Question

Case 18-3 rev. Nailed It! Construction Nailed It! Construction (Nailed It! or the “Company), an SEC registrant, is a constru
. As of June 30, 20X1, in total, Nailed It! has purchased $75,000 of component parts. As of June 30, 20X1, $25,000 of compone
00 20 Forma B5 ✓ fx А B с D E F H к 1 BRIEFLY EXPLAIN WHY NAILED IT CAN RECOGNIZED REVENU OVER TIME 4 5 ASC paragraphs 6 7 8
ma Cell Formatting as Table Styles 5 x fe А B K M N 0 AS OF: 6/30/X1 9/30/X1 12/31/X1 с D E DOG CONVICTIVE DOTTO QUARTER PURC
0 0
Add a comment Improve this question Transcribed image text
Answer #1

1. As far as the construction contracts are concerned they are usually long term contacts therefore it is prudent to record the revenue on timely basis rather than recording it in one go. It is prudent to allocate the revenue on the basis of some criteria over the period of time considering the percentage of work completed. In case of Nailed it as it seems to be a construction contract whose performance can be analysed at quarterly intervals therefore it is wise to record the revenues, costs and profits over the period of time rather than recording it at one go so that the fluctuation in the costs and prices can be accounted for. Also it is advantageous for nailed it to record revenue over time so that it can accept payment for work done on work completed to date basis periodically.

2. A. Input Method is used to measure the progress.

B. There are two methods of recognizing revenue by measuring progress of completion of contracts:

One is Output method where the progress of the contract is measured by measuring the value transferred to customers. Whereas in Input Method the progress of a contract is measured by the value of materials consumed and the efforts utilized in carrying on the contract work.

In case of Nailed it since the performance of the contract is measured by valuing the components used in the construction and the direct expenses incurred on the project. Therefore, Nailed it is following the Input Method.

3. Keeping in mind the trend of past two quarters, quarter ending June 30,20X1 and September 30, 20X1 it is clearly visible that there are further additional direct costs that are being incurred to integrate the component parts into the village other than the purchase cost of components which will also be incurred in future and will increase the overall project cost. Therfore, Nailed it decided to revise its cost estimate from previous figure of $1 million to $1.25 million.

4. Calculations for revenue to be recognized in each of the 3- Month period:

Fixed price: $

1500000

As of

Cost Incurred

Purchases

Direct Costs

Total cost

Percentage of completion

Quarterly Revenue Recognised

A

B

C=A+B

30.06.2021

            75,000

          12,500

             87,500

87500/1250000*100

7%

           105,000

30.09.2021

          500,000

          50,000

           550,000

550000/1250000*100

44%

           660,000

31.12.2021

          425,000

       187,500

           612,500

612500/1250000*100

49%

           735,000

       1,250,000

       1,500,000

Add a comment
Know the answer?
Add Answer to:
Case 18-3 rev. Nailed It! Construction Nailed It! Construction (Nailed It! or the “Company"), an SEC...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Nailed It! Construction (Nailed It! or the “Company”), an SEC registrant, is a construction company that...

    Nailed It! Construction (Nailed It! or the “Company”), an SEC registrant, is a construction company that manufactures commercial and residential buildings. On March 1, 20X1, the Company entered into an agreement with a customer, Village Apartments, to construct a residential apartment building for a fixed price of $1.5 million. The Company estimates that it will incur costs of $1 million to complete construction of the apartment building. The apartment building will only transfer to Village Apartments once the construction of...

  • 18.A construction company was hired on a construction project to build a building for $1,800,000. The...

    18.A construction company was hired on a construction project to build a building for $1,800,000. The project was begun in 2015 and completed in 2016. Cost and other data are presented below: 2015 2016 Costs incurred during the year $450,000 $1,100,000 Estimated costs to complete 1,050,000 0 Billing during the year 400,000 1,400,000 Cash collections during the year 300,000 1,500,000 Assume that A recognizes revenue on this contract over time according to percentage of completion. Required: Prepare all journal entries...

  • MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 20X1 and...

    MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 20X1 and was completed in 20x2. Information relating to the contract follows: 20x1 20x2 Costs incurred during the year $299,000 $ 150,000 Estimated additional cost to complete 15,000 Billings during the year @, eee 265,000 Cash collections during the year 240, eee 285,000 Required: 1. Record the preceding transactions in MSK's books assuming it recognizes revenue over time and uses costs incurred to measure the extent...

  • Davis Construction company was a low bidder on a construction project to build and earthen dam...

    Davis Construction company was a low bidder on a construction project to build and earthen dam for $2,000,000. The project was begun in 2017. Cost and other are presented bellow. 2017 2018 Costs incurred during the year $450,000 $1,100,000 Total costs 1,050,000 50,000 Percentage of completion 30%   96.875% Billings during the year 500,000 1,400,000 Cash collections during the year 400,000 1,400,000 Assume the Beavis recognizes revenue on the contract over time according to percentage of completion Required 1. Compute the...

  • Saved Help Save & MSK Construction Company contracted to construct a factory building for $525.000. Construction...

    Saved Help Save & MSK Construction Company contracted to construct a factory building for $525.000. Construction started during 20X1 and was completed in 20X2. Information relating to the contract follows: 20x2 $150,000 Costs incurred during the year Estimated additional cost to complete Billings during the year Cash collections during the year 20x1 $290,000 145,000 260,000 240,000 265,000 285,000 Required: 1. Record the preceding transactions in MSK's books assumingit recognizes revenue over time and uses costs incurred to measure the extent...

  • Lance Corp is self constructing a building. Construction began 3/1/19 and ended on 9/30/20. Lance borrowed$1,600,000...

    Lance Corp is self constructing a building. Construction began 3/1/19 and ended on 9/30/20. Lance borrowed$1,600,000 to help finance the project. Lance had other debt of $3million at 6% and $5 million at 9%. Costs on the building were incurred as follows: costs 3/1/2019 600,000.00 7/1/2019 1,200,000 .00 9/30/2019 12/31/2019 3/30/2020 9/30/2020 800,000.00 600,000.00 400,000.00 200,000.00 What is capitalized interest in 2019? What are total construction costs on 12/31/19 What is capitalized interest in 2020? What are total construction costs...

  • Davis Construction company was a low bidder on a construction project to build and earthen dam...

    Davis Construction company was a low bidder on a construction project to build and earthen dam for $2,000,000. The project was begun in 2017. Cost and other are presented bellow. 2017 2018 Costs incurred during the year $450,000 $1,100,000 Total costs 1,050,000 50,000 Percentage of completion 30%   96.875% Billings during the year 500,000 1,400,000 Cash collections during the year 400,000 1,400,000 Assume the Beavis recognizes revenue on the contract over time according to percentage of completion Required 1. Compute the...

  • MULTIPLE-CHOICE questions E1-1.ABC Engineering use cost method to cart engineering use cost method to calculate the...

    MULTIPLE-CHOICE questions E1-1.ABC Engineering use cost method to cart engineering use cost method to calculate the stage of completion of its construction act. Total estimated contract costs of their contract are $100 million. In the first year of their contract, ABC Engineering has incurred the following costs: Cost of purchase of raw materials worth $10 million ($5 million of which are unused by the year end) 2. Payment of salaries and wages of $5 million ($1 million of accrued salaries...

  • 2. Brady Construction Company contracted to build an apartment complex for a price of $5,000,000. Construction...

    2. Brady Construction Company contracted to build an apartment complex for a price of $5,000,000. Construction began in 2021 and was completed in 2023. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Situation о» от дома Costs Incurred During Year 2021 2022 2023 1,500 2,100 900 1,500 900 2,400 1,500 2,100 1,600 500 3,000 1,000 500 3,000 1,300 500 3,000 1,800 Estimated...

  • grand construction company was awarded a contact to construct an interchange at the junction of u.s...

    grand construction company was awarded a contact to construct an interchange at the junction of u.s 94 and highway 30 at atotoal contract price of 8000000$. the estimated total cost to complete the project were 6000000$. Cooper Construction Company had a contract starting April 2012, to construct a $9,000,000 building that is expected to be completed in September 2014, at an estimated cost of $8,250,000. At the end of 2012, the costs to date were $3,795,000 and the estimated total...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT