Question

Check my work 9 [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Comp5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer

  • Requirement 5 asked [Note: in case of this being incorrect, follow the other answer and working provided below]

2021

2022

2023

Revenue

$2,900,000

$2,912,183

$4,187,817

Gross Profit (Loss)

$841,000

($1,085,000)

$105,000

--Working

Working

2021

2022

2023

A

Contract Price

$10,000,000

$10,000,000

$10,000,000

B

Cost Incurred to Date

$2,059,000

$5,954,000

$10,139,000

C

Estimated cost yet to be incurred to complete the contract

$5,041,000

$4,290,000

$0

D = B+C

Total Cost

$7,100,000

$10,244,000

$10,139,000

E = (B/D) x 100

% of Completion

29.00%

58.12%

100.00%

F = A x E

Revenue to date

$2,900,000

$5,812,183

$10,000,000

G

Revenue of Previous year

$0

$2,900,000

$5,812,183

H = F - G

Net Revenue this year

$2,900,000

$2,912,183

$4,187,817

I (=B)

Cost to date

$2,059,000

$5,954,000

$10,139,000

J

Cost to date of previous year

$0

$2,059,000

$5,954,000

K = I - J

Net Cost for the year

$2,059,000

$3,895,000

$4,185,000

L = A - D

Estimated Gross Profit (Loss)

$2,900,000

($244,000)

($139,000)

M

Gross Profit (Loss) to be recognised

$841,000

($1,085,000)

$105,000

  • Requirement 5

2021

2022

2023

Revenue

$2,900,000

$2,912,183

$4,187,817

Gross Profits (Loss)

$841,000

($982,817)

$2,817

Working

2021

2022

2023

A

Contract Price

$10,000,000

$10,000,000

$10,000,000

B

Cost Incurred to Date

$2,059,000

$5,954,000

$10,139,000

C

Estimated cost yet to be incurred to complete the contract

$5,041,000

$4,290,000

$0

D = B+C

Total Cost

$7,100,000

$10,244,000

$10,139,000

E = (B/D) x 100

% of Completion

29.00%

58.12%

100.00%

F = A x E

Revenue to date

$2,900,000

$5,812,183

$10,000,000

G

Revenue of Previous year

$0

$2,900,000

$5,812,183

H = F - G

Net Revenue this year

$2,900,000

$2,912,183

$4,187,817

I (=B)

Cost to date

$2,059,000

$5,954,000

$10,139,000

J

Cost to date of previous year

$0

$2,059,000

$5,954,000

K = I - J

Net Cost for the year

$2,059,000

$3,895,000

$4,185,000

L = H - K

Gross Profits

$841,000

($982,817)

$2,817

Add a comment
Know the answer?
Add Answer to:
Check my work 9 [The following information applies to the questions displayed below.] In 2021, the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Check my work 8 ! Required information [The following information applies to the questions displayed below.]...

    Check my work 8 ! Required information [The following information applies to the questions displayed below.] Part 4 of 5 In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 6 points 2023 $2,655,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021...

  • My answers are right!! please help on the 2 blank ones! Required information [The following information...

    My answers are right!! please help on the 2 blank ones! Required information [The following information applies to the questions displayed below) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,655,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021...

  • Check my work 5 Required information [The following information applies to the questions displayed below.] Part...

    Check my work 5 Required information [The following information applies to the questions displayed below.] Part 1 of 5 In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 6 points Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,059,000 5,041,000 2,190,000...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: $2,655,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,059,000 5.041.000 2,190,000 1,895,000 2022 $2,627,000 2,414,000 2,496,000 2,400,000 5,314,000 5.705.000 Westgate recognizes revenue over time according to percentage of completion 4. Calculate...

  • Check my work mode: This shows what is correct or incorrect for the work you have...

    Check my work mode: This shows what is correct or incorrect for the work you have completed so far. It does not Increate completion. Return to question Required information [The following information applies to the questions displayed below.) Part 4 of In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,655 400 Coat incurred...

  • What is the revenue and gross profit? Required information (The following information applies to the questions...

    What is the revenue and gross profit? Required information (The following information applies to the questions displayed below.) In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: ear-end Cost incurred during the year Estimated costs to complete as o Billings during the year Cash collections during the year 2018 $2,059,000 5,041,000 2,190,000 1,895,000 2019 $2,627,000...

  • Required information (The following information applies to the questions displayed below.) In 2021, the Westgate Construction...

    Required information (The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $ 2,044,000 5, 256,000 2,170,000 1,885,000 2022 2023 $2,628,000 $2,890, 800 2,628,000 2,502,0005...

  • Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,604,000 $ 4,032,000 $ 1,940,400 Estimated costs to complete as of year-end 5,796,000 1,764,000 0 Billings during the year 2,040,000 4,596,000 3,364,000 Cash collections during the...

  • Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,604,000 $ 4,032,000 $ 1,940,400 Estimated costs to complete as of year-end 5,796,000 1,764,000 0 Billings during the year 2,040,000 4,596,000 3,364,000 Cash collections during the...

  • Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,604,000 $ 4,032,000 $ 1,940,400 Estimated costs to complete as of year-end 5,796,000 1,764,000 0 Billings during the year 2,040,000 4,596,000 3,364,000 Cash collections during the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT