Check my work mode: This shows what is correct or incorrect for the work you have...
Check my work 8 ! Required information [The following information applies to the questions displayed below.] Part 4 of 5 In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 6 points 2023 $2,655,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: $2,655,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,059,000 5.041.000 2,190,000 1,895,000 2022 $2,627,000 2,414,000 2,496,000 2,400,000 5,314,000 5.705.000 Westgate recognizes revenue over time according to percentage of completion 4. Calculate...
Check my work 9 [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: art 5 of 5 2023 $2,655,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,059,000 5,041,000 2,190,000 1,895,000 2022...
What is the revenue and gross profit? Required information (The following information applies to the questions displayed below.) In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: ear-end Cost incurred during the year Estimated costs to complete as o Billings during the year Cash collections during the year 2018 $2,059,000 5,041,000 2,190,000 1,895,000 2019 $2,627,000...
My answers are right!! please help on the 2 blank ones! Required information [The following information applies to the questions displayed below) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,655,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021...
a work mode : This shows what is correct or Incorrect for the work you have completed so far. It does not Indicate completion. Return to question Required Information (The following information applies to the questions displayed below) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,655 400 Cost incurred during the year...
Check my work 5 Required information [The following information applies to the questions displayed below.] Part 1 of 5 In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 6 points Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,059,000 5,041,000 2,190,000...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,059,000 $ 2,627,000 $ 2,655,400 Estimated costs to complete as of year-end 5,041,000 2,414,000 0 Billings during the year 2,190,000 2,496,000 5,314,000 Cash collections during the year 1,895,000 2,400,000 5,705,000 Westgate recognizes revenue over time according to...
pleass help on wrong answers!!! Required information The following information applies to the questions displayed below) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,655,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,059,000 5,041,000 2,190,000 1,895,000 2022 $2,627,000...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,016,000 $ 2,808,000 $ 2,613,600 Estimated costs to complete as of year-end 5,184,000 2,376,000 0 Billings during the year 2,180,000 2,644,000 5,176,000 Cash collections during the...