Bonita Industries began construction of a new citrus processing plant. The automated plant was finished and ready for use on September 30, 2021. Expenditures for the construction were as follows: January 2, 2020 September 1, 2020 December 31, 2020 March 31, 2021 September 30, 2021 $ 609000 1812000 1812000 812000 198000 1 1 Bonita Industries borrowed $3290000 on a construction loan at 12% interest on January 2, 2020. This loan was outstanding during the construction period....
On January 2, 2020, Marigold Corp. began construction of a new citrus processing plant. The automated plant was finished and ready for use on September 30, 2021. Expenditures for the construction were as follows: January 2, 2020 September 1, 2020 December 31, 2020 March 31, 2021 September 30, 2021 $ 592000 1806000 1806000 1806000 1219000 Marigold Corp. borrowed $3330000 on a construction loan at 10% interest on January 2, 2020. This loan was outstanding during the construction period. The company...
15 On January 1, 2020, Southtree Co. began construction of a building to be used as its office headquarters. The building is expected to be completed on December 31, 2020. Expenditures on this project during 2020 were as follows: January $100,000 March 1 360,000 June 15 270,000 October 31" 153,000 On Jan. 1, 2020, the company obtained a $500,000 specific construction loan with a 6% interest rate. The loan was outstanding during the entire construction period. The company's other interest-bearing...
On January 1, 2021, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2022. The company borrowed $2,000,000 at 13% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2021: points $5.829.oe. 17% bonds $3.880.880.13% long-term note Construction expenditures incurred during 2021 were as follows: $ January 1 March 31 June 30 September 30 December 31 820,000 1,420.000...
On January 1, 2021, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2022. The company borrowed $1,850,000 at 10% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2021: $4,000,000, 14% bonds $1,000,000, 10% long-term note Construction expenditures incurred during 2021 were as follows: January 1 $ 800,000 March 31 1,400,000 June 30 1,040,000 September 30 800,000...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,280,000 960,000 1,160,000 960,000 324,000 657,000 954,000 On January 1, 2021, the company obtained a $3,600,000 construction loan with a 15% interest rate. The...