Question

CICLAY WUIHUUU. HIS SUUWS will is LUMELUI CURELIUI Lie wUIR you dve completed so lol. Il uue HOL Holtate comple Exercise 5-21
project All costs are Slateu uusalus Ur Lunds. Costs incurred During Year Situation 2018 2019 2020 1,630 2,520 1,290 1. 630 1  
Just need help with the four that are incorrect. Thank you!
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Situation 3

Revenue recognized upon completion

2018

2019

2020

0

(390000)

(100000)

Total loss = total revenue – total costs = 6300000-(1630000+2520000+2640000)= (490000)

Loss recognized in 2020 = 2640000 2018 actual cost – 2540000 (2017 estimated cost) = (100000)

Remaining 390000 loss is recognized in 2019

Situation 5

Revenue recognized upon completion

2018

2019

2020

(230000)

(100000)

(230000)

Total loss = total revenue – total costs = 6300000-(630000+3130000+3100000)= (560000)

Loss recognized in 2020 = 310000 2018 actual cost – 2870000 (2017 estimated cost) = (230000)

Remaining 330000 loss is recognized in 2018 and 2019

Add a comment
Know the answer?
Add Answer to:
   Just need help with the four that are incorrect. Thank you! CICLAY WUIHUUU. HIS SUUWS...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • I just need help with situation 6, the two that are incorrect. thank you! Exercise 5-21...

    I just need help with situation 6, the two that are incorrect. thank you! Exercise 5-21 Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project completion (LO5-9) Brady Construction Company contracted to build an apartment complex for a price of $6,300,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Costs...

  • Exercise 5-21 Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project completion (LO5-9)...

    Exercise 5-21 Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project completion (LO5-9) Brady Construction Company contracted to build an apartment complex for a price of $6,300,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Costs Incurred During Year Situation 2018 2019 2020 1 1,630 2,520 1,290 2 1,630 1,290...

  • Exercise 5-21 Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project completion (LO5-9)...

    Exercise 5-21 Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project completion (LO5-9) Brady Construction Company contracted to build an apartment complex for a price of $6,300,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Costs incurred During Year Situation 2018 2019 2020 1 1,630 2,520 1,290 2 1630 1,290...

  • project completion [LO5-9 Brady Construction Company contracted to build an apartment complex for a price of...

    project completion [LO5-9 Brady Construction Company contracted to build an apartment complex for a price of $6.300,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Costs incurred During Year Situation 2018 2019 2020 1 1630 2,520 1.290 2 1.630 1290 2,920 3 1,630 2.520 2.640 4 630 3.130 1.260 5 630 3.130 2.210 6...

  • Check my work mode: This shows what is correct or incorrect for the work you have...

    Check my work mode: This shows what is correct or incorrect for the work you have completed so far. I dou Brady Construction Company contracted to build an apartment complex for a price of $6,300.000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Estimated Costs to Complete (As of the End of the Year...

  • 5-HW O Exercise 5-21 Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project...

    5-HW O Exercise 5-21 Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project completion (LO5-9) Brady Construction Company contracted to build an apartment complex for a price of $6,300,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Year Estimated costs to Complete Costs incurred During (As of the End of...

  • Can you explain how you came to your answers. Just the answer does me no good....

    Can you explain how you came to your answers. Just the answer does me no good. Thank you so much! On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,400,000. During 2018, costs of $2,160,000 were incurred, with estimated costs of $4,160,000 yet to be incurred. Billings of $2,692,000 were sent, and cash collected was $2,410,000. In 2019, costs incurred were $2,692,000 with remaining costs estimated to be...

  • I need help completing this. Thank you!! Saved Help Save & Exit Submi Check my work...

    I need help completing this. Thank you!! Saved Help Save & Exit Submi Check my work Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,660,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated...

  • Just need help on a couple of these t-accounts DO Recount Titles Cash Recounts Receivable Supplies...

    Just need help on a couple of these t-accounts DO Recount Titles Cash Recounts Receivable Supplies Land Equipment Accumulated Depreciation Software Neculated mortisation Accounts Payable Notes Payable short-term) Salaries and Wages Payable Interest Payable Income Tax Payable Common Stock Retained Earnings Service Revenue Salaries and Wages Expense Depreciation Expense Sortisation Expense Income Tax Expense Interest Expense Supplies Expense Totals OOOO $106 $106 Transactions and events during 2018 (summarized in thousands of dollars) follow. a Borrowed $11 cash on March 1...

  • I just need help with the statement of cash flow Required: a. Record the transactions for...

    I just need help with the statement of cash flow Required: a. Record the transactions for the year in general journal form. b. Prepare a Statement of Revenues, Expenses, and Changes in Fund Net Position. c. Prepare a Statement of Net Position as of June 30, 2020. d. Prepare a Statement of Cash Flows for the year ended June 30, 2020. Assume all debt and interest are related to capital outlay. Assume the entire construction work in progress liability (see...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT