Situation 3
Revenue recognized upon completion |
||
2018 |
2019 |
2020 |
0 |
(390000) |
(100000) |
Total loss = total revenue – total costs = 6300000-(1630000+2520000+2640000)= (490000)
Loss recognized in 2020 = 2640000 2018 actual cost – 2540000 (2017 estimated cost) = (100000)
Remaining 390000 loss is recognized in 2019
Situation 5
Revenue recognized upon completion |
||
2018 |
2019 |
2020 |
(230000) |
(100000) |
(230000) |
Total loss = total revenue – total costs = 6300000-(630000+3130000+3100000)= (560000)
Loss recognized in 2020 = 310000 2018 actual cost – 2870000 (2017 estimated cost) = (230000)
Remaining 330000 loss is recognized in 2018 and 2019
Just need help with the four that are incorrect. Thank you! CICLAY WUIHUUU. HIS SUUWS...
I just need help with situation 6, the two that are
incorrect.
thank you!
Exercise 5-21 Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project completion (LO5-9) Brady Construction Company contracted to build an apartment complex for a price of $6,300,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Costs...
Exercise 5-21 Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project completion (LO5-9) Brady Construction Company contracted to build an apartment complex for a price of $6,300,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Costs Incurred During Year Situation 2018 2019 2020 1 1,630 2,520 1,290 2 1,630 1,290...
Exercise 5-21 Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project completion (LO5-9) Brady Construction Company contracted to build an apartment complex for a price of $6,300,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Costs incurred During Year Situation 2018 2019 2020 1 1,630 2,520 1,290 2 1630 1,290...
project completion [LO5-9 Brady Construction Company contracted to build an apartment complex for a price of $6.300,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Costs incurred During Year Situation 2018 2019 2020 1 1630 2,520 1.290 2 1.630 1290 2,920 3 1,630 2.520 2.640 4 630 3.130 1.260 5 630 3.130 2.210 6...
Check my work mode: This shows what is correct or incorrect for the work you have completed so far. I dou Brady Construction Company contracted to build an apartment complex for a price of $6,300.000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Estimated Costs to Complete (As of the End of the Year...
5-HW O Exercise 5-21 Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project completion (LO5-9) Brady Construction Company contracted to build an apartment complex for a price of $6,300,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Year Estimated costs to Complete Costs incurred During (As of the End of...
Can you explain how you came to your answers. Just the answer
does me no good. Thank you so much!
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,400,000. During 2018, costs of $2,160,000 were incurred, with estimated costs of $4,160,000 yet to be incurred. Billings of $2,692,000 were sent, and cash collected was $2,410,000. In 2019, costs incurred were $2,692,000 with remaining costs estimated to be...
I
need help completing this. Thank you!!
Saved Help Save & Exit Submi Check my work Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,660,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated...
Just need help on a couple of these t-accounts
DO Recount Titles Cash Recounts Receivable Supplies Land Equipment Accumulated Depreciation Software Neculated mortisation Accounts Payable Notes Payable short-term) Salaries and Wages Payable Interest Payable Income Tax Payable Common Stock Retained Earnings Service Revenue Salaries and Wages Expense Depreciation Expense Sortisation Expense Income Tax Expense Interest Expense Supplies Expense Totals OOOO $106 $106 Transactions and events during 2018 (summarized in thousands of dollars) follow. a Borrowed $11 cash on March 1...
I just need help with the
statement of cash flow
Required: a. Record the transactions for the year in general journal form. b. Prepare a Statement of Revenues, Expenses, and Changes in Fund Net Position. c. Prepare a Statement of Net Position as of June 30, 2020. d. Prepare a Statement of Cash Flows for the year ended June 30, 2020. Assume all debt and interest are related to capital outlay. Assume the entire construction work in progress liability (see...