Question

1. Suppose a university has an opportunity to build a solar facility just outside of the...

1. Suppose a university has an opportunity to build a solar facility just outside of the city that would generate about 120,000 MWh per year (1 MWh = 1000 KWh), and cost $25 million to install.

To determine if this is a good deal for the university, you need to analyze the economics. Assume the market price for electricity over the next five years is $48 per MWh and there is a 5-year project horizon. Evaluate this decision using a 3% discount rate. For this problem, assume that the costs of installing the solar panels occur at time 0 (beginning of year 1), and the benefits occur at the end of each subsequent year (end of year 1, end of year 2, etc.). The 5 year horizon implies that you only need to evaluate the gains of the solar project over a 5 year period. Solar panels obviously will provide benefits in the future if they remain installed, but you should ignore years beyond the 5th year for this analysis.

The present value of the stream of costs is $ _______ million and the present value of the stream of benefits is $ ________ million.

A. 0;28.8

B. 25; 23.5

C.25; 26.4

D. 25; 28.8

2. Use the data for the last question as you consider this question. Suppose Ohio State University sells the resulting renewable energy credits from this project on the market at the current price of renewable energy credits in Ohio of $5 per MWh. How much would Ohio State make each year selling renewable energy credits (RECs), and is this a benefit or a cost to the University?

3.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

i. The cost to install a project is $25000000, so the stream of cost is $25000000.

The cash flows in this project are same across five years = $48*120000= $5760000

This is the periodic stream of benefit from the project for next 5 years.

To calculate the present value when cash flows occur at the end of the year (remember payments can be made at the beginning of the year as well, in that case the formula will change), the formula to be used is =

PV= C*((1-(1+r)^-n))/r)

C= Periodic cash flow

n= No. of periods/payments to be made

r= interest rate

PV= 28,288,771

So, PV of stream of benefit is $28,288,771.

So, answer is option D

ii) In this case we have to calculate the NPV of the project, if NPV is positive, the project is beneficial

NPV = (C)/( 1+r) t - Initial investment

C= Cash flows in the time period= 5*120000

r = Discount rate= 3%

t = time period= 5

NPV = -22,252,175.69. Since it is negative, the project is not beneficial, it is the cost to the university.

Add a comment
Know the answer?
Add Answer to:
1. Suppose a university has an opportunity to build a solar facility just outside of the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 1. Suppose MSU has an opportunity to build a solar facility just outside of Ann Arbor...

    1. Suppose MSU has an opportunity to build a solar facility just outside of Ann Arbor that would generate about 120,000 MWh per year (1 MWh = 1000 KWh), and cost $25 million to install. To determine if this is a good deal for the university, you need to analyze the economics. Assume the market price for electricity over the next five years is $48 per MWh and there is a 5-year project horizon. Evaluate this decision using a 3%...

  • I really need help with number 5 1. Suppose MSU has an opportunity to build a solar facility just outside of Ann Arbor...

    I really need help with number 5 1. Suppose MSU has an opportunity to build a solar facility just outside of Ann Arbor that would generate about 120,000 MWh per year (1 MWh = 1000 KWh), and cost $25 million to install. To determine if this is a good deal for the university, you need to analyze the economics. Assume the market price for electricity over the next five years is $48 per MWh and there is a 5-year project...

  • A university spent $2 million to install solar panels atop a parking garage. These panels will...

    A university spent $2 million to install solar panels atop a parking garage. These panels will have a capacity of 800 kilowatts (kW) and have a life expectancy of 20 years. Suppose that the discount rate is 10%, that electricity can be purchased at $0.30 per kilowatt-hour (kWh), and that the marginal cost of electricity production using the solar panels is zero. Hint: It may be easier to think of the present value of operating the solar panels for 1...

  • A university spent $1.9 million to install solar panels atop a parking garage. These panels will...

    A university spent $1.9 million to install solar panels atop a parking garage. These panels will have a capacity of 300 kilowatts (kW) and have a life expectancy of 20 years. Suppose that the discount rate is 20%, that electricity can be purchased at $0.10 per kilowatt-hour (kWh), and that the marginal cost of electricity production using the solar panels is zero. Hint: It may be easier to think of the present value of operating the solar panels for 1...

  • 4. Individual Problems 5-4 A university spent $1.6 million to install solar panels atop a parking...

    4. Individual Problems 5-4 A university spent $1.6 million to install solar panels atop a parking garage. These panels will have a capacity of 400 kilowatts (kW) and have a life expectancy of 20 years. Suppose that the discount rate is 10%, that electricity can be purchased at $0.10 per kilowatt-hour (kWh), and that the marginal cost of electricity production using the solar panels is zero. Hint: It may be easier to think of the present value of operating the...

  • The developer and owner of a shopping mall is planning to install solar PV panels on...

    The developer and owner of a shopping mall is planning to install solar PV panels on the roof top. Project Costs: The 100-kw system will cost $225,000 to install on 600 m2 of space available on the roof top. It will have a useful life 20 years and a salvage value of $2,000. Annual operations and maintenance cost will be $1,500. Energy output: Based on Singapore weather conditions, the system is capable of producing 170,000 kwh of electricity in the...

  • Question The developer and owner of a shopping mall is planning to install solar PV panels...

    Question The developer and owner of a shopping mall is planning to install solar PV panels on the roof top. Project Costs: The 100-kw system will cost $225,000 to install on 600 m2 of space available on the roof top. It will have a useful life 20 years and a salvage value of $2,000. Annual operations and maintenance cost will be $1,500. Energy output: Based on Singapore weather conditions, the system is capable of producing 170,000 kwh of electricity in...

  • Suppose that you invest $170 per month (before taxes) for 25 years (300 payments) and the...

    Suppose that you invest $170 per month (before taxes) for 25 years (300 payments) and the annual interest rate (APR) is 7%, compounded monthly. If your income tax bracket is 32%, what lump sum, after-tax distribution can be taken at the end of 25 years? $ can be taken at the end of 25 years after-tax distribution. (Round to the nearest dollar.) Nowadays it is very important to reduce one's carbon "footprint" (how much carbon we produce in our daily...

  • 1 A renewable energy electricity supply technology has the following characteristics: Capital cost ($) Annual operating...

    1 A renewable energy electricity supply technology has the following characteristics: Capital cost ($) Annual operating cost ($) Lifetime (years) Salvage value ($) Annual electricity supplied (MWh) 300 000 27 200 25 40 000 400 1.1 If the owner can sell the electricity at 25 c/kWh, what is the simple payback period for the technology? 1.2 Would the owner invest in this technology if (s)he set a strict maximum four-year payback period? 1.3 What would the selling price for the...

  • Question 1 Solar Power Ltd., a small Kumasi –based manufacturer and distributor of solar energy panels,...

    Question 1 Solar Power Ltd., a small Kumasi –based manufacturer and distributor of solar energy panels, was in its first year of operation. The company was conceived and controlled by two retired executives. Nana Darkwa, an engineer by profession, developed the basic patent for the solar panels. He lacked adequate liquid resources to finance the venture, although he did control a fair amount of wealth. Yaw Manu’s chosen field of endeavor was real estate. He, too, possessed few pied real...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT