Part A
Weighted-Average Accumulated Expenditures |
X |
Interest Rate |
= |
Avoidable Interest |
2000000 |
12% |
240000 |
||
1600000 |
10.42% |
166720 |
||
3600000 |
$406720 |
Weighted-average interest rate computation |
Principal |
Interest |
10% short-term loan |
1400000 |
140000 |
11% long-term loan |
1000000 |
110000 |
2400000 |
250000 |
Weighted-average interest rate = 250000/2400000 = 10.42%
Part B
Actual Interest |
||
Construction loan |
$2,000,000 X 12% = |
240000 |
Short-term loan |
$1,400,000 X 10% = |
140000 |
Long-term loan |
$1,000,000 X 11% = |
110000 |
Total |
$490000 |
Avoidable interest < actual interest, and thus avoidable interest is capitalized
Cost = 5200000+406720 = $5606720
Depreciation expense = (5606720-300000)/30 = $176891
Acquisition and Disposition of Property, Plant, and Equipment Instructions Prepare the entry that should have been...
quisition and Disposition of Property, Plant, and Equipment Instructions Prepare the entry that should have been made at the dat E10.7 (LO 2) (Capitalization of Interest) Harrisburg of a combination office and warehouse building for its own use at an estimates January 1, 2020. Harrisburg expected to complete the building by Decem arrisburg expected to complete the building by December 31, 2020. Harrisburg nasce following debt obligations outstanding during the construction period. anization of Interest) Harrisburg Furniture Company started construction...
Instructions Prepare the entry that should have been made at the date of each acquisition. E10-7 (Capitalization of Interest) Harrisburg Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $5,000,000 on January 1, 2014. Harrisburg expected to complete the building by December 31, 2014. Harrisburg has the following debt obligations outstanding during the construction period. Construction loan�12% interest, payable semiannually, issued December 31, 2013 $2,000,000 Short-term loan�10% interest, payable...
103) (Capitalization of Inter TO LOS house building rusting by Decemb wach acquisition ation of Interest) Harrisburg Furniture Company started construction of for its own use at an estimated cost of $5,000,000 on January 1, 2017. Harrisburg expected to com Furniture Company started construction of a combination office and umber 31, 2017. Harrisburg has the follow nowing debt obligations outstanding during the construction period. Construction loan-12% Interest, payable semiannually, issued December 31, 2016 $2,000,000 Short-term loan-10interest, payable monthly, and principal...
Harrisburg Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $5,000,000 on January 1, 2020. Harrisburg expected to complete the building by December 31, 2020. Harrisburg has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2019 $2,000,000 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 1,400,000 Long-term loan-11% interest, payable on January 1 of...
Pronghorn Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $13,000,000 on January 1, 2020. Pronghorn expected to complete the building by December 31, 2020. Pronghorn has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2019 $5,200,000Short-term loan-10% interest, payable monthly, and principal...
Exercise 10-07 Sheridan Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $13,000,000 on January 1, 2020. Sheridan expected to complete the building by December 31, 2020. Sheridan has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2019 $5,200,000 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 3,640,000 Long-term loan-11% interest, payable on January...
E10.7B (L0 2) (Capitalization of Interest) Bagwell Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $2,500,000 on January 1, 2020. Bagwell expected to complete the building by December 31, 2020. Bagwell has the following debt obligations outstanding during the construction period. Construction loan—15% interest, payable semiannually, issued December 31, 2019 Short-term loan—10% interest, payable monthly, and principal payable $1,000,000 at maturity on May 30, 2021 Long-term loan—11% interest,...
Pronghorn Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $8,500,000 on January 1, 2020. Pronghorn expected to complete the building by December 31, 2020. Pronghorn has the following debt obligations outstanding during the construction period. Construction loan-10% interest, payable semiannually, issued December 31, 2019 $3,400,000 Short-term loan-8% interest, payable monthly, and principal payable at maturity on May 30, 2021 $2,380,000 Long-term loan-9% interest, payable on January 1 of...
Coronado Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $7,500,000 on January 1, 2020. Coronado expected to complete the building by December 31, 2020. Coronado has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2019 $3,000,000 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 2,100,000 Long-term loan-11% interest, payable on January 1 of...
Exercise 10-07 (Part Level Submission) Ivanhoe Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $4,500,000 on January 1, 2020. Ivanhoe expected to complete the building by December 31, 2020. Ivanhoe has the following debt obligations outstanding during the construction period. Exercise 10-07 (Part Level Submission) Ivanhoe Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $4,500,000 on...