Question

Nailed It! Construction (Nailed It! or the “Company”), an SEC registrant, is a construction company that...

Nailed It! Construction (Nailed It! or the “Company”), an SEC registrant, is a construction company that manufactures commercial and residential buildings. On March 1, 20X1, the Company entered into an agreement with a customer, Village Apartments, to construct a residential apartment building for a fixed price of $1.5 million. The Company estimates that it will incur costs of $1 million to complete construction of the apartment building. The apartment building will only transfer to Village Apartments once the construction of the entire building is complete. In addition, Village Apartments has various design requirements that would require Nailed It! to incur significant costs to rework the building prior to selling it to a customer other than Village Apartments. To construct the apartment building, Nailed It! acquires standard materials that it regularly uses in construction contracts for both residential and commercial buildings. These materials are used to manufacture generic component parts for inclusion in Village Apartments’ residential buildings. These standard materials remain interchangeable with other items until they are deployed in a Village Apartments building. The Company has made the following purchases and incurred the following costs throughout the construction progress: • As of June 30, 20X1, in total, Nailed It! has purchased $75,000 of component parts. As of June 30, 20X1, $25,000 of component parts remain in inventory and $50,000 have been integrated into the project. Further, Nailed It! has incurred $12,500 of direct costs to integrate the component parts into the Village Apartments construction project during the three months ended June 30, 20X1. • During the three months ended September 30, 20X1, Nailed It! purchased an additional $500,000 of component parts ($575,000 in total). Of the $575,000 of component parts, $325,000 remain in inventory and $200,000 have been integrated into the project during the three months ended September 30, 20X1. During the three months ended September 30, 20X1, Nailed It! incurred an additional $50,000 of direct costs to integrate the component parts into the Village Apartments construction project. • As of September 30, 20X1, Nailed It! determined that the project was over budget and revised its cost estimate from $1 million to $1.25 million. • As of December 31 20X1, the construction project was completed. During the three months ended December 31, 20X1, Nailed It! purchased an additional $425,000 of generic component parts ($1 million in total). Of the $1 million component parts, $0 remain in inventory and $750,000 were integrated into the project during the three months ended December 31, 20X1. Nailed It! has incurred $187,500 of direct costs to integrate the component parts into the Village Apartments construction project during the three months ended December 31, 20X1. If Village Apartments cancels the contract, Nailed It! will be entitled to reimbursement for costs incurred for work completed to date plus a margin of 20 percent, which is Case 7: Nailed It! Construction Page 2 Copyright 2018 Deloitte Development LLC All Rights Reserved. considered to be a reasonable margin. Nailed It! will not be reimbursed for any materials that have been purchased for use in the contract but have not yet been used and are still controlled by Nailed It!.

Required: 1. Does the performance obligation meet any of the criteria or recognition of revenue over time? 2. How should the entity recognize revenue for the satisfaction of its performance obligation? What amount of revenue should be recognized for the following periods: 2a. The three months ended June 30, 20X1? 2b. The three months ended September 30, 20X1? 2c. The three months ended December 31, 20X1?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

The apartment building will only transfer to Village Apartments once the construction of the entire building is complete. So no revenue will be recognised till the construction of the entire building is complete. The entire revenue will be recognised on 31st December 20X1. No revenue will be recognised in June 20X1 and September 20X1.  

Add a comment
Know the answer?
Add Answer to:
Nailed It! Construction (Nailed It! or the “Company”), an SEC registrant, is a construction company that...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Case 18-3 rev. Nailed It! Construction Nailed It! Construction (Nailed It! or the “Company"), an SEC...

    Case 18-3 rev. Nailed It! Construction Nailed It! Construction (Nailed It! or the “Company"), an SEC registrant, is a construction company that manufactures commercial and residential buildings. On March 1, 20X1, the Company entered into an agreement with a customer, Village Apartments, to construct a residential apartment building for a fixed price of $1.5 million. The Company estimates that it will incur costs of $1 million to complete construction of the apartment building. The apartment building will only transfer to...

  • MULTIPLE-CHOICE questions E1-1.ABC Engineering use cost method to cart engineering use cost method to calculate the...

    MULTIPLE-CHOICE questions E1-1.ABC Engineering use cost method to cart engineering use cost method to calculate the stage of completion of its construction act. Total estimated contract costs of their contract are $100 million. In the first year of their contract, ABC Engineering has incurred the following costs: Cost of purchase of raw materials worth $10 million ($5 million of which are unused by the year end) 2. Payment of salaries and wages of $5 million ($1 million of accrued salaries...

  • In February 2020, Crane Construction signed a contract and commenced construction on a parking garage. The t...

    In February 2020, Crane Construction signed a contract and commenced construction on a parking garage. The total contract price was $89.8 million and was expected to be completed in July 2024 at a total estimated cost of $82.0 million. Payment by the customer was to be made in several stages, based on significant events and dates throughout the construction timeline. The customer was to have control over the parking garage and was able to make major changes to the project...

  • grand construction company was awarded a contact to construct an interchange at the junction of u.s...

    grand construction company was awarded a contact to construct an interchange at the junction of u.s 94 and highway 30 at atotoal contract price of 8000000$. the estimated total cost to complete the project were 6000000$. Cooper Construction Company had a contract starting April 2012, to construct a $9,000,000 building that is expected to be completed in September 2014, at an estimated cost of $8,250,000. At the end of 2012, the costs to date were $3,795,000 and the estimated total...

  • 2. Brady Construction Company contracted to build an apartment complex for a price of $5,000,000. Construction...

    2. Brady Construction Company contracted to build an apartment complex for a price of $5,000,000. Construction began in 2021 and was completed in 2023. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Situation о» от дома Costs Incurred During Year 2021 2022 2023 1,500 2,100 900 1,500 900 2,400 1,500 2,100 1,600 500 3,000 1,000 500 3,000 1,300 500 3,000 1,800 Estimated...

  • Queens Construction Company commences construction of a harbour on 1 July 2020. It signs a fixed-price...

    Queens Construction Company commences construction of a harbour on 1 July 2020. It signs a fixed-price contract for total revenue of $400 million. The project is expected to be completed by the end of June 2023. The expected cost at the commencement of construction was $300 million. The expected costs to complete a construction project can change throughout the project. The following data relates to the project: 2021 2022 2023 ($ M) ($ M) ($ M) Costs for the year...

  • On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its...

    On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The company borrowed $1,500,000 at 10% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2018: $8,000,000, 15% bonds $2,000,000, 10% long-term note Construction expenditures incurred during 2018 were as follows: January 1 $ 660,000 March 31 1,260,000 June 30 872,000 September 30 660,000...

  • On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its...

    On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The company borrowed $1,700,000 at 7% on January 1 to help finance the construction, in addition to the construction loan, Highlands had the following debt outstanding throughout 2018: $7,000,000, 12t bonds $3,000,000, 78 long-term note Construction expenditures incurred during 2018 were as follows: January 1 March 31 June 30 September 30 December 31 $ 740,000 1,340,000...

  • 1) A construction company entered into a fixed-price contract to build an office building for $20...

    1) A construction company entered into a fixed-price contract to build an office building for $20 million. Construction costs incurred during the first year were $6 million and estimated costs to complete at the end of the year were $9 million. The building was completed during the second year. Construction costs incurred during the second year were $10 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes...

  • On January 1, 2016 Walker company began construction of its own building. Construction was completed on...

    On January 1, 2016 Walker company began construction of its own building. Construction was completed on September 30, 2017. Walker incurred the following building construction costs: Payments for Construction 2016 January 1, 2016: $300,000 June 1, 2016: $600,000 October 1, 2016: $800,000 Payments for Construction in 2017 May 1, 2017: $675,000 September 30, 2017: $450,000 Walker had 3 loans outstanding during this entire period from January 1, 2016 through December 31 2017: $500,000 specific construction loan with interest rate of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT