I can figure this question out until the last step of the NPV calculation
Initial cash outflow = Fixed capital Investment + Working capital Investment = 715,000 + 59,000 = 774,000
Now we will calculate the cash flow of each year of the project
Particulars | Year 1 | Year 2 | Year 3 | Year 4 | Year 5 | Year 6 |
Savings in Pre-tax Operating Cost | 207000 | 207000 | 207000 | 207000 | 207000 | 207000 |
Tax @ 22% | 45540 | 45540 | 45540 | 45540 | 45540 | 45540 |
Net Savings | 161460 | 161460 | 161460 | 161460 | 161460 | 161460 |
Aftertax Salvage Value @ Year 6 | 75660 | |||||
Return of Working Capital | 59000 | |||||
Cash Flow | 161460 | 161460 | 161460 | 161460 | 161460 | 296120 |
NPV of the project:
Particulars | |
Cash Outflow | -774000 |
Cash inflow at Year 1 | 161460 |
Cash inflow at Year 2 | 161460 |
Cash inflow at Year 3 | 161460 |
Cash inflow at Year 4 | 161460 |
Cash inflow at Year 5 | 161460 |
Cash inflow at Year 6 | 296120 |
Cost of capital | 8.00% |
Present value of cash flows | ₹ 8,31,268.79 |
Net present value of cash flow | ₹ 57,268.79 |
NPV = 57,268.79
I can figure this question out until the last step of the NPV calculation Kolby's Korndogs...
Kolby's Korndogs is looking at a new sausage system with an installed cost of $655,000. This cost will be depreciated straightline to zero over the project's five-year life, at the end of which the sausage system can be scrapped for $85,000. The sausage system will save the firm $183,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $35,000. If the tax rate is 22 percent and the discount rate is...
Kolby's Korndogs is looking at a new sausage system with an installed cost of $730,00o. This cost will be depreciated straight-line to zero over the project's 7-year life, at the end of which the sausage system can be scrapped for $100,000. The sausage system will save the firm $213,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $65,000. If the tax rate is 25 percent and the discount rate is...
Kolby's Korndogs is looking at a new sausage system with an installed cost of $750,000. This cost will be depreciated straight-line to zero over the project's 7-year life, at the end of which the sausage system can be scrapped for $104,000. The sausage system will save the firm $221,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $73,000. If the tax rate is 24 percent and the discount rate is...
Kolby’s Korndogs is looking at a new sausage system with an installed cost of $715,000. This cost will be depreciated straight-line to zero over the project’s 6-year life, at the end of which the sausage system can be scrapped for $97,000. The sausage system will save the firm $207,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $59,000. If the tax rate is 22 percent and the discount rate is...
Kolby's Korndogs is looking at a new sausage system with an installed cost of $725,000. This cost will be depreciated straight-line to zero over the project's 7-year life, at the end of which the sausage system can be scrapped for $99,000. The sausage system will save the firm $211,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $63,000. If the tax rate is 24 percent and the discount rate is...
Kolby's Korndogs is looking at a new sausage system with an installed cost of $735,000. This cost will be depreciated straight-line to zero over the project's five-year life, at the end of which the sausage system can be scrapped for $105,000. The sausage system will save the firm $204,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $35,000. If the tax rate is 34 percent and the discount rate is...
Kolby’s Korndogs is looking at a new sausage system with an installed cost of $715,000. The asset qualifies for 100 percent bonus depreciation and can be scrapped for $97,000 at the end of the project’s 5-year life. The sausage system will save the firm $207,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $59,000. If the tax rate is 22 percent and the discount rate is 8 percent, what is...
Kolby's Korndogs is looking at a new sausage system with an installed cost of $800,000. This cost will be depreciated straight-line to zero over the project's five- year life, at the end of which the sausage system can be scrapped for $95,000. The sausage system will save the firm $150,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $45,000. If the tax rate is 35 percent and the discount rate...
Kolby's Korndogs is looking at a new sausage system with an installed cost of $720,000. The asset qualifies for 100 percent bonus depreciation and can be scrapped for $98.000 at the end of the project's 5-year life. The sausage system will save the firm $209,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $61,000. If the tax rate is 23 percent and the discount rate is 9 percent, what is...
Kolby's Korndogs is looking at a new sausage system with an installed cost of $670,000 The asset qualities for 100 percent bonus depreciation and can be scrapped for $88.000 at the end of the project's 5-year life. The sausage system will save the firm $213,000 per year in pretax operating costs and the system requires an initial investment in net working capital of $41.000. If the tax rate is 23 percent and the discount rate is 11 percent, what is...