Question

project completion [LO5-9 Brady Construction Company contracted to build an apartment complex for a price of $6.300,000. Cons
project completion [LO5-9] Brady Construction Company contracted to build an apartment complex for a price of $6,300,000. Con
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Revenue Recognition over time

Situation-1
2018 2019 2020
A Cumulative Cost incurred for up to the end of year (cost for the year +previous year cumulative cost 1630 4150 5440
B Expected to incurred for the remaining 3810 1290 0
C Total Expected /Actual cost at completion (A+B) 5440 5440 5440
D Project value 6300 6300 6300
E Total Expected Gross profit (D)-(C) 860 860 860
F Cumulative Expected Gross profit/Loss to be recognised up to this year (See Note) 257.68 656.07 860.00
G Gross profit recognised up to previous year (Previous year F) 0 257.6838235294 656.0661764706
H Gross profit to be recognised for the year ($'000) (F)-(G) 257.6838235294 398.3823529412 203.9338235294
I Gross profit in $ (H*1000) 257,684 398,382 203,934
.
Situation-2
2018 2019 2020
A Cumulative Cost incurred for up to the end of year (cost for the year +previous year cumulative cost 1630 2920 5840
B Expected to incurred for the remaining 3810 2920 0
C Total Expected /Actual cost at completion (A+B) 5440 5840 5840
D Project value 6300 6300 6300
E Total Expected Gross profit (D)-(C) 860 460 460
F Cumulative Expected Gross profit/Loss to be recognised up to this year (See Note) 257.684 230.000 460.00
G Gross profit recognised up to previous year (Previous year F) 0 257.684 230.000
H Gross profit to be recognised for the year ($'000) (F)-(G) 257.684 -27.684 230.00
I Gross profit in $ (H*1000) 257,684 -27,684 230,000
Situation-3
2018 2019 2020
A Cumulative Cost incurred for up to the end of year (cost for the year +previous year cumulative cost 1630 4150 6790
B Expected to incurred for the remaining 3810 2540 0
C Total Expected /Actual cost at completion (A+B) 5440 6690 6790
D Project value 6300 6300 6300
E Total Expected Gross profit (D)-(C) 860 -390 -490
F Cumulative Expected Gross profit/Loss to be recognised up to this year (See Note) 257.68 -390.00 -490.00
G Gross profit recognised up to previous year (Previous year F) 0 257.6838235294 -390
H Gross profit to be recognised for the year ($'000) (F)-(G) 257.6838235294 -647.6838235294 -100
I Gross profit in $ (H*1000) 257,684 -647,684 -100,000
Situation-4
2018 2019 2020
A Cumulative Cost incurred for up to the end of year (cost for the year +previous year cumulative cost 630 3760 5020
B Expected to incurred for the remaining 4410 940 0
C Total Expected /Actual cost at completion (A+B) 5040 4700 5020
D Project value 6300 6300 6300
E Total Expected Gross profit (D)-(C) 1260 1600 1280
F Cumulative Expected Gross profit/Loss to be recognised up to this year (See Note) 157.50 1280.00 1280.00
G Gross profit recognised up to previous year (Previous year F) 0 157.5 1280
H Gross profit to be recognised for the year ($'000) (F)-(G) 157.5 1122.5 0
I Gross profit in $ (H*1000) 157,500 1,122,500 0
Situation-5
2018 2019 2020
A Cumulative Cost incurred for up to the end of year (cost for the year +previous year cumulative cost 630 3760 5970
B Expected to incurred for the remaining 4410 2540 0
C Total Expected /Actual cost at completion (A+B) 5040 6300 5970
D Project value 6300 6300 6300
E Total Expected Gross profit (D)-(C) 1260 0 330
F Cumulative Expected Gross profit/Loss to be recognised up to this year (See Note) 157.50 0.00 330.00
G Gross profit recognised up to previous year (Previous year F) 0 157.5 0
H Gross profit to be recognised for the year ($'000) (F)-(G) 157.5 -157.5 330
I Gross profit in $ (H*1000) 157,500 -157,500 330,000
Situation-6
2018 2019 2020
A Cumulative Cost incurred for up to the end of year (cost for the year +previous year cumulative cost 630 3760 6860
B Expected to incurred for the remaining 5855 2870 0
C Total Expected /Actual cost at completion (A+B) 6485 6630 6860
D Project value 6300 6300 6300
E Total Expected Gross profit (D)-(C) -185 -330 -560
F Cumulative Expected Gross profit/Loss to be recognised up to this year (See Note) -185.00 -330.00 -560.00
G Gross profit recognised up to previous year (Previous year F) 0 -185 -330
H Gross profit to be recognised for the year ($'000) (F)-(G) -185 -145 -230
I Gross profit in $ (H*1000) -185,000 -145,000 -230,000
Note:- (F)
Cumulative Expected Gross profit/Loss to be recognised up to this year (See Note)
If the figure E (Expected Gross profit ) is negative , then entire loss is to be considered
If the figure E (Expected Gross profit ) is positive , then this figure is arrived by the following formula:
=total expected gross profit('E') * cumulative cost incurred up to end of the YEAR ('A')/total expected cost('C')

Revenue Recognition at a time:-

2018 2019 2020
Situation-1 0 0 860000
Situation-2 0 0 460000
Situation-3 0 0 -490000
Situation-4 0 0 1280000
Situation-5 0 0 330000
Situation-6 0 0 -230000

Note:- The loss or profit will recognise only at the end of the project

Add a comment
Know the answer?
Add Answer to:
project completion [LO5-9 Brady Construction Company contracted to build an apartment complex for a price of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Check my work mode: This shows what is correct or incorrect for the work you have...

    Check my work mode: This shows what is correct or incorrect for the work you have completed so far. I dou Brady Construction Company contracted to build an apartment complex for a price of $6,300.000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Estimated Costs to Complete (As of the End of the Year...

  • Exercise 5-21 Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project completion (LO5-9)...

    Exercise 5-21 Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project completion (LO5-9) Brady Construction Company contracted to build an apartment complex for a price of $6,300,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Costs Incurred During Year Situation 2018 2019 2020 1 1,630 2,520 1,290 2 1,630 1,290...

  • Exercise 5-21 Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project completion (LO5-9)...

    Exercise 5-21 Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project completion (LO5-9) Brady Construction Company contracted to build an apartment complex for a price of $6,300,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Costs incurred During Year Situation 2018 2019 2020 1 1,630 2,520 1,290 2 1630 1,290...

  • 5-HW O Exercise 5-21 Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project...

    5-HW O Exercise 5-21 Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project completion (LO5-9) Brady Construction Company contracted to build an apartment complex for a price of $6,300,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Year Estimated costs to Complete Costs incurred During (As of the End of...

  •    Just need help with the four that are incorrect. Thank you! CICLAY WUIHUUU. HIS SUUWS...

       Just need help with the four that are incorrect. Thank you! CICLAY WUIHUUU. HIS SUUWS will is LUMELUI CURELIUI Lie wUIR you dve completed so lol. Il uue HOL Holtate comple Exercise 5-21 Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project completion (LO5-9) Brady Construction Company contracted to build an apartment complex for a price of $6,300,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered...

  • I just need help with situation 6, the two that are incorrect. thank you! Exercise 5-21...

    I just need help with situation 6, the two that are incorrect. thank you! Exercise 5-21 Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project completion (LO5-9) Brady Construction Company contracted to build an apartment complex for a price of $6,300,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Costs...

  • Brady Construction Company contracted to build an apartment complex for a price of $5,300,000. Construction began...

    Brady Construction Company contracted to build an apartment complex for a price of $5,300,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Estimated Costs to Complete (As of the End of the Year) Costs Incurred During Year Situation 2018 2019 2020 2018 2019 2020 11,530 2,220 990 3,210 990 2 1,530 990 2,520...

  • Brady Construction Company contracted to build an apartment complex for a price of $6,100,000. Construction began...

    Brady Construction Company contracted to build an apartment complex for a price of $6,100,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Costs Incurred During Year Situation 2018 2019 2020 1,610 2,460 1,230 1,610 1,230 2,840 3 1,610 2,460 2,480 4 6103,110 1,220 610 3,110 2,070 6 610 3,110 2,900 Estimated Costs to...

  • Brady Construction Company contracted to build an apartment complex for a price of $5,400,000. Construction began...

    Brady Construction Company contracted to build an apartment complex for a price of $5,400,000. Construction began in 2021 and was completed in 2023. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Situation Costs Incurred During Year 2021 2022 2023 1,540 2,250 1,020 1,540 1,020 2,560 1,540 2,250 1,920 540 3,040 1,080 540 3,040 1,580 540 3,040 2,200 Estimated costs to Complete (As...

  • Brady Construction Company contracted to build an apartment complex for a price of $5,000,000. Construction began...

    Brady Construction Company contracted to build an apartment complex for a price of $5,000,000. Construction began in 2021 and was completed in 2023. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Estimated Costs to Complete Costs Incurred During Year (As of the End of the Year) Situation 2021 2022 2023 2021 2022 2023 1 1,500 2,100 900 3,000 900 — 2 1,500...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT