Question

Required information [The following information applies to the questions displayed below] Pert 3 of 5 In 2018, the Westgate C

0 0
Add a comment Improve this question Transcribed image text
Answer #1


Please hit LIKE button if this helped. For any further explanation, please put your query in comment, will get back to you. CPart 2b: 2019 Journal entries: S No Account Debit Credit $ 2,738,000 $ 2,738,000 $ 2,650,000 $ 2,650,000 Construction in Prog

Add a comment
Know the answer?
Add Answer to:
Required information [The following information applies to the questions displayed below] Pert 3 of 5 In...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Required information [The following information applies to the questions displayed below.) Part 5 of 5 In...

    Required information [The following information applies to the questions displayed below.) Part 5 of 5 In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: points 2020 $2,849,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $2,072,000 5,328,000 2,160,000 1,880,000 2019 $2,738,000...

  • Required information [The following information applies to the questions displayed below] In 2018, the Westgate Construction...

    Required information [The following information applies to the questions displayed below] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $2,072,000 $2,738,000 2,590, 000 2,650, 000 $2,849,000 Estimated costs to complete as of year-end Billings during the year Cash collections during the year 5,328,000 2,160,000 1,880,000 0...

  • Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $2,580,000 6,020,000 2,060,000 1,830,000 2019 $4,042,000 1,978,000 4,562,000 4,200,000 2020 $2,175,800 0 3,378,000...

  • Required information The following information applies to the questions displayed below) In 2018, the Westgate Construction...

    Required information The following information applies to the questions displayed below) In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $2,200,000 Coat incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $2,400,000 5,600,000 2,000,000 1,800,000 2019 $3,600,000 2,000,000 4,000,000 3,600,000 4,000,000 4,600,000...

  • Required information [The following information applies to the questions displayed below. In 2018, the Westgate Construction...

    Required information [The following information applies to the questions displayed below. In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows 2019 $2,542,000 $3,772,000 $2,074,600 1,886,000 2,020,000 4,294,0003,686,000 1,810,000 3,800,000 4,390,000 2018 2020 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 5,658,000 Westgate...

  • Required information (The following information applies to the questions displayed below.] In 2018, the Westgate Construction...

    Required information (The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $1,940,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $ 2,604,000 5,796,000 2,040,000 1,820,000 2019 $4,032,000 1,764,000 4,596,000 4,000,000 3,364,000...

  • The following information applies to the questions displayed below In 2018, the Westgate Construction Company entered...

    The following information applies to the questions displayed below In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2019 $2,542,000 3,772,000 $2,074,600 1, 886,000 2,020,000 ,294,000 3,686,000 1,810,000 3, 800,000 4,390,000 2018 2020 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 5,658,000...

  • ! Required information [The following information applies to the questions displayed below.] In 2018, the Westgate...

    ! Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $1,940,400 2018 $2,604,000 5,796,000 2,040,000 1,820,000 2019 $4,032,000 1,764,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 4,596,000 4,000,000 3,364,000...

  • Required information [The following information applies to the questions displayed below.]    In 2018, the Westgate...

    Required information [The following information applies to the questions displayed below.]    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,204,000 $ 3,192,000 $ 2,424,400 Estimated costs to complete as of year-end 5,396,000 2,204,000 0 Billings during the year 2,140,000 3,256,000 4,604,000 Cash collections during...

  • Required information The following information applies to the questions displayed below) In 2018, the Westgate Construction...

    Required information The following information applies to the questions displayed below) In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $2,200,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $2,400,000 5,600,000 2,000,000 1,800,000 2019 $3,600,000 2.000.000 4,000,000 3,600,000 4.000.000 4.600.000...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT