Consider a project to supply Detroit with 28,000 tons of machine screws annually for automobile production. You will need an initial $5,200,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,250,000 and that variable costs should be $235 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value of $625,000 after dismantling costs. The marketing department estimates that the automakers will let the contract at a selling price of $344 per ton. The engineering department estimates you will need an initial net working capital investment of $500,000. You require a return of 13 percent and face a tax rate of 24 percent on this project.
a-1. What is the estimated OCF for this project? (Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.)
a-2. What is the estimated NPV for this project? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)
b. Suppose you believe that the accounting department’s initial cost and salvage value projections are accurate only to within ±5 percent; the marketing department’s price estimate is accurate only to within ±10 percent; and the engineering department’s net working capital estimate is accurate only to within ±15 percent. What are your worst-case and best-case NPVs for this project? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.)
*Please rate thumbs up
Consider a project to supply Detroit with 28,000 tons of machine screws annually for automobile production....
Consider a project to supply Detroit with 31,000 tons of machine screws annually for automobile production. You will need an initial $6,200,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,500,000 and that variable costs should be $285 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...
Consider a project to supply Detroit with 30,000 tons of machine screws annually for automobile production. You will need an initial $4,600,000 investment in threading equipment to get the project started; the project will last for 3 years. The accounting department estimates that annual fixed costs will be $750,000 and that variable costs should be $410 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 3-year project life. It also estimates a salvage value...
Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $5,300,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $1,275,000 and that variable costs should be $240 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life. It also estimates a salvage value...
Consider a project to supply Detroit with 31,000 tons of machine screws annually for automobile production. You will need an initial $6,200,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,500,000 and that variable costs should be $285 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...
Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production. You will need an initial $4,800,000 investment in threading equipment to get the project started; the project will last for three years. The accounting department estimates that annual fixed costs will be $850,000 and that variable costs should be $250 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the three-year project life. It also estimates a salvage value...
Consider a project to supply Detroit with 30,000 tons of machine screws annually for automobile production. You will need an initial $4.3 million investment in threading equipment to get the project started; the project will last for five years. The accounting department estimates that annual fixed costs will be $1.025 million and that variable costs should be $190 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the five-year project life. It also estimates a...
Consider a project to supply Detroit with 31,000 tons of machine screws annually for automobile production. You will need an initial $6,200,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,500,000 and that variable costs should be $285 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...
Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $4,700,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,125,000 and that variable costs should be $210 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...
Consider a project to supply Detroit with 25,000 tons of machine screws annually for automobile production. You will need an initial $4,500,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,075,000 and that variable costs should be $200 per ton; accounting will depreciate the in itial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage...
Consider a project to supply Detroit with 25,000 tons of machine screws annually for automobile production. You will need an initial $2,200,000 investment in threading equipment to get the project started; the project will last for five years. The accounting department estimates that annual fixed costs will be $700,000 and that variable costs should be $400 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the five-year project life. It also estimates a salvage value...