Budgeted cost per labor hour 29.28 =193834/6620
Add: Profit margin 37.51
Labor rate 66.79 per hour
2
Material loading charges 11.53% =75867/658000
Add: Profit on parts 80.00%
Material loading percentage 91.53%
3
Labor charges 5209.62 =78*66.79
Materials parts 44300.00
Material loading charges 40547.79 =44300*91.53%
Total estimated bill 90057.41
Add a comment
Know the answer?
Add Answer to:
Exercise M-9 Rey Custom Electronics (RCE) sells and installs complete security, computer, audio, and video systems...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Exercise 22-9 Rey Custom Electronics (RCE) sells and installs complete security, computer, audio, and video systems...

    Exercise 22-9 Rey Custom Electronics (RCE) sells and installs complete security, computer, audio, and video systems for homes. On newly constructed homes it provides bids using time-and-material pricing. The following budgeted cost data are available. Material Loading Charges Technicians' wages and benefits Parts manager's salary and benefits Office employee's salary and benefits Other overhead Total budgeted costs Time Charges $156,789 - 31,858 13,269 $ 201,916 $ 35,000 8,440 46,698 $ 90,138 The company has budgeted for 6,410 hours of technician...

  • accouting question: Question 17 Rey Custom Electronics (RCE) sells and installs complete security, computer, audio, and...

    accouting question: Question 17 Rey Custom Electronics (RCE) sells and installs complete security, computer, audio, and video systems for homes. On newly constructed homes it provides bids using time- and-material pricing. The following budgeted cost data are available. Material Loading Charges Time Charges Technicians' wages and benefits $ 133,653 Parts manager's salary and benefits Office employee's salary and benefits 23,045 Other overhead 15,133 Total budgeted costs $ 171,831 $ 33,200 17,620 43,633 $ 94,453 The company has budgeted for 5,310...

  • Exercise 22-9 Rey Custom Electronics (RCE) sells and installs complete security, computer, audio, and video systems...

    Exercise 22-9 Rey Custom Electronics (RCE) sells and installs complete security, computer, audio, and video systems for homes. On newly constructed homes it provides bids using time-and-material pricing. The following budgeted cost data are available. Material Loading Charges Charges Technicians' wages and benefits Parts manager's salary and benefits Office employee's salary and benefits Other overhead Total budgeted costs 34,700 10,800 15,37337,635 $164,186 83,135 Time 125,642 23,171 The company has budgeted for 5,530 hours of technician time during the coming year....

  • BACK NEXT Exercise 21-09 Rey Custom Electronics (RCE) sells and installs complete security, computer, audio, and...

    BACK NEXT Exercise 21-09 Rey Custom Electronics (RCE) sells and installs complete security, computer, audio, and video systems for homes. On newly constructed homes it provides bids using time-and-material pricing. The following budgeted cost data are available. Material Time Loading Charges Charges Technicians' wages and benefits $100,000 Parts manager's salary and benefits $33,000 Office employee's salary and benefits 20,000 6,000 Other overhead 10,000 39,000 Total budgeted costs $130,000 $78,000 The company has budgeted for 5,000 hours of technician time during...

  • Exercise 8-8 (Video) Second Chance Welding rebuilds spot welders for manufacturers. The following budgeted cost data...

    Exercise 8-8 (Video) Second Chance Welding rebuilds spot welders for manufacturers. The following budgeted cost data for 2020 is available for Second Chance. Time Charges $198,800 Material Loading Charges Technicians' wages and benefits Parts manager's salary and benefits Office employee's salary and benefits Other overhead Total budgeted costs 56,800 7,100 $262,700 $39,800 9,700 28,000 $77,500 - The company desires a $35 profit margin per hour of labor and a 23.00% profit margin on parts. It has budgeted for 7,100 hours...

  • Need help with this question! Exercise 22-8 Second Chance Welding rebuilds spot welders for manufacturers. The...

    Need help with this question! Exercise 22-8 Second Chance Welding rebuilds spot welders for manufacturers. The following budgeted cost data for 2017 is available for Second Chance. Time Charges $266,000 Material Loading Charges Technicians' wages and benefits Parts manager's salary and benefits Office employee's salary and benefits Other overhead Total budgeted costs 45,600 22,800 $334,400 $40,000 10,947 28,210 $79,157 The company desires a $35.00 profit margin per hour of labor and a 26.00% profit margin on parts. It has budgeted...

  • Second Chance Welding rebuilds spot welders for manufacturers. The following budgeted cost data for 2017 is...

    Second Chance Welding rebuilds spot welders for manufacturers. The following budgeted cost data for 2017 is available for Second Chance. Time Charges Material Loading Charges Technicians' wages and benefits $237,000 - Parts manager's salary and benefits - $39,100 Office employee's salary and benefits 71,100 9,169 Other overhead 39,500 19,300 Total budgeted costs $347,600 $67,569 The company desires a $34.00 profit margin per hour of labor and a 21.00% profit margin on parts. It has budgeted for 7,900 hours of repair...

  • Sheridan Welding rebuilds spot welders for manufacturers. The following budgeted cost data for 2020 is available...

    Sheridan Welding rebuilds spot welders for manufacturers. The following budgeted cost data for 2020 is available for Sheridan. Time Charges Material Loading Charges Technicians' wages and benefits $221,200 -        Parts manager's salary and benefits -        $40,200 Office employee's salary and benefits 39,500 6,840 Other overhead 23,700 23,040 Total budgeted costs $284,400 $70,080 The company desires a $37 profit margin per hour of labor and a 20.00% profit margin on parts. It has budgeted for 7,900 hours of repair time in...

  • Second Chance Welding rebuilds spot welders for manufacturers. The following budgeted cost data for 2020 is...

    Second Chance Welding rebuilds spot welders for manufacturers. The following budgeted cost data for 2020 is available for Second Chance. Material Loading Time Charges Charges $192,400 Technicians' wages and benefits $39,600 Parts manager's salary and benefits Office employee's salary and benefits 51,800 9.400 Other overhead 14,800 19,600 Total budgeted costs $259,000 $68.600 The company desires a $39 profit margin per hour of labor and a 27.00% proft margin on parts. It has budgeted for 7,400 hours of repair time in...

  • just e8.9 5.200 24UR The company desin eted for 7.600 hours of repair Total budgeted costs $281.200 $75,500 "pan...

    just e8.9 5.200 24UR The company desin eted for 7.600 hours of repair Total budgeted costs $281.200 $75,500 "pany desires a $30 profit margin per hour of labor and a 20% profit margin on parts. It has budg- Po hours of repair time in the coming year, and estimates that the total invoice cost of parts and materials in 2020 will be $400,000. Instructions a. Compute the rate charged per hour of labor. Compute the material loading percentage. (Round to...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT