Question

Check my work mode: This shows what is correct or incorrect for the work you have completed so far. I dou Brady Construction
En 5 - HW Exercise 5-21 Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project complet
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Gross profit(loss) recognized Revenue recogniszed over time Revenue recognized upon completion Situations 2018 2019 2020 2018

Situation 2: Revenue 2018 = [ 1,630,000/ (1,630,000 +3,810,000)] x 6,300,000 = $1,887,684 Gross profit = 1,887,684 - 1,630,00

Situation 4: Revenue 2018 = [ 630,000/ (630,000 +4,410,000)] x 6,300,000 = $787,500 Gross profit = 787,500-630,000 = $ 157,50

Please rate the answer If like the work

Add a comment
Know the answer?
Add Answer to:
Check my work mode: This shows what is correct or incorrect for the work you have...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • project completion [LO5-9 Brady Construction Company contracted to build an apartment complex for a price of...

    project completion [LO5-9 Brady Construction Company contracted to build an apartment complex for a price of $6.300,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Costs incurred During Year Situation 2018 2019 2020 1 1630 2,520 1.290 2 1.630 1290 2,920 3 1,630 2.520 2.640 4 630 3.130 1.260 5 630 3.130 2.210 6...

  • 5-HW O Exercise 5-21 Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project...

    5-HW O Exercise 5-21 Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project completion (LO5-9) Brady Construction Company contracted to build an apartment complex for a price of $6,300,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Year Estimated costs to Complete Costs incurred During (As of the End of...

  • I just need help with situation 6, the two that are incorrect. thank you! Exercise 5-21...

    I just need help with situation 6, the two that are incorrect. thank you! Exercise 5-21 Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project completion (LO5-9) Brady Construction Company contracted to build an apartment complex for a price of $6,300,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Costs...

  • Exercise 5-21 Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project completion (LO5-9)...

    Exercise 5-21 Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project completion (LO5-9) Brady Construction Company contracted to build an apartment complex for a price of $6,300,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Costs Incurred During Year Situation 2018 2019 2020 1 1,630 2,520 1,290 2 1,630 1,290...

  • Exercise 5-21 Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project completion (LO5-9)...

    Exercise 5-21 Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project completion (LO5-9) Brady Construction Company contracted to build an apartment complex for a price of $6,300,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Costs incurred During Year Situation 2018 2019 2020 1 1,630 2,520 1,290 2 1630 1,290...

  •    Just need help with the four that are incorrect. Thank you! CICLAY WUIHUUU. HIS SUUWS...

       Just need help with the four that are incorrect. Thank you! CICLAY WUIHUUU. HIS SUUWS will is LUMELUI CURELIUI Lie wUIR you dve completed so lol. Il uue HOL Holtate comple Exercise 5-21 Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project completion (LO5-9) Brady Construction Company contracted to build an apartment complex for a price of $6,300,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered...

  • Check my work mode: This shows what is correct or incorrect for the work you have...

    Check my work mode: This shows what is correct or incorrect for the work you have completed so far. It does not Increate completion. Return to question Required information [The following information applies to the questions displayed below.) Part 4 of In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,655 400 Coat incurred...

  • Check my work mode : This shows what is correct or incorrect for the work you...

    Check my work mode : This shows what is correct or incorrect for the work you have completed so far. It does not indicate completion. Return to question 7 Required information [The following information applies to the questions displayed below Duval Co. issues four-year bonds with a $105,000 par value on January 1, 2017, at a price of $100,950. The annual contract 8 points rate is 7%, and interest is paid semiannually on June 30 and December 31. 1. Prepare...

  • Check my work mode : This shows what is correct or incorrect for the work you...

    Check my work mode : This shows what is correct or incorrect for the work you have completed so far. It does not indicate completion. Return to Blooming Flower Company was started in 2018 when it acquired $61,400 cash from the issue of common stock. The following data summarize the company's first three years' operating activities. Assume that all transactions were cash transactions. 2018 $23,900 27,700 11,600 5,420 2019 $10,000 31,200 17,200 8,120 2020 Purchases of inventory $20,000 36,800 18,100...

  • omework Saved Help Save & Exit Submit Check my work Exercise 5-19 Long-term contract; revenue recognition...

    omework Saved Help Save & Exit Submit Check my work Exercise 5-19 Long-term contract; revenue recognition over time; loss projected on entire project [LO5-9] On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,180,000. During 2018, costs of $2,060,000 were incurred with estimated costs of $4,060,000 yet to be incurred. Billings of $2,560,000 were sent, and cash collected was $2,310,000. In 2019, costs incurred were $2,560,000 with remaining...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT